Financier | Commitments |
---|---|
Climate Investment Funds | 9.00 |
IDA Credit | 200.00 |
Energy Sector Management Assistance Program | 6.00 |
P177140
Active
Jenny Hasselsten , Mbuso Gwafila, Carla De Nobrega
UNITED REPUBLIC OF TANZANIA
March 29, 2022
(as of board presentation)
September 26, 2022
N/A
US$ 341.00 million
Rural Energy Agency
2023
US$ 215.00 million
N/A
November 15, 2023
June 15, 2026
BANK APPROVED
Financier | Commitments |
---|---|
Climate Investment Funds | 9.00 |
IDA Credit | 200.00 |
Energy Sector Management Assistance Program | 6.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | 15.00 |
Total Project Cost** | 341.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO Indicator 1: People provided with access to electricity under the program by household connections | Value | 0.00 | 2925000.00 | 7925000.00 |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
PDO Indicator 2: Non-residential connections implemented under the Program | Value | 0.00 | 31524.00 | 80000.00 |
Date | March 9, 2018 | April 26, 2022 | July 31, 2023 | |
Comment |
PDO Indicator 3: Cumulative number of proposed MWs covered by SPP and renewable energy sub-loans reaching financial close under the CL | Value | 0.00 | 0.36 | 13.00 |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
PDO Indicator 4: People provided with access to electricity via off-grid supplies and/or efficient cookstoves under the Program (including SPP, solar PV and cookstoves) | Value | 0.00 | 0.00 | 1350000.00 |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
PDO Indicator 5: Capacity for delivery of energy access and renewable energy generation strengthened | Value | No | No | Yes |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IR Indicator 2.4: :Female owned Business connected under the program | Value | 0.00 | 676.00 | 6000.00 |
Date | May 30, 2022 | May 30, 2022 | May 1, 2026 | |
Comment |
IR Indicator 1.1: Cumulative number of grid electricity connections, including those under mini-grids, made under the program | Value | 0.00 | 585000.00 | 1585000.00 |
Date | January 30, 2017 | April 26, 2022 | May 29, 2026 | |
Comment |
IR Indicator 5.1: Annual capacity building and project preparation activities completed | Value | No | Yes | Yes |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 1.2: Transmission and distribution lines constructed or rehabilitated under the program | Value | 0.00 | 28496.00 | 60000.00 |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indictor 5.2: Implementation of the National Energy Policy of 2015 to enhance access to modern energy services completed | Value | No | No | Yes |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 4.2: Households provided with electricity via SPPs or renewable energy under the program that are female-headed | Value | 24.00 | 0.00 | 24.00 |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 1.3: Households connected to the grid that are female-headed | Value | 24.00 | 19.00 | 24.00 |
Date | January 30, 2017 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 2.1: Educational facilities connected under the program | Value | 0.00 | 5900.00 | 10000.00 |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 2.2: Health care facilities connected under the program | Value | 0.00 | 1664.00 | 4000.00 |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 2.3: Business connected under the program | Value | 0.00 | 14316.00 | 20000.00 |
Date | December 30, 2016 | April 26, 2022 | July 31, 2023 | |
Comment |
IR Indicator 3.1: Cumulative value of eligible SPP and renewable energy sub-loans reaching financial close | Value | 0.00 | 400000.00 | 16500000.00 |
Date | July 30, 2021 | April 26, 2022 | July 31, 2023 | |
Comment |
IR indicator 4.1: Cumulative number of off-grid electricity connections, made under the program | Value | 0.00 | 0.00 | 70000.00 |
Date | May 30, 2022 | May 30, 2022 | May 1, 2026 | |
Comment |
IR Indicator 5.3: Contractors that have prepared and operationalized stakeholder engagement plan through conducting at least one stakeholder meeting in each project village | Value | 0.00 | 0.00 | 100.00 |
Date | May 30, 2022 | May 30, 2022 | May 1, 2026 | |
Comment |
IR Indicator 4.3: Households provided with clean cooking solutions | Value | 0.00 | 0.00 | 200000.00 |
Date | May 30, 2022 | May 30, 2022 | May 1, 2026 | |
Comment |
IR Indicator 4.4 (new) Amount of private investment mobilized for clean cooking solutions | Value | 0.00 | 0.00 | 3250000.00 |
Date | May 31, 2022 | May 31, 2022 | May 1, 2026 | |
Comment |
IR Indicator 4.5 (new) Action Plans and guidelines adopted by the government to support clean cooking market development | Value | 0.00 | 0.00 | 1.00 |
Date | May 31, 2022 | May 31, 2022 | May 1, 2026 | |
Comment |