Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Borrower/Recipient | 10.00 |
P176620
Active
Thomas Flochel , Elisa Portale, Tamaro Kane
Republic of Senegal
June 16, 2021
(as of board presentation)
March 8, 2022
June 1, 2022
US$ 160.00 million
Senegal National Electricity Company (Société Nationale d'Électricité du Sénégal - SENELEC)
2022
US$ 150.00 million
N/A
Substantial
June 30, 2027
TBD
BANK APPROVED
December 7, 2023
Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Borrower/Recipient | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 160.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 14, 2024 | IDA-70470 | Loan Disb | 5,618,374.50 |
Aug 15, 2024 | IDA-70470 | Int Charges | 6,779.56 |
Oct 17, 2023 | IDA-70470 | Loan Disb | 152,030.56 |
Feb 24, 2023 | IDA-70470 | Loan Disb | 162,520.60 |
Jun 20, 2023 | IDA-70470 | Loan Disb | 72,143.35 |
Aug 15, 2023 | IDA-70470 | Int Charges | 160,370.52 |
Oct 17, 2023 | IDA-70470 | Loan Disb | 231.76 |
Jan 17, 2024 | IDA-70470 | Loan Disb | 1,806,102.90 |
Aug 15, 2023 | IDA-70470 | Int Charges | 71,485.03 |
Aug 15, 2023 | IDA-70470 | Int Charges | 15,012.46 |
Feb 15, 2023 | IDA-70470 | Int Charges | 778.84 |
Feb 15, 2023 | IDA-70470 | Int Charges | 174,878.27 |
Feb 15, 2023 | IDA-70470 | Int Charges | 28,876.60 |
Feb 15, 2023 | IDA-70470 | Int Charges | 559.21 |
Aug 15, 2022 | IDA-70470 | Int Charges | 59,705.81 |
Jul 21, 2022 | IDA-70470 | Loan Disb | 3,106,606.00 |
Jul 1, 2022 | IDA-70470 | Fee Charges | 346,346.12 |
Jun 1, 2022 | IDA-70470 | Fee Charges | 107.18 |
Aug 26, 2024 | IDA-70470 | Loan Disb | 1,077,202.40 |
Feb 15, 2024 | IDA-70470 | Int Charges | 27.18 |
May 31, 2024 | IDA-70470 | Loan Disb | 1,922,717.50 |
Jun 7, 2024 | IDA-70470 | Loan Disb | 4,354,490.50 |
May 24, 2024 | IDA-70470 | Loan Disb | 1,265,341.20 |
Jun 5, 2024 | IDA-70470 | Loan Disb | 2,597,707.50 |
Feb 20, 2024 | IDA-70470 | Int Charges | 175,286.69 |
Feb 20, 2024 | IDA-70470 | Int Charges | 423.99 |
Feb 20, 2024 | IDA-70470 | Int Charges | 92,554.24 |
Aug 15, 2024 | IDA-70470 | Int Charges | 362.08 |
Mar 8, 2022 | IDA-70470 | Loan Commitment | 150,000,000.00 |
Aug 15, 2024 | IDA-70470 | Int Charges | 292,787.20 |
Aug 15, 2024 | IDA-70470 | Int Charges | 166,712.48 |
Nov 29, 2023 | IDA-70470 | Loan Disb | 243,468.05 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-10-24 |
Project Management | Moderately Satisfactory | 2024-10-24 |
Financial Management | Moderately Satisfactory | 2024-10-24 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-24 |
Monitoring and Evaluation | Satisfactory | 2024-10-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Of which rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Micro, small and medium-sized enterprises provided with new or improved electricity services | Value | 0.00 | 0.00 | 700.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Female-managed and/or female-owned | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Public institutions provided with new or improved electricity service | Value | 0.00 | 0.00 | 800.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Health clinics | Value | 0.00 | 0.00 | 600.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Schools | Value | 0.00 | 0.00 | 200.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 1580000.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Of which urban | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Least cost geospatial electrification plan developed and adopted by the Universal Access Program Steering Committee | Value | No | No | Yes |
Date | September 1, 2021 | December 7, 2023 | December 31, 2024 | |
Comment |
Lines constructed, reinforced or rehabilitated under the project | Value | 0.00 | 0.00 | 3470.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Adoption of a lifeline connection policy for vulnerable households | Value | No | No | Yes |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Consumer awareness campaign developed and implemented | Value | No | No | Yes |
Date | September 1, 2021 | December 7, 2023 | December 31, 2024 | |
Comment |
Vulnerable households connected to the grid under the project | Value | 0.00 | 0.00 | 40000.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
MV lines constructed, reinforced or rehabilitated under the project | Value | 0.00 | 0.00 | 761.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
People trained in technical, planning, and management areas | Value | 0.00 | 41.00 | 250.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
LV lines constructed, reinforced or rehabilitated under the project | Value | 0.00 | 0.00 | 2709.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Percentage of women in technical positions at SENELEC | Value | 7.40 | 7.00 | 10.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Distribution assets financed under the project are resilient to flooding | Value | 0.00 | 0.00 | 100.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Beneficiaries of a technical assistance promoting productive use of electricity | Value | 0.00 | 0.00 | 200.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Additional distribution transformer capacity installed | Value | 0.00 | 0.00 | 45750.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
of which women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Grievances received and addressed within the project Grievance Mechanism specific timeframe | Value | 0.00 | 0.00 | 100.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Households provided with new electricity service under the project | Value | 0.00 | 0.00 | 200000.00 |
Date | September 1, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |
Overall SENELEC recovery rate | Value | 81.50 | 82.30 | 85.20 |
Date | December 31, 2021 | December 7, 2023 | June 30, 2027 | |
Comment |