Skip to Main Navigation

Togo Public Sector Strengthening for Service Delivery Operation

Abstract*

The proposed Investment Project Financing (IPF) component will support the PforR operation, which is the first of its kind in Togo. As such, it is necessary to support the Government with complementary Technical Assistance (TA) in the form of an IPF component that will continue to strengthen the Government’s capacity and provide specialized support and high-level technical expertise for the implementation of the Program’s results areas: (i) strengthening...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PforR development objective is to enhance human resource and public expenditure management.

Key Details

Project Details

  • P176883

  • Active

  • Ibrahim El ghandour , Lorena Vinuela, Emeline Bredy

  • Government of the Republic of Togo

  • Togo

  • September 19, 2023

  • (as of board presentation)

    May 23, 2024

  • October 3, 2024

  • US$ 65.00 million

  • Ministry of Economy and Finance,Ministry of Civil Service, Labor, and Social Dialogue,President's Office of the Republic of Togo

  • Western and Central Africa

  • 2024

  • US$ 75.00 million

  • N/A

  • February 1, 2024

  • June 30, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 7.00
Borrower/Recipient 298.00
IDA Shorter Maturity Loan (SML) 68.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 75.00
IBRD + IDA Commitment 75.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 65.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 23, 2024 IDA-75570 Loan Commitment 7,000,000.00
May 23, 2024 IDA-75560 Loan Commitment 68,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-03-31
Monitoring and Evaluation Satisfactory 2025-03-31
Overall Implementation Progress (IP) Satisfactory 2025-03-31

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Women appointed to key senior and technical positions trained in Civil Service Excellence ProgramValue0.000.0010.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Civil servants appointed to senior and key technical positions trained through Civil Service Excellence ProgramValue0.000.0010.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Tax revenue collected digitallyValue19.000.0095.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Gender-focused expenditure increaseValue0.000.0020.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Digital Government to Person paymentsValue70.000.0096.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Deviation in outturn of education and health expenditureValue25.000.005.00
    DateDecember 31, 2021December 31, 2029
    Comment
  • Climate change mitigation and adaptation expenditure increaseValue0.000.0020.00
    DateDecember 31, 2021December 31, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reports on joint sectoral action plans (education and health) , developed with inputs from citizens dialogues, and publishedValue0.000.004.00
    DateDecember 31, 2021December 31, 2028
    Comment
  • Strategy to improve recruitment and retention of women in the Civil Service adoptedValueNoYes
    DateDecember 31, 2021December 31, 2028
    Comment
  • Increase in procured goods and service value following green procurement guidelinesValue0.000.0020.00
    DateDecember 31, 2021December 31, 2028
    Comment
  • Procured goods and services value contracted through the e-procurement online platformValue0.000.0070.00
    DateDecember 31, 2021December 31, 2028
    Comment
  • Budget tagging design and practice and reference manual to track gender expenditure adoptedValueNoYes
    DateDecember 31, 2021December 31, 2028
    Comment
  • Budget tagging design and reference and practice manual to track climate mitigation and adaptation expenditure adoptedValueNoYes
    DateDecember 31, 2021December 31, 2028
    Comment
  • Climate filter informing the screening of public investment projects above US$ 2 million implementedValueNoYes
    DateDecember 31, 2021December 31, 2028
    Comment