Progestão Alagoas: Public Sector Management Efficiency

Abstract*

The proposed project is the first operation in a Series of Projects (SoP) under the Progestão Program designed to assist Brazilian States implement reforms that will improve efficiency in public expenditure. The Progestão Program recognizes that the subnational fiscal crisis is largely a result of structural problems in public sector management. The Program, available to all Brazilian States regardless of their fiscal situation, will provide technical...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve efficiency in public resource management in selected departments of the State of Alagoas

Key Details

Project Details

  • P177070

  • Active

  • Carolina Vaira , Gustavo Covolan Bozzetti

  • State of Alagoas, with the guarantee of the Federative Republic of Brazil

  • Brazil

  • September 9, 2021

  • (as of board presentation)

    July 21, 2022

  • January 15, 2025

  • US$ 50.00 million

  • Secretariat of Finance - State of Alagoas

  • Latin America and Caribbean

  • 2023

  • US$ 40.00 million

  • N/A

  • Low

  • March 31, 2028

  • Yes

  • BANK APPROVED

  • March 28, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00
Borrower/Recipient 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 21, 2022 IBRD-94350 Loan Commitment 40,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-06-18
Procurement Moderately Satisfactory 2025-06-18
Financial Management Moderately Satisfactory 2025-06-18
Project Management Moderately Satisfactory 2025-06-18
Counterpart Funding Moderately Satisfactory 2025-06-18
Monitoring and Evaluation Moderately Satisfactory 2025-06-18
Overall Implementation Progress (IP) Moderately Satisfactory 2025-06-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Public sector workforce replacement rateValue0.980.980.97
    DateJanuary 31, 2022December 11, 2023March 28, 2028
    Comment
  • Time between opening and finalizing the procurement processValue163.00163.00120.00
    DateDecember 31, 2021December 12, 2023March 28, 2028
    Comment
  • Public investment project time overrunsValue350.00350.00200.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Classrooms at less than 50 percent of capacityValue3.003.000.00
    DateJanuary 31, 2022June 22, 2023March 28, 2028
    Comment
  • Net fixed property incomeValueR$ 0 millionR$ 0 millionR$ 5.2 million
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Payroll irregularitiesValueN.AN/A0.3 percent
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Hospitals with a hospital management system implemented and operationalValue0.000.005.00
    DateJanuary 31, 2022December 12, 2023March 29, 2027
    Comment
  • State public agencies or institutions conducting strategic workforce planningValue5.005.0075.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Percent of municipalities using the new management system for financial reportingValue0.000.0065.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Pension payroll irregularitiesValueN.AN/A0.3 percent
    DateJanuary 31, 2022December 12, 2023September 30, 2027
    Comment
  • Municipalities implementing the new management system for social servicesValue0.000.0080.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Use of price reference system on bidding documents for goods and servicesValueNoNoYes
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Women-owned businesses registered in the state's procurement system and eligible to participate in public bidsValueN.A.N/A15 percent
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Public investment projects prepared and selected in line with PIM methodologyValue0.000.00100.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Integrated dashboard for municipal transfers with operational information and accessible to the publicValueNoNoYes
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Implementation of public hearings on government's capital investmentsValueNoNoYes
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Inventory of State ICT InfrastructureValueNoNoYes
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment
  • Public real estate with complete legal documentationValue0.000.0070.00
    DateJanuary 31, 2022December 12, 2023March 28, 2028
    Comment