Somalia Enhancing Public Resource Management Project

Abstract*

The proposed project rests on the premise that synergies and sustainable improvements can be achieved by taking a comprehensive approach to governance reforms. In this regard, the project design aims to explore in detail the interlink between public financial management (PFM), domestic revenue mobilization (DRM), and the public sector. For instance, budget credibility sets the stage for strong PFM, and it rests heavily on improving DRM. Furthermore...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen accountability, transparency and institutional capacity in public resource management, across participating entities

Key Details

Project Details

  • P177298

  • Active

  • May Olalia , Vikram Menon, Alma Nurshaikhova

  • Federal Republic of Somalia

  • Somalia

  • October 24, 2022

  • (as of board presentation)

    December 14, 2022

  • October 30, 2023

  • US$ 75.00 million

  • Federal Ministry of Finance, Somalia,Ministry of Finance, Somaliland

  • Eastern and Southern Africa

  • 2023

  • US$ 75.00 million

  • N/A

  • Substantial

  • December 31, 2027

  • Yes

  • BANK APPROVED

  • February 9, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Somalia Multi-Partner Fund 15.00
IDA Grant 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 60.00
IBRD + IDA Commitment 60.00
Lending Instrument
Grant Amount 15.00
Total Project Cost** 75.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 12, 2024 IDA-E1360 Loan Disb 2,500,000.00
Dec 14, 2022 IDA-E1360 Loan Commitment 60,000,000.00
Aug 29, 2024 IDA-E1360 Loan Disb 290,438.38
Aug 21, 2024 IDA-E1360 Loan Disb 104,022.30

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-19
Progress towards achievement of PDO Moderately Satisfactory 2024-10-19
Financial Management Moderately Satisfactory 2024-10-19
Monitoring and Evaluation Moderately Satisfactory 2024-10-19
Procurement Moderately Satisfactory 2024-10-19
Project Management Moderately Satisfactory 2024-10-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Accountability: Implementation of previous years' audit recommendations relevant to Ministries of Finance on the consolidated financial statements - FGSValue50.0050.0075.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Implementation of previous years' audit recommendations relevant to Ministries of Finance on the consolidated financial statements - FMSsValue10.0010.0050.00
    Date
    Comment
  • Implementation of previous years' audit recommendations relevant to Ministries of Finance on the consolidated financial statements - SLValue30.0030.0050.00
    Date
    Comment
  • Transparency: Time taken (from end of financial year) to publish annual audited financial statements - (FGS)Value11.0011.006.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Time taken (from end of financial year) to publish annual audited financial statements - (FMSs)Value24.0024.0012.00
    Date
    Comment
  • Time taken (from end of financial year) to publish annual audited financial statements - (SL)Value6.006.006.00
    Date
    Comment
  • Institutional Capacity: New potential taxpayers identified and registeredValue0.000.0030.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Institutional Capacity: Implementation of budgeted staffing plans for technical positions in PFM, DRM and policy making functions ((disaggregated by gender and professional categories)Value0.000.00100.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Female staff recruited at Director General, Director of Department and Head of Section positionsValue0.000.008.00
    Date
    Comment
  • Institutional Capacity: Pilot service centers established and operational - SLValue0.000.003.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Internal Audit report issued by MoFValue0.000.004.00
    DateDecember 30, 2022November 30, 2023June 30, 2027
    Comment
  • On-line filing declaration for income tax and sales tax by large taxpayersValue0.000.0080.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • HRMIS interfaced with FMIS and BISAN in all jurisdictionsValueNoNoYes
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Staff trained based on PFM and DRM training plans across FGS, FMS and SLValue0.000.0080.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Budget warrant requests by Ministries of Health and Education met by MoFValue0.000.0085.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Civil servants transitioned into the new pay and grading system in FGS and Puntland, and donor-financed staff salaries aligned withthe new civil service pay scaleValueNoNoYes
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Budget warrants received by Ministries of Health and Education are committed during the requested timeValue0.000.0090.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Officials passing the DRM Training Course competency testValue0.000.0080.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Civil servants eligible for pension benefits under relevant Pension Laws are retired and receiving pension benefits as defined by the FGS and PSS Pension Laws, respectivelyValueNoNoYes
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Procurement, legal and regulatory framework operationalizedValueLegal and regulatory framework is not operationaliLegal and regulatory framework is not operationaliAnnual performance report published
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Prepare and publish previous year's tax revenue and expenditure information for citizensValueNoNoYes
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Citizen Feedback Mechanism for pilot access points operational (yes/no) - SLValueNoNoYes
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Time from budget approval to publishing a citizens' budget in English and local language (FGS and FMSs)Value6.006.001.00
    DateJune 30, 2022November 30, 2023June 30, 2027
    Comment
  • Number of periodic citizen engagement feedback reports on service access points published , including data on female satisfaction -SLValue0.000.004.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Number of transactions completed per pilot center annually - SLValueBaseline to be established in Y3 based on data froBaseline to be established in Y3 based on data fro30% increase over Y4
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Time from budget approval to publishing a citizens' budget in English and local language (SL)Value3.003.002.00
    Date
    Comment
  • Time from the period end to publishing mid-year and year-end budget analysis reports (FGS and FMSs)Value0.000.0030.00
    DateJune 30, 2022November 30, 2023December 31, 2027
    Comment
  • Time from the period end to publishing mid-year and year-end budget analysis reports (SL)Value60.0060.0045.00