Enhancing Connectivity in Northern Guinea-Bissau Project

Abstract*

The development objective of the Enhancing Connectivity in Northern Guinea-Bissau Project for Guinea-Bissau is to provide efficient, safe, and climate resilient road connectivity on selected sections of the Safim-Mpak corridor in the northern part of the Recipient's territory. The project comprises of four components. The first component, transport infrastructure improvement will finance the rehabilitation and upgrade of priority road sections of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide efficient, safe, and climate resilient road connectivity on selected sections of the Safim-Mpak corridor in the northern part of the Recipient's territory.

Key Details

Project Details

  • P176948

  • Active

  • Philippe Neves , Nabil Samir

  • Republic of Guinea-Bissau

  • Guinea-Bissau

  • November 1, 2021

  • (as of board presentation)

    June 15, 2022

  • September 26, 2022

  • US$ 70.30 million

  • Ministry of Public Works, Housing, and Urban Planning

  • Western and Central Africa

  • 2022

  • US$ 84.70 million

  • N/A

  • Substantial

  • November 30, 2029

  • Yes

  • BANK APPROVED

  • April 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.30
IDA Grant 84.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 84.70
IBRD + IDA Commitment 84.70
Lending Instrument
Grant Amount N/A
Total Project Cost** 70.30

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 20, 2022 IDA-E0750 Loan Disb 29,782.84
Oct 17, 2022 IDA-E0750 Loan Disb 1,481,657.10
Sep 26, 2022 IDA-E0750 Loan Disb 346,727.03
Jan 30, 2023 IDA-E0750 Loan Disb 5,019.25
Apr 28, 2023 IDA-E0750 Loan Disb 8,867.03
Apr 28, 2023 IDA-E0750 Loan Disb 237,892.77
Apr 17, 2024 IDA-E0750 Loan Disb 48,090.81
Jul 1, 2024 IDA-E0750 Loan Disb 68,613.76
Jul 11, 2024 IDA-E0750 Loan Disb 13,683.63
Feb 21, 2024 IDA-E0750 Loan Disb 29,024.13
Jan 19, 2024 IDA-E0750 Loan Disb 5,138.03
Mar 26, 2024 IDA-E0750 Loan Disb 204,726.06
May 24, 2024 IDA-E0750 Loan Disb 8,751.96
Jun 15, 2022 IDA-E0750 Loan Commitment 70,000,000.00
Dec 21, 2023 IDA-E0750 Loan Disb 39,464.93
Sep 1, 2023 IDA-E0750 Loan Disb 4,262.47
Dec 1, 2023 IDA-E0750 Loan Disb 13,788.96
May 24, 2023 IDA-E0750 Loan Disb 33,747.93
Aug 20, 2024 IDA-E0750 Loan Disb 206,594.89
Jul 11, 2023 IDA-E0750 Loan Disb 391,906.25
Feb 24, 2023 IDA-E0750 Loan Disb 244,612.86

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-03-13
Monitoring and Evaluation Satisfactory 2025-03-13
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-13
Procurement Moderately Unsatisfactory 2025-03-13
Project Management Satisfactory 2025-03-13
Financial Management Satisfactory 2025-03-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in travel time along the rehabilitated road sectionsValue0.000.0030.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Project rehabilitated road sections achieving minimum 3-star safe infrastructure rating for all road usersValueto be determined0100%
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Length of road rehabilitated incorporating climate resilience measuresValue0.000.0050.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Direct beneficiaries with enhanced access to road transport – number of daily road usersValue0.000.004500.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Indirect beneficiaries with enhanced access to road transport – number of people living near the project roadValue0.000.0020000.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehablitatedValue0.000.0050.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Grievances responded and/or resolved within the stipulated service standard for response timeValue0.000.0090.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Fully functional National Road Safety AuthorityValueNoNoYes
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Water points constructed or rehabilitatedValue0.000.0010.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Percentage of workers that have signed the SEA/SH code of conductValue0.000.00100.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Road crash data entered into a database system and used in decision makingValueNoNoYes
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Share of women employed in skilled jobs for road works financed by the projectValue0.000.005.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment
  • Share of women trained and certified in specialized skillsValue0.000.0010.00
    DateJune 30, 2022December 8, 2023May 31, 2028
    Comment