Financier | Commitments |
---|---|
IDA Credit | 150.00 |
P177094
Active
Pierre Lorillou , Clementine Stip, Aissata Bama Nati
Burkina Faso
January 10, 2023
(as of board presentation)
June 7, 2024
N/A
US$ 150.00 million
Direction Generale des Infrastructures Hydrauliques
2024
US$ 150.00 million
N/A
November 11, 2024
June 30, 2030
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 6, 2024 | IDA-75590 | Loan Commitment | 150,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-03-13 |
Procurement | Satisfactory | 2025-03-13 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-13 |
Project Management | Satisfactory | 2025-03-13 |
Financial Management | Satisfactory | 2025-03-13 |
Monitoring and Evaluation | Satisfactory | 2025-03-13 |