Financier | Commitments |
---|---|
IDA Grant | 120.00 |
P177210
Active
Ibrahim Kabore , Malaika Becoulet
Ministry of Finance
Haiti
November 10, 2021
(as of board presentation)
May 26, 2022
August 25, 2022
US$ 120.00 million
Unite Centrale d'execution of Ministry of Transport, Public works and Communications
2022
US$ 120.00 million
N/A
November 1, 2023
May 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 120.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 120.00 |
IBRD + IDA Commitment | 120.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 120.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 23, 2024 | IDA-E0440 | Loan Disb | 413,469.38 |
Jun 5, 2024 | IDA-E0440 | Loan Disb | 304,326.22 |
Jun 5, 2024 | IDA-E0440 | Loan Disb | 286,868.84 |
May 24, 2024 | IDA-E0440 | Loan Disb | 612,395.20 |
Jun 5, 2024 | IDA-E0440 | Loan Disb | 270,619.72 |
Jun 5, 2024 | IDA-E0440 | Loan Disb | 226,350.20 |
Aug 5, 2024 | IDA-E0440 | Loan Disb | 428,199.75 |
Aug 8, 2024 | IDA-E0440 | Loan Disb | 1,460,411.50 |
May 30, 2024 | IDA-E0440 | Loan Disb | 282,087.50 |
Jun 28, 2024 | IDA-E0440 | Loan Disb | 1,000,000.00 |
Apr 17, 2024 | IDA-E0440 | Loan Disb | 679,020.50 |
May 20, 2024 | IDA-E0440 | Loan Disb | 342,393.88 |
Jul 3, 2024 | IDA-E0440 | Loan Disb | 216,622.58 |
May 26, 2022 | IDA-E0440 | Loan Commitment | 120,000,000.00 |
Feb 21, 2023 | IDA-E0440 | Loan Disb | 3,000,000.00 |
Jul 3, 2023 | IDA-E0440 | Loan Disb | 117,374.71 |
Sep 19, 2023 | IDA-E0440 | Loan Disb | 139,557.60 |
Sep 11, 2023 | IDA-E0440 | Loan Disb | 138,000.00 |
Sep 11, 2023 | IDA-E0440 | Loan Disb | 117,003.90 |
Dec 20, 2023 | IDA-E0440 | Loan Disb | 100,248.79 |
Dec 11, 2023 | IDA-E0440 | Loan Disb | 282,966.30 |
Oct 30, 2023 | IDA-E0440 | Loan Disb | 161,401.80 |
Nov 1, 2023 | IDA-E0440 | Loan Disb | 277,963.75 |
Jun 10, 2024 | IDA-E0440 | Loan Disb | 802,041.90 |
Sep 28, 2023 | IDA-E0440 | Loan Disb | 237,272.78 |
Jan 17, 2024 | IDA-E0440 | Loan Disb | 1,749,146.90 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-16 |
Monitoring and Evaluation | Satisfactory | 2024-12-16 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-16 |
Project Management | Satisfactory | 2024-12-16 |
Procurement | Moderately Satisfactory | 2024-12-16 |
Financial Management | Moderately Satisfactory | 2024-12-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People benefited from improved climate-resilient rural roads in the South peninsula | Value | 0.00 | 0.00 | 226800.00 |
Date | November 1, 2022 | November 3, 2023 | December 31, 2027 | |
Comment |
Economic opportunities in Cap-Haitien accessible by public transport in less than 60 minutes | Value | 35.00 | 35.00 | 90.00 |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Municipal Public Transport Unit in Cap Haitien is operational and staffed | Value | No | No | Yes |
Date | November 1, 2022 | March 23, 2023 | May 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 0.00 | 200.00 |
Date | May 2, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Design study for the interventions in the selected corridors delivered | Value | No | No | Yes |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Public agents trained on urban mobility planning and management | Value | 0.00 | 4.00 | 60.00 |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Drainage improvements of urban-rural mobility infrastructure in selected cities in the South Peninsula | Value | 0.00 | 0.00 | 5.00 |
Date | May 2, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Public agents trained that are women | Value | 0.00 | 1.00 | 30.00 |
Date | June 30, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
The design of the urban infrastructure investments addresses the specific needs of women | Value | No | No | Yes |
Date | ||||
Comment |
Infrastructure investments climate informed in the South Peninsula | Value | 0.00 | 0.00 | 100.00 |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Length of streets improved with climate-resilient features and better street space sharing in selected corridors in Cap Haitien and other targeted urban areas | Value | 0.00 | 0.00 | 18000.00 |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
National Strategy for urban transport delivered | Value | No | No | Yes |
Date | May 2, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Person-days of labour intensive works of people from local communities generated by Project activities | Value | 0.00 | 0.00 | 350000.00 |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Intersections improved in selected corridors and downtown in Cap Haitien | Value | 0.00 | 0.00 | 8.00 |
Date | November 1, 2022 | November 3, 2023 | January 28, 2028 | |
Comment |
Regulatory framework for urban public transport adopted | Value | No | No | Yes |
Date | November 30, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Road infrastructure safety assessment completed | Value | No | No | Yes |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Person.days of Labour Intensive Work of women | Value | 0.00 | 0.00 | 60000.00 |
Date | ||||
Comment |
Toolkit and Manual for inclusive and climate-resilient urban transport planning delivered | Value | 0.00 | 0.00 | 2.00 |
Date | November 1, 2022 | November 3, 2023 | November 28, 2025 | |
Comment |
Citizens reporting satisfaction with project’s consultation and communication mechanisms, disaggregated by gender | Value | 0.00 | 0.00 | 90.00 |
Date | May 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Direct beneficiaries of improved resilient and accessible street environment in Cap Haitien and targeted urban areas | Value | 0.00 | 0.00 | 180000.00 |
Date | March 31, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Gender action plan for the urban transport sector delivered | Value | No | No | Yes |
Date | November 1, 2022 | November 3, 2023 | November 28, 2025 | |
Comment |
Users satisfied with improved urban transport infrastructure in the selected corridors | Value | 0.00 | 0.00 | 80.00 |
Date | November 30, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Women reporting satisfaction | Value | 0.00 | 0.00 | 90.00 |
Date | May 2, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Road safety data base established and populated | Value | No | No | Yes |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Automated fare collection pilot deployed in one corridor | Value | No | No | Yes |
Date | November 1, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Women satisfied | Value | 0.00 | 0.00 | 90.00 |
Date | ||||
Comment |
Plan for the Renewal fleet mechanism delivered | Value | No | No | Yes |
Date | May 2, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
Number of participants in transport internship programs hired before the end of the project | Value | 0.00 | 0.00 | 12.00 |
Date | December 30, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |
that are women | Value | 0.00 | 0.00 | 7.00 |
Date | December 30, 2022 | November 3, 2023 | May 31, 2028 | |
Comment |