Financier | Commitments |
---|---|
IDA Credit | 200.00 |
P176786
Active
Olivier Durand , Francois Onimus
Islamic Republic of Pakistan
February 7, 2022
(as of board presentation)
July 15, 2022
November 4, 2022
US$ 262.00 million
Government of Punjab, Agriculture Department
2023
US$ 200.00 million
N/A
November 22, 2023
June 30, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 262.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2024 | IDA-71640 | Int Charges | 227,198.83 |
Aug 15, 2023 | IDA-71640 | Int Charges | 9,045.75 |
Jul 15, 2022 | IDA-71640 | Loan Commitment | 200,000,000.00 |
Feb 15, 2024 | IDA-71640 | Int Charges | 227,198.83 |
Jul 31, 2024 | IDA-71640 | Loan Disb | 21,000,000.00 |
Jul 29, 2024 | IDA-71640 | Loan Disb | 5,000,000.00 |
Aug 15, 2023 | IDA-71640 | Int Charges | 15,076.25 |
Nov 3, 2023 | IDA-71640 | Loan Disb | 12,000,000.00 |
Feb 15, 2024 | IDA-71640 | Int Charges | 20,542.42 |
Aug 15, 2023 | IDA-71640 | Int Charges | 132,337.53 |
Aug 15, 2023 | IDA-71640 | Int Charges | 91,816.76 |
Aug 15, 2023 | IDA-71640 | Int Charges | 91,816.76 |
Jul 24, 2023 | IDA-71640 | Loan Disb | 2,000,000.00 |
Jan 23, 2023 | IDA-71640 | Loan Disb | 20,000,000.00 |
Mar 7, 2023 | IDA-71640 | Loan Disb | 3,000,000.00 |
Dec 1, 2023 | IDA-71640 | Loan Disb | 10,000,000.00 |
Dec 1, 2023 | IDA-71640 | Loan Disb | 5,000,000.00 |
Jul 26, 2023 | IDA-71640 | Loan Disb | 18,000,000.00 |
Aug 15, 2023 | IDA-71640 | Int Charges | 9,045.75 |
Aug 15, 2024 | IDA-71640 | Int Charges | 296,150.53 |
Aug 15, 2024 | IDA-71640 | Int Charges | 296,150.53 |
Aug 15, 2024 | IDA-71640 | Int Charges | 473,276.75 |
Aug 15, 2024 | IDA-71640 | Int Charges | 8,509.48 |
Aug 15, 2024 | IDA-71640 | Int Charges | 8,509.48 |
Oct 26, 2023 | IDA-71640 | Loan Disb | 8,810,000.00 |
Feb 15, 2024 | IDA-71640 | Int Charges | 378,664.72 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-26 |
Project Management | Satisfactory | 2024-12-26 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-26 |
Procurement | Satisfactory | 2024-12-26 |
Financial Management | Satisfactory | 2024-12-26 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in agriculture incomes of HHs participating in project activities | Value | 0.00 | 0.00 | 20.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increased agricultural output per unit of water used at farm level (kilograms/cubic meter) for wheat | Value | 0.00 | 0.00 | 15.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Direct beneficiaries reached | Value | 0.00 | 250932.00 | 1330000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Reduction of the differences in water availability among head, middle, and tail end users of watercourses | Value | 0.00 | 0.00 | 40.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in agriculture incomes of FHHs participating in project activities | Value | 0.00 | 0.00 | 25.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increased agricultural output per unit of water used at farm level (kilograms/cubic meter) for rice | Value | 0.00 | 0.00 | 20.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
of which female beneficiaries | Value | 0.00 | 0.00 | 40.00 |
Date | ||||
Comment |
Increased share of area under HVC cultivation | Value | 0.00 | 0.00 | 30.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
OFWM workers, private sector, and service providers that have been trained | Value | 0.00 | 630.00 | 6000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
PA proposals approved for financing | Value | 0.00 | 0.00 | 330.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Area provided with new/improved irrigation or drainage services | Value | 0.00 | 133127.00 | 559000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Command area of watercourses improved/reconstructed, and of water conveyance schemes improved | Value | 0.00 | 132277.00 | 543000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
of which PA proposals approved for female-headed FEGs | Value | 0.00 | 0.00 | 10.00 |
Date | ||||
Comment |
of which female beneficiaries | Value | 0.00 | 0.00 | 25.00 |
Date | ||||
Comment |
Project beneficiaries satisfied with project | Value | 0.00 | 0.00 | 85.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Area equipped HEIS | Value | 0.00 | 850.00 | 16000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in marketed value through PAs in project areas | Value | 0.00 | 0.00 | 30.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Watercourses improved | Value | 0.00 | 1329.00 | 7000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
New watercourses improved | Value | 0.00 | 0.00 | 150.00 |
Date | ||||
Comment |
Watercourses partially improved | Value | 0.00 | 0.00 | 300.00 |
Date | ||||
Comment |
Watercourses reconstructed | Value | 0.00 | 0.00 | 150.00 |
Date | ||||
Comment |
Improved irrigation conveyance schemes completed outside canal command area | Value | 0.00 | 0.00 | 450.00 |
Date | ||||
Comment |
Reduction in water conveyance losses in watercourses | Value | 0.00 | 0.00 | 20.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in cropping intensity in project areas | Value | 140.00 | 0.00 | 165.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in yield of major crops | Value | 0.00 | 0.00 | 10.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in yield of orchards | Value | 0.00 | 0.00 | 25.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Increase in yield of vegetables | Value | 0.00 | 0.00 | 25.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Watercourses with water accounting and budgeting established and monitored | Value | 0.00 | 0.00 | 72.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
Farmers adopted CSA and water management practice | Value | 0.00 | 0.00 | 30000.00 |
Date | May 25, 2022 | October 30, 2023 | June 30, 2027 | |
Comment |
of which female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |