Financier | Commitments |
---|---|
IDA Grant | 150.00 |
P177044
Active
Eduardo Ereno Blanchet , Nadim Saghir, Ndeye Ba
Republic of Chad
January 29, 2022
(as of board presentation)
March 31, 2023
October 9, 2023
US$ 150.00 million
Ministry of Territorial Development, Urban Planning and Housing,Ministry of Infrastructure and road maintenance
2023
US$ 150.00 million
N/A
January 25, 2024
August 31, 2029
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 31, 2023 | IDA-E1620 | Loan Commitment | 150,000,000.00 |
Jun 17, 2024 | IDA-E1620 | Loan Disb | 118,676.54 |
May 17, 2024 | IDA-E1620 | Loan Disb | -101,171.78 |
Jun 20, 2024 | IDA-E1620 | Loan Disb | 10,000,000.00 |
Oct 11, 2023 | IDA-E1620 | Loan Disb | 1,187,867.90 |
Jul 26, 2024 | IDA-E1620 | Loan Disb | 2,083,630.20 |
Nov 14, 2023 | IDA-E1620 | Loan Disb | 1,633,986.90 |
Jul 23, 2024 | IDA-E1620 | Loan Disb | 956,531.90 |
Jun 17, 2024 | IDA-E1620 | Loan Disb | 291,987.80 |
Jun 25, 2024 | IDA-E1620 | Loan Disb | 973,483.90 |
Jun 24, 2024 | IDA-E1620 | Loan Disb | 101,337.77 |
May 17, 2024 | IDA-E1620 | Loan Disb | 102,277.48 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-12-16 |
Progress towards achievement of PDO | Satisfactory | 2024-12-16 |
Project Management | Satisfactory | 2024-12-16 |
Monitoring and Evaluation | Satisfactory | 2024-12-16 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-16 |
Procurement | Moderately Satisfactory | 2024-12-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People with reduced flood risk through infrastructure investments under the project | Value | 0.00 | 0.00 | 650000.00 |
Date | June 30, 2023 | December 11, 2023 | August 15, 2029 | |
Comment |
Those who are female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Reduction of the 20-year return period flood plain | Value | 0.00 | 0.00 | 1050.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Population living in a radius of 2 kilometers to a nature-based solution | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Drainage networks dredged and cleaned of solid waste according to yearly O&M plan | Value | 35.00 | 0.00 | 75.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
MATUH and Municipality have improved urban planning and management capacity | Value | N/A | N/A | Urban planning, flood risk management and emergenc |
Date | June 30, 2023 | December 11, 2023 | March 30, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with improved urban living conditions - Female (RMS requirement) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Constructed and/or rehabilitated flood protection infrastructure | Value | 0.00 | 0.00 | 42000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Update of the Urban Development Masterplan | Value | No | No | Yes |
Date | June 30, 2023 | December 11, 2023 | December 15, 2026 | |
Comment |
Municipality’s technical services buildings rehabilitated and/or provided with adequate equipment | Value | 0.00 | 0.00 | 90.00 |
Date | June 30, 2023 | December 11, 2023 | October 15, 2026 | |
Comment |
of which drainage infrastructure | Value | 0.00 | 0.00 | 20000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Municipal and ministerial staff from selected technical services trained according to the project’s capacity building plan | Value | 0.00 | 0.00 | 90.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
of which dikes | Value | 0.00 | 0.00 | 22000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Preparation of Pluvial and Fluvial Flood Risk Management Master Plan | Value | No | No | Yes |
Date | June 30, 2023 | December 11, 2023 | April 30, 2026 | |
Comment |
Women in leadership positions in the community preparedness and response committees supported by the project | Value | 0.00 | 0.00 | 25.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Community-level interventions supported by the project | Value | 0.00 | 0.00 | 200.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
of which led by women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Waste collected in selected areas targeted by the project | Value | 0.00 | 0.00 | 146000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Person-days of employment created by community-level interventions supported under the project | Value | 0.00 | 0.00 | 250000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
of which those who are female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
A contingency plan for the city (plan ORSEC) is developed, validated and adopted | Value | No | No | Yes |
Date | June 30, 2023 | December 11, 2023 | June 30, 2027 | |
Comment |
Neighborhoods reached by gender-sensitive disaster awareness campaigns targeting women | Value | 0.00 | 0.00 | 90.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Registered grievances appropriately addressed | Value | 0.00 | 0.00 | 90.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
Beneficiaries whose needs are met through community-level interventions | Value | 0.00 | 0.00 | 85.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
of which those who are female | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |
People provided with improved urban living conditions | Value | 0.00 | 0.00 | 750000.00 |
Date | June 30, 2023 | December 11, 2023 | June 30, 2029 | |
Comment |