Financier | Commitments |
---|---|
IDA Credit | 300.00 |
P176811
Active
Vincent Vesin , Alphonse Soh
Republic of Madagascar
May 19, 2021
(as of board presentation)
June 29, 2021
November 17, 2021
US$ 200.00 million
Road Agency,Ministry of Public Works
2021
US$ 300.00 million
N/A
June 3, 2024
September 30, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 25, 2024 | IDA-69520 | Loan Disb | 7,500,000.00 |
Jun 27, 2024 | IDA-69520 | Loan Disb | 1,823,321.20 |
Apr 17, 2023 | IDA-69520 | Loan Disb | 1,325,184.00 |
Mar 7, 2023 | IDA-69520 | Loan Disb | 1,957,712.00 |
Apr 25, 2023 | IDA-69520 | Loan Disb | 5,457,264.50 |
Mar 8, 2023 | IDA-69520 | Loan Disb | 815,673.94 |
Apr 7, 2023 | IDA-69520 | Loan Disb | 332,632.38 |
Oct 5, 2022 | IDA-69520 | Loan Disb | 96,102.15 |
Nov 22, 2022 | IDA-69520 | Loan Disb | 50,635.13 |
Jul 29, 2022 | IDA-69520 | Loan Disb | 189,664.14 |
Aug 15, 2022 | IDA-69520 | Int Charges | 23,467.36 |
Aug 15, 2022 | IDA-69520 | Int Charges | 23,467.36 |
Mar 9, 2022 | IDA-69520 | Loan Disb | 7,500,000.00 |
Jun 28, 2022 | IDA-69520 | Loan Disb | 30,400,000.00 |
Jun 29, 2022 | IDA-69520 | Loan Disb | 25,368.67 |
Jun 16, 2023 | IDA-69520 | Loan Disb | 175,646.84 |
Jun 16, 2023 | IDA-69520 | Loan Disb | 307,653.56 |
Aug 4, 2023 | IDA-69520 | Loan Disb | 1,237,087.90 |
Aug 4, 2023 | IDA-69520 | Loan Disb | 5,282,877.00 |
Jun 14, 2023 | IDA-69520 | Loan Disb | 4,360,293.00 |
Jun 14, 2023 | IDA-69520 | Loan Disb | 30,000,000.00 |
Jun 15, 2023 | IDA-69520 | Loan Disb | 346,910.80 |
Aug 16, 2023 | IDA-69520 | Int Charges | 402.19 |
Aug 16, 2023 | IDA-69520 | Int Charges | 402.19 |
Aug 16, 2023 | IDA-69520 | Int Charges | 213,986.80 |
Aug 16, 2023 | IDA-69520 | Int Charges | 213,986.80 |
Sep 20, 2023 | IDA-69520 | Loan Disb | 5,991,019.50 |
Jul 28, 2023 | IDA-69520 | Loan Disb | 223,547.78 |
Mar 14, 2023 | IDA-69520 | Loan Disb | 1,293,568.80 |
Feb 28, 2023 | IDA-69520 | Loan Disb | 98,331.28 |
Feb 21, 2023 | IDA-69520 | Int Charges | 29,598.18 |
Feb 21, 2023 | IDA-69520 | Int Charges | 29,598.18 |
Feb 21, 2023 | IDA-69520 | Int Charges | 141,685.20 |
Feb 21, 2023 | IDA-69520 | Int Charges | 141,685.20 |
Mar 20, 2023 | IDA-69520 | Loan Disb | -1,290,608.60 |
Apr 15, 2024 | IDA-69520 | Loan Disb | 2,602,395.20 |
Aug 20, 2024 | IDA-69520 | Int Charges | 377,464.94 |
Aug 20, 2024 | IDA-69520 | Int Charges | 377,464.94 |
Aug 15, 2024 | IDA-69520 | Int Charges | 4,559.99 |
Aug 15, 2024 | IDA-69520 | Int Charges | 4,559.99 |
Jun 26, 2023 | IDA-69520 | Loan Disb | 370,165.75 |
May 25, 2023 | IDA-69520 | Loan Disb | 1,064,695.80 |
Jun 30, 2023 | IDA-69520 | Loan Disb | 3,524,891.00 |
Jul 2, 2024 | IDA-69520 | Loan Disb | 905,899.90 |
Mar 13, 2024 | IDA-69520 | Loan Disb | 665,932.56 |
Jun 29, 2021 | IDA-69520 | Loan Commitment | 200,000,000.00 |
Sep 27, 2022 | IDA-72140 | Loan Commitment | 100,000,000.00 |
Feb 16, 2024 | IDA-69520 | Int Charges | 371,068.60 |
Feb 16, 2024 | IDA-69520 | Int Charges | 371,068.60 |
Feb 16, 2024 | IDA-69520 | Int Charges | 5,780.78 |
Feb 16, 2024 | IDA-69520 | Int Charges | 5,780.78 |
Jul 15, 2024 | IDA-69520 | Loan Disb | 1,099,118.50 |
Jul 15, 2024 | IDA-69520 | Loan Disb | 1,163,822.10 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2025-03-14 |
Progress towards achievement of PDO | Satisfactory | 2025-03-14 |
Project Management | Moderately Satisfactory | 2025-03-14 |
Monitoring and Evaluation | Satisfactory | 2025-03-14 |
Financial Management | Moderately Satisfactory | 2025-03-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-14 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People with enhanced access to transportation services | Value | 0.00 | 375000.00 | 2488000.00 |
Date | December 31, 2021 | April 17, 2024 | December 31, 2027 | |
Comment |
Additional national paved roads in good or excellent condition | Value | 0.00 | 0.00 | 20.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
National paved roads with safe and more climate-resilient features | Value | 0.00 | 0.00 | 20.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Main infrastructure restored to good condition following national emergency | Value | 0.00 | 10.00 | 8.00 |
Date | July 14, 2022 | April 17, 2024 | September 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Maintained, climate resilient, and safer roads | Value | 0.00 | 0.00 | 1200.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Lead road safety agency established | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
km of cyclone damaged main roads restored | Value | 0.00 | 41.50 | 210.00 |
Date | September 1, 2022 | April 17, 2024 | September 30, 2027 | |
Comment |
Road Fund financing strategy adopted & implemented | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
number of cyclone damaged railway bridges restored | Value | 0.00 | 2.00 | 2.00 |
Date | September 30, 2022 | April 17, 2024 | September 30, 2027 | |
Comment |
Road Safety Audits on 1200 km | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
km of cyclone damaged electricity distribution lines restored | Value | 0.00 | 4.00 | 700.00 |
Date | September 30, 2022 | April 17, 2024 | September 30, 2027 | |
Comment |
Transfer of full responsibility of the primary road network to Road Agency | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Number of cyclone damaged electricity poles replaced | Value | 0.00 | 7000.00 | 32000.00 |
Date | September 30, 2022 | April 17, 2024 | September 30, 2027 | |
Comment |
National standard bidding documents for performance-based contracts developed and implemented. | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
National standard bidding documents for road maintenance and construction updated with new climate resilience standards | Value | No | Yes | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Number of GBV and HIV/AIDS awareness-raising campaigns carried out in the project areas | Value | 0.00 | 3.00 | 20.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Percentage of grievances recorded and processed as per the project's GRM | Value | 0.00 | 100.00 | 100.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Share of construction workers that have signed the Code of Conduct | Value | 0.00 | 100.00 | 100.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Study assessing barriers for women in road construction sector. | Value | No | No | Yes |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |
Percentage of women working in road maintenance in the project. | Value | 0.00 | 0.00 | 10.00 |
Date | September 30, 2021 | April 17, 2024 | September 30, 2027 | |
Comment |