Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 2.00 |
IDA Credit | 40.00 |
P176943
Active
Jared Mercadante
St. Vincent and the Grenadines
September 23, 2021
(as of board presentation)
November 30, 2021
December 10, 2021
US$ 42.00 million
Ministry of Finance, Economic Planning, and Information Technology
2022
US$ 42.00 million
N/A
January 10, 2024
December 30, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 2.00 |
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | 2.00 |
Total Project Cost** | 42.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 9, 2024 | IDA-70060 | Loan Disb | 656,852.10 |
Jun 3, 2024 | IDA-70060 | Loan Disb | 1,239,633.50 |
May 15, 2023 | IDA-70060 | Int Charges | 84,301.40 |
Nov 15, 2023 | IDA-70060 | Int Charges | 104,099.04 |
Nov 15, 2023 | IDA-70060 | Int Charges | 104,099.04 |
Aug 3, 2023 | IDA-70060 | Loan Disb | 4,753,336.00 |
Mar 31, 2022 | IDA-70060 | Loan Disb | 3,816,098.00 |
Jul 25, 2022 | IDA-70060 | Loan Disb | 7,653,480.50 |
Nov 15, 2022 | IDA-70060 | Int Charges | 62,425.21 |
Nov 15, 2022 | IDA-70060 | Int Charges | 62,425.21 |
Nov 15, 2022 | IDA-70060 | Int Charges | 7,012.08 |
Nov 15, 2022 | IDA-70060 | Int Charges | 7,012.08 |
May 15, 2024 | IDA-70060 | Int Charges | 119,238.42 |
May 15, 2024 | IDA-70060 | Int Charges | 119,238.42 |
Nov 30, 2021 | IDA-70060 | Loan Commitment | 40,000,000.00 |
May 15, 2023 | IDA-70060 | Int Charges | 84,301.40 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-10-18 |
Financial Management | Satisfactory | 2024-10-18 |
Progress towards achievement of PDO | Satisfactory | 2024-10-18 |
Monitoring and Evaluation | Satisfactory | 2024-10-18 |
Overall Implementation Progress (IP) | Satisfactory | 2024-10-18 |
Procurement | Moderately Satisfactory | 2024-10-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of households impacted by the volcanic eruption and climate-related events, benefiting from short-term income support program (number; disaggregated by gender) | Value | 0.00 | 4030.00 | 4000.00 |
Date | August 2, 2021 | October 17, 2023 | December 30, 2022 | |
Comment |
of which are women (Percentage) | Value | 0.00 | 63.00 | 55.00 |
Date | August 2, 2021 | October 17, 2023 | December 30, 2022 | |
Comment |
Number of people benefiting from restored utility/infrastructure services (number; disaggregated by gender) | Value | 0.00 | 0.00 | 15000.00 |
Date | August 2, 2021 | October 17, 2023 | August 3, 2026 | |
Comment |
of which are women (Percentage) | Value | 0.00 | 0.00 | 40.00 |
Date | August 2, 2021 | October 17, 2023 | August 3, 2026 | |
Comment |
The GoSVG has improved command and control systems in place | Value | No | No | Yes |
Date | August 2, 2021 | October 17, 2023 | August 5, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Households provided with support services to enhance household’s self-agency | Value | 0.00 | 623.00 | 750.00 |
Date | August 2, 2021 | October 17, 2023 | December 30, 2022 | |
Comment |
Water systems rehabilitation and/or augmented, in accordance with climate and disaster resilient improvements and practices with operational capacity restored. | Value | 0.00 | 0.00 | 1.00 |
Date | August 2, 2021 | October 17, 2023 | August 5, 2025 | |
Comment |
Grievances responded to in the stipulated time | Value | 0.00 | 60.00 | 60.00 |
Date | August 2, 2021 | October 17, 2023 | August 3, 2026 | |
Comment |
Government has improved command and control systems in place to better prepare for and respond to emergencies such as volcanic eruption, as well as climate change-related disasters such as hurricanes | Value | No | No | Yes |
Date | August 2, 2021 | October 17, 2023 | August 4, 2025 | |
Comment |
Beneficiary satisfaction with project’s stakeholder engagement process | Value | 0.00 | 0.00 | 60.00 |
Date | November 30, 2021 | October 17, 2023 | November 30, 2026 | |
Comment |
Of which are women (Percentage) | Value | 0.00 | 83.50 | 55.00 |
Date | August 2, 2021 | October 17, 2023 | December 30, 2022 | |
Comment |
Households receiving temporary grants | Value | 0.00 | 4030.00 | 4000.00 |
Date | August 2, 2021 | October 17, 2023 | December 30, 2022 | |
Comment |
Public buildings repaired in accordance with volcanic eruption risk and climate and disaster-resilient improvements | Value | 0.00 | 0.00 | 5.00 |
Date | August 2, 2021 | October 17, 2023 | August 4, 2025 | |
Comment |
of which are women (Percentage) | Value | 0.00 | 0.00 | 50.00 |
Date | November 30, 2021 | October 17, 2023 | November 30, 2026 | |
Comment |
Of which are women (Percentage) | Value | 0.00 | 63.00 | 55.00 |
Date | August 2, 2021 | October 17, 2023 | August 1, 2022 | |
Comment |
Women economically benefiting from project investments in agriculture in impacted areas (% increase of the women economically benefiting from agriculture investments). | Value | 0.00 | 0.00 | 55.00 |
Date | November 1, 2021 | October 17, 2023 | August 5, 2025 | |
Comment |
Implement project activities at the community level, with women included in decision making processes. | Value | No | Yes | Yes |
Date | August 2, 2021 | October 17, 2023 | August 4, 2023 | |
Comment |
Number of bridges rehabilitated or protected | Value | 0.00 | 0.00 | 1.00 |
Date | November 1, 2021 | October 17, 2023 | November 28, 2025 | |
Comment |
Volcanic ash, debris and floodwater cleared following the volcanic eruption and/or climate-related events (in critical spots/segments, houses, and public buildings) | Value | 0.00 | 30.00 | 30.00 |
Date | November 30, 2021 | October 17, 2023 | August 5, 2026 | |
Comment |
Number of critical spots/segments built or rehabilitated | Value | 0.00 | 2.00 | 25.00 |
Date | November 5, 2021 | October 17, 2023 | November 28, 2025 | |
Comment |