Skip to Main Navigation

Kiribati Outer Islands Resilience and Adaptation Project

Abstract*

The development objective of the Outer Islands Resilience and Adaptation Project for Kiribati is to: (i) strengthen the capabilities of island councils for risk-informed land development planning and basic infrastructure and service delivery; and (ii) strengthen the climate resilience of vulnerable communities. The project comprises of three components. The first component, expansion of basic infrastructure and services on outer islands will finance...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to: (i) strengthen the capabilities of island councils for risk-informed land development planning and basic infrastructure and service delivery; and (ii) strengthen the climate resilience of vulnerable communities.

Key Details

Project Details

  • P176702

  • Active

  • Armando Guzman Escobar , Yarissa Sommer

  • Ministry of Finance & Economic Development

  • Kiribati

  • September 28, 2021

  • (as of board presentation)

    May 13, 2022

  • August 15, 2022

  • US$ 20.00 million

  • Ministry of Internal Affairs

  • East Asia and Pacific

  • 2022

  • US$ 20.00 million

  • N/A

  • January 23, 2024

  • August 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 12, 2024 IDA-E0210 Loan Disb 117,356.20
Jul 1, 2024 IDA-E0210 Loan Disb 17,846.51
Jun 27, 2024 IDA-E0210 Loan Disb 41,356.47
Jun 27, 2024 IDA-E0210 Loan Disb 5,429.06
May 28, 2024 IDA-E0210 Loan Disb 104,588.32
Oct 18, 2022 IDA-E0210 Loan Disb 314,800.00
May 13, 2022 IDA-E0210 Loan Commitment 20,000,000.00
Oct 30, 2023 IDA-E0210 Loan Disb 198,306.98
Aug 22, 2024 IDA-E0210 Loan Disb 160,145.83
Apr 9, 2024 IDA-E0210 Loan Disb 199,396.19
Aug 25, 2023 IDA-E0210 Loan Disb 134,359.98
Feb 5, 2024 IDA-E0210 Loan Disb 133,718.30

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-08-14
Project Management Moderately Satisfactory 2024-08-14
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-08-14
Financial Management Satisfactory 2024-08-14
Monitoring and Evaluation Satisfactory 2024-08-14
Procurement Moderately Unsatisfactory 2024-08-14

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries of climate resilience subprojectsValue0.000.0014000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Beneficiaries of climate resilience subprojectsValue0.000.0014000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • New or updated by-laws adopted by local governments that are informed by climate and disaster riskValue0.000.008.00
    DateJune 1, 2022January 22, 2024August 31, 2028
    Comment
  • New or updated by-laws adopted by local governments that are informed by climate and disaster riskValue0.000.008.00
    DateJune 1, 2022January 22, 2024August 31, 2028
    Comment
  • Women beneficiaries of climate resilience subprojectsValue0.000.007000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Women beneficiaries of climate resilience subprojectsValue0.000.007000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • People provided with access to improved water sourcesValue0.000.0010000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • People provided with access to improved water sourcesValue0.000.0010000.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.001000.00
    Date
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.001000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Island Councils with updated physical asset management plans that are fully resourced, designed and implemented for at least 12 monthsValue0.000.004.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Island Councils with updated physical asset management plans that are fully resourced, designed and implemented for at least 12 monthsValue0.000.004.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Issues or complaints raised in the Grievance Redress Mechanism are addressed within 21 calendar daysValue0.00100.0085.00
    DateJune 1, 2022January 22, 2024August 31, 2028
    Comment
  • Issues or complaints raised in the Grievance Redress Mechanism are addressed within 21 calendar daysValue0.00100.0085.00
    DateJune 1, 2022January 22, 2024August 31, 2028
    Comment
  • Island Councils that have adopted climate and disaster risk-informed land development plansValue0.000.0010.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Island Councils that have adopted climate and disaster risk-informed land development plansValue0.000.0010.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Women's participation in Island Council decision-making committees for local service delivery and climate adaptationValue0.000.0030.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Women's participation in Island Council decision-making committees for local service delivery and climate adaptationValue0.000.0030.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Basic subprojects constructed and incorporating agreed climate and disaster resilience measures under the projectValue0.000.0065.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Basic subprojects constructed and incorporating agreed climate and disaster resilience measures under the projectValue0.000.0065.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Island Councils that have prepared applications for competitive subprojects as a result of support from Component 2 activitiesValue0.000.0040.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Island Councils that have prepared applications for competitive subprojects as a result of support from Component 2 activitiesValue0.000.0040.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Women's participation in project-specific training and capacity building activities related to climate change planning and budgetingValue0.0032.0050.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Women's participation in project-specific training and capacity building activities related to climate change planning and budgetingValue0.0032.0050.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Competitive subprojects constructed and incorporating agreed climate and disaster resilience measures under the projectValue0.000.007.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Competitive subprojects constructed and incorporating agreed climate and disaster resilience measures under the projectValue0.000.007.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Beneficiaries who report that project investments reflect their needsValue0.000.0070.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Beneficiaries who report that project investments reflect their needsValue0.000.0070.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Beneficiaries with perceived increase in their resilienceValue0.000.0070.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment
  • Beneficiaries with perceived increase in their resilienceValue0.000.0070.00
    DateAugust 31, 2022January 22, 2024August 31, 2028
    Comment