Togo Urban Water Security (TUWS)

Abstract*

The development objectives of the Urban Water Security Project for Togo are to increase access to and quality of water supply and sanitation services, and to improve the operational performance of the water supply services provider(s) and water resources management in Greater Lomé. The project comprises of six components. The first component, improving urban water supply services will aim to improve access to improved water supply services in Greater...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives (PDO) are to increase access to and quality of water supply and sanitation services, and to improve the operational performance of the water supply services provider(s) and water resources management in Greater Lomé.

Key Details

Project Details

  • P176902

  • Active

  • Stephane Dahan , Yeli Dakoure Sou

  • Republic of Togo

  • Togo

  • April 14, 2022

  • (as of board presentation)

    March 29, 2023

  • August 10, 2023

  • US$ 100.00 million

  • Ministry of Water and Village Hydraulics

  • Western And Central Africa

  • 2023

  • US$ 100.00 million

  • N/A

  • January 18, 2024

  • March 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 55.70
IDA Shorter Maturity Loan (SML) 44.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 2023 IDA-72750 Loan Commitment 44,300,000.00
Mar 29, 2023 IDA-72760 Loan Commitment 55,700,000.00
Jan 19, 2024 IDA-72760 Loan Disb 107,278.66
May 29, 2024 IDA-72760 Loan Disb 72,317.63
Jun 17, 2024 IDA-72760 Loan Disb 79,913.39
Sep 3, 2024 IDA-72760 Loan Disb 59,299.09
Nov 29, 2023 IDA-72760 Loan Disb 209,331.56
Aug 10, 2023 IDA-72760 Loan Disb 419,103.20
Aug 12, 2024 IDA-72760 Loan Disb 92,931.96
Mar 27, 2024 IDA-72760 Loan Disb 85,247.53
Mar 14, 2024 IDA-72760 Loan Disb 1,000,629.60
Jun 28, 2024 IDA-72760 Loan Disb 2,896,066.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-11-08
Progress towards achievement of PDO Satisfactory 2024-11-08
Financial Management Moderately Satisfactory 2024-11-08
Monitoring and Evaluation Satisfactory 2024-11-08
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-08
Project Management Moderately Satisfactory 2024-11-08

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Schools and health center facilities supplied with WASH servicesValue0.000.00110.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • People provided with access to improved water sources through piped household water connectionsValue0.000.00200000.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Reduction in non-revenue water leading to reduced energy intensity of water supplyValue40.0040.0020.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Share of TdE customers in Greater Lomé provided with continuous water supply servicesValue0.000.0080.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Volume of fecal sludge treated per international standardsValue0.000.00800.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Improved management of water resources used for Greater Lomé’s collective water supplyValue0.000.000.75
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Of which womenValue0.000.0099400.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • District metered areas (DMAs) createdValue0.000.0025.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • TdE's groundwatrer production capacity in Lomé benefiting from enhanced protection measures against flooding risksValue0.000.0070.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Schools and health center facilities supplied with menstrual hygiene health (MHH)-friendly water, sanitation, and hygiene (WASH) servicesValue0.000.0070.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • New storage capacity constructedValue0.000.008000.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Collection ratioValue0.860.860.95
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Water resources geographic information system established and operationalValueNoNoYes
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Accredited emptiers discharging their trucks at the septage treatment facilityValue0.000.0040.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • People benefiting from water supply system rehabilitation or expansion under the ProjectValue0.000.00950000.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Share of complainants assessing that their past grievances to TdE have been addressed satisfactorily and within the project GRM time frame, this figure being disclosed publicly by TdEValue0.000.0075.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Girls in schools where the Project supports WASH facilities who attest attending school during menstrual period as the facilities offer them an enabling environment to continue to study.Value0.000.001400.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Reduction in physical lossesValue30.0030.0015.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • TdE's audit committee established, adequately staffed and fully functioningValueNoNoYes
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment
  • Water network created and rehabilitatedValue0.000.00200.00
    DateMarch 28, 2023December 22, 2023March 30, 2029
    Comment