Climate Resilience and Water Security in Angola-RECLIMA

Abstract*

The proposed project will build on the achievements of PDISA in terms of expanded access to improved WASH services and water resources management strengthening to improve climate resilience and water security in Angola. The PDISA2 project is supporting DNA, IRSEA, targeted PWSUs, on institutional strengthening, water supply and sanitation planning investments in urban and peri-urban areas. This project will scale up support to four new provincial...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve water supply services and strengthen water resources management for climate resilience in selected areas in the Angolan territory

Key Details

Project Details

  • P177004

  • Active

  • Berta Macheve , Marco Aguero, Aleix Serrat Capdevila

  • Republic of Angola,Ministry of Finance

  • Angola

  • August 25, 2021

  • (as of board presentation)

    March 30, 2022

  • May 19, 2023

  • US$ 450.00 million

  • N/A

  • January 10, 2024

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FRANCE: French Agency for Development 150.00
International Bank for Reconstruction and Development 300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount 150.00
Total Project Cost** 450.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 28, 2024 IBRD-93700 Loan Disb 65,152.48
May 28, 2024 IBRD-93700 Loan Disb 94,860.69
Jun 18, 2024 IBRD-93700 Loan Disb 64,895.91
Mar 30, 2022 IBRD-93700 Loan Commitment 300,000,000.00
May 30, 2024 IBRD-93700 Loan Disb -65,448.87
May 28, 2024 IBRD-93700 Loan Disb 72,743.12
Apr 15, 2024 IBRD-93700 Int Charges 17,234.15
Apr 15, 2024 IBRD-93700 Int Charges 17,234.15
Apr 15, 2024 IBRD-93700 Int Charges 339,165.66
Apr 19, 2024 IBRD-93700 Loan Disb 3,194,250.00
Jul 23, 2024 IBRD-93700 Loan Disb 114,042.71
May 19, 2023 IBRD-93700 Fee Charges 722,961.60
May 19, 2023 IBRD-93700 Loan Disb 722,961.60
Oct 15, 2023 IBRD-93700 Int Charges 12,041.48
Oct 15, 2023 IBRD-93700 Int Charges 593,253.60
Oct 15, 2023 IBRD-93700 Int Charges 12,041.48

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-20
Project Management Moderately Satisfactory 2024-12-20
Financial Management Moderately Unsatisfactory 2024-12-20
Progress towards achievement of PDO Moderately Satisfactory 2024-12-20
Monitoring and Evaluation Moderately Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people in urban and peri-urban areas provided with access to improved water services under the project, disaggregated by male and female. (core indicator)Value0.000.00550000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Number of people in rural areas provided with access to a reliable and safe water source, disaggregated by male and femaleValue0.000.00310000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Number of community-level water and sanitation groups supported, including trainingValue0.000.0060.00
    DateMay 31, 2022December 14, 2022May 31, 2027
    Comment
  • Number of Municipalities with operational Municipal Water Plans, developed through participatory processes (citizen engagement), that include climate risk identification and contingency measures.Value0.000.0010.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of Provincial and Municipal technicians capacitated in the training centerValue0.000.00125.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Additional volume per year of groundwater resources mobilized by the project, including rehabilitation, and new investmentsValue0.000.0012388000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Percentage of women Young Professional and Technicians (YPTs) recruited and deployed by the projectValue14.0014.0050.00
    DateJanuary 2, 2023December 14, 2022December 28, 2029
    Comment
  • At least 1 Regional IRSEA office operationalized (pilot) assiting the utilities in the implementation of the regulatory instrumentsValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Additional storage created by new or rehabilitated infrastructure for multi-purpose water use.Value0.000.0010000000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • New piped household water connections resulting from the projectValue0.000.00110000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • GABHIC established in the South, operational in the 3 basins (Cunene, Cuvelai, Cubango), and strengthened to fulfill its mandate.ValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Increased water treatment capacity (production)Value0.000.0030000.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Number of surface and groundwater monitoring points providing data for GABHIC's information system.Value0.000.0015.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Percentage of maintained or repaired rural water systems supported by the project that are functionalValue0.000.0080.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Information Management System for water resources management established and operational in GABHIC.ValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Percentage of female members in community-based decision-making structures or positions in water users associationsValue14.0014.0030.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Number of Integrated River Basin Management Plans including a climate-informed water management strategy; and other regional studies performed.Value0.000.007.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Utilities have adopted data culture to improve decision making and management practices (using IBNET services) and complying with IRSEA's reporting requirementsValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 31, 2025
    Comment
  • Number of agency or administrations staff (from GABHIC, provinces, municipalities, and others) trained for the operation and management of hydraulic infrastructure including dams.Value0.000.0050.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Mechanism to gather beneficiary feedback for project activities at municipal level, used by beneficiaries and stakeholdersValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Number of people benefitting from water supply services provided by Sendi Dam (Huila)Value0.000.0019250.00
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment
  • Support the operationalization of one Interinstitutional unit between MINEA and MINAGRIP to oversee water services for irrigation and livestock (in coordination with MOSAP 3)ValueNoNoYes
    DateJanuary 2, 2023December 14, 2022December 29, 2028
    Comment