Federated States of Micronesia Strategic Climate-Oriented Road Enhancements

Development Objective

To improve the climate resilience of the Recipient’s secondary road network, and in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

Key Details

Project Details

  • P177073

  • Active

  • Anita Shrestha

  • Federated States of Micronesia

  • US$ 35.25 million

  • Department of Transportation, Communications & Infrastructure

  • East Asia and Pacific

  • 2022

  • US$ 35.25 million

  • N/A

  • October 15, 2023

  • August 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 35.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 35.25
IBRD + IDA Commitment 35.25
Lending Instrument
Grant Amount N/A
Total Project Cost** 35.25

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 26, 2023 IDA-D9710 Loan Disb 2,030.91
Jan 11, 2023 IDA-D9710 Loan Disb 2,000,000.00
May 24, 2024 IDA-D9710 Loan Disb 9,510.22
Feb 1, 2024 IDA-D9710 Loan Disb 4,383.87
Mar 25, 2022 IDA-D9710 Loan Commitment 35,250,000.00
Oct 26, 2022 IDA-D9710 Loan Disb 41,598.61

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2024-11-11
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-11
Procurement Moderately Satisfactory 2024-11-11
Project Management Moderately Satisfactory 2024-11-11
Progress towards achievement of PDO Satisfactory 2024-11-11
Financial Management Satisfactory 2024-11-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved planning process for transport network investment and maintenance toward climate resilienceValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Length of secondary road upgraded with climate resilience measuresValue0.000.0013.50
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Vulnerable strategic secondary roads made more resilient to climate eventsValue0.000.0040.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Enabling environment solutions identified and implemented for enhanced climate resilienceValue0.000.005.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Population benefited from climate-resilient road improvements (work and/or technical assistance)Value0.000.0055.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of road upgraded using participatory design approaches (Kilometers)Value0.000.008.80
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Road Crash database established and used to inform sector planningValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Roads rehablitatedValue0.000.0013.50
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Road safety audits completed (Number)Value0.000.002.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Adoption of a CERC manualValueNoYesYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.000.0075.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Access audits completedValue0.000.002.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Roads rehabilitated - ruralValue0.000.000.00
    Date
    Comment
  • Transport Sector Data Management Unit is staffed and operationalValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Roads rehabilitated - non-ruralValue0.000.000.00
    Date
    Comment
  • Length of road rehabilitated with pavement strengtheningValue0.000.0013.50
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Percentage of Transport Sector Data Management Unit staff who are femaleValue0.000.0050.00
    Date
    Comment
  • Length of road with improved drainageValue0.000.007.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Materials Testing Laboratory established and in useValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Length of road improved with spot slope stabilizationValue0.000.00135.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Percentage of wage employees in project activities who are femaleValue0.000.0020.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Strategic 10-year plan for women in STEM establishedValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Percentage of contractor staff trained on SEA and SH components of the Codes of ConductValue0.000.00100.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Number of direct and indirect beneficiaries having enhanced access to road transport servicesValue0.000.0057658.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Motorization Management Policy Implementation Plan completedValueNoNoYes
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment
  • Climate resilient design packages completedValue0.000.001.00
    DateJune 15, 2022September 21, 2023August 31, 2028
    Comment