Khyber Pakhtunkhwa Rural Investment and Institutional Support Project

Abstract*

The project is being implemented under a Multiphase Programmatic Approach (MPA) as an Investment Project Financing (IPF) instrument. Over an eight year period, the proposed MPA will include two phases, focused on key areas that address the most pressing development challenges in the Newly Merged Areas (NMA) of Khyber Pakhtunkhwa, including emergency reconstruction in the first phase related to damages caused by catastrophic 2022 floods. During Phase...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to strengthen state capabilities for delivery of basic services and climate resilient infrastructure in the project areas, including for the poor and vulnerable

Key Details

Project Details

  • P176780

  • Active

  • Robert Wrobel , Mohammad Sami, Akmal Minallah

  • Islamic Republic of Pakistan

  • Pakistan

  • June 8, 2021

  • (as of board presentation)

    June 13, 2023

  • September 6, 2023

  • US$ 400.00 million

  • Agriculture Department,Communication and Works Department,Irrigation Department,Planning and Development Department,Local Government , Elections and Rural Development Department,Public Health Engineering Department

  • South Asia

  • 2023

  • US$ 200.00 million

  • N/A

  • April 1, 2024

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Shorter Maturity Loan (SML) 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 200.00
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 13, 2023 IDA-73480 Loan Commitment 200,000,000.00
Feb 22, 2024 IDA-73480 Loan Disb 560,000.00
Mar 22, 2024 IDA-73480 Loan Disb 500,000.00
Mar 20, 2024 IDA-73480 Loan Disb 3,000,000.00
Mar 28, 2024 IDA-73480 Loan Disb 5,000,000.00
Apr 26, 2024 IDA-73480 Loan Disb 5,030,000.00
Apr 19, 2024 IDA-73480 Loan Disb 3,000,000.00
Jun 20, 2024 IDA-73480 Loan Disb 4,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Village Councils with strengthened capacity for needs-based planningValue0.000.00711.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Village Councils with strengthened capacity for needs-based planningValue0.000.00711.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Beneficiaries that feel critical public service investments meet their needs (percentage, by gender)Value0.000.0085.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Beneficiaries that feel critical public service investments meet their needs (percentage, by gender)Value0.000.0085.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • People with improved access to climate resilient public servicesValue0.000.00200000.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • People with improved access to climate resilient public servicesValue0.000.00200000.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Beneficiaries of climate resilient flood protection infrastructureValue0.000.00100000.00
    DateJune 30, 2023March 8, 2024November 30, 2027
    Comment
  • Beneficiaries of climate resilient flood protection infrastructureValue0.000.00100000.00
    DateJune 30, 2023March 8, 2024November 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land area developed under climate smart agriculture interventionsValue0.000.0020000.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Land area developed under climate smart agriculture interventionsValue0.000.0020000.00
    DateJune 30, 2023March 8, 2024June 30, 2029
    Comment
  • Beneficiary households of village investments that are categorized as poor and vulnerableValue0.000.0035.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Beneficiary households of village investments that are categorized as poor and vulnerableValue0.000.0035.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • District administrative centers established and functionalValue0.000.008.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • District administrative centers established and functionalValue0.000.008.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • Administrative service centers established and operational at sub-district levelValue0.000.0018.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Administrative service centers established and operational at sub-district levelValue0.000.0018.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • People provided with access to improved water sourcesValue0.000.0075000.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • People provided with access to improved water sourcesValue0.000.0075000.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • VC/NC with approved participatory village plansValue0.000.00711.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • VC/NC with approved participatory village plansValue0.000.00711.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • Integrated water resources management and flood protection master plan completedValueNoNoYes
    DateJune 30, 2023March 8, 2024June 30, 2027
    Comment
  • Integrated water resources management and flood protection master plan completedValueNoNoYes
    DateJune 30, 2023March 8, 2024June 30, 2027
    Comment
  • Digital system/dashboard developed to track physical progress and priority results in project areasValueNo formal monitoring system existsNo dashboardProvince-level dashboard will provide a snapshot o
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • Digital system/dashboard developed to track physical progress and priority results in project areasValueNo formal monitoring system existsNo dashboardProvince-level dashboard will provide a snapshot o
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • Women's increased access to safe water sourcesValue0.000.0050.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Women's increased access to safe water sourcesValue0.000.0050.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Village Councils with established women’s committeesValue0.000.0050.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Village Councils with established women’s committeesValue0.000.0050.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Flood protection investments reflecting climate resilient designsValue0.000.003.00
    DateJune 30, 2023March 8, 2024June 30, 2027
    Comment
  • Flood protection investments reflecting climate resilient designsValue0.000.003.00
    DateJune 30, 2023March 8, 2024June 30, 2027
    Comment
  • Three-tier Grievance Redressal Mechanism established for project areas (Text)ValueNo functional project specific GRM in placeInterim GRM establishedGRM operational including at the lowest tier of ad
    DateMarch 1, 2023March 29, 2024June 29, 2029
    Comment
  • Three-tier Grievance Redressal Mechanism established for project areas (Text)ValueNo functional project specific GRM in placeInterim GRM establishedGRM operational including at the lowest tier of ad
    DateMarch 1, 2023March 29, 2024June 29, 2029
    Comment
  • Rural roads rehabilitated to climate resilient standardsValue0.000.0075.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Rural roads rehabilitated to climate resilient standardsValue0.000.0075.00
    DateJune 30, 2023March 8, 2024June 29, 2029
    Comment
  • Sub-projects at VC level that finance women's prioritiesValue0.000.0050.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment
  • Sub-projects at VC level that finance women's prioritiesValue0.000.0050.00
    DateMarch 1, 2023March 8, 2024June 29, 2029
    Comment