Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 10.00 |
P177070
Active
Carolina Vaira , Gustavo Covolan Bozzetti
State of Alagoas, with the guarantee of the Federative Republic of Brazil
September 9, 2021
(as of board presentation)
July 21, 2022
January 15, 2025
US$ 50.00 million
Secretariat of Finance - State of Alagoas
2023
US$ 40.00 million
N/A
Low
March 31, 2028
Yes
BANK APPROVED
March 28, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 21, 2022 | IBRD-94350 | Loan Commitment | 40,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-06-18 |
Procurement | Moderately Satisfactory | 2025-06-18 |
Financial Management | Moderately Satisfactory | 2025-06-18 |
Project Management | Moderately Satisfactory | 2025-06-18 |
Counterpart Funding | Moderately Satisfactory | 2025-06-18 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-06-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-06-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Public sector workforce replacement rate | Value | 0.98 | 0.98 | 0.97 |
Date | January 31, 2022 | December 11, 2023 | March 28, 2028 | |
Comment |
Time between opening and finalizing the procurement process | Value | 163.00 | 163.00 | 120.00 |
Date | December 31, 2021 | December 12, 2023 | March 28, 2028 | |
Comment |
Public investment project time overruns | Value | 350.00 | 350.00 | 200.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Classrooms at less than 50 percent of capacity | Value | 3.00 | 3.00 | 0.00 |
Date | January 31, 2022 | June 22, 2023 | March 28, 2028 | |
Comment |
Net fixed property income | Value | R$ 0 million | R$ 0 million | R$ 5.2 million |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Payroll irregularities | Value | N.A | N/A | 0.3 percent |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Hospitals with a hospital management system implemented and operational | Value | 0.00 | 0.00 | 5.00 |
Date | January 31, 2022 | December 12, 2023 | March 29, 2027 | |
Comment |
State public agencies or institutions conducting strategic workforce planning | Value | 5.00 | 5.00 | 75.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Percent of municipalities using the new management system for financial reporting | Value | 0.00 | 0.00 | 65.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Pension payroll irregularities | Value | N.A | N/A | 0.3 percent |
Date | January 31, 2022 | December 12, 2023 | September 30, 2027 | |
Comment |
Municipalities implementing the new management system for social services | Value | 0.00 | 0.00 | 80.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Use of price reference system on bidding documents for goods and services | Value | No | No | Yes |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Women-owned businesses registered in the state's procurement system and eligible to participate in public bids | Value | N.A. | N/A | 15 percent |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Public investment projects prepared and selected in line with PIM methodology | Value | 0.00 | 0.00 | 100.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Integrated dashboard for municipal transfers with operational information and accessible to the public | Value | No | No | Yes |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Implementation of public hearings on government's capital investments | Value | No | No | Yes |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Inventory of State ICT Infrastructure | Value | No | No | Yes |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |
Public real estate with complete legal documentation | Value | 0.00 | 0.00 | 70.00 |
Date | January 31, 2022 | December 12, 2023 | March 28, 2028 | |
Comment |