Eskom Just Energy Transition Project

Abstract*

The development objective of Eskom Just Energy Transition Project for South Africa is to (i) decommission the Komati coal-fired power plant, (ii) repurpose the project area with renewables, and (iii) create opportunities for workers and communities during the transition process. This project has three components. 1) The first component, Komati Decommissioning, has the following sub-components: (i) Subcomponent A.1; and (ii) Subcomponent A.2. 2) The...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to (i) decommission the Komati coal-fired power plant, (ii) repurpose the project area with renewables, and (iii) create opportunities for workers and communities during the transition process.

Key Details

Project Details

  • P177398

  • Active

  • Mirlan Aldayarov , Miarintsoa Rakotondramanana, Bandita Sijapati

  • Eskom Holdings Soc Ltd,Eskom Holdings Soc Ltd

  • South Africa

  • December 2, 2021

  • (as of board presentation)

    November 3, 2022

  • July 28, 2023

  • US$ 497.00 million

  • N/A

  • December 18, 2023

  • December 29, 2028

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Energy Sector Management Assistance Program 10.00
International Bank for Reconstruction and Development 439.50
Canada Clean Energy and Forest Climate Facility Trust Fund 47.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 439.50
IDA Commitment N/A
IBRD + IDA Commitment 439.50
Lending Instrument
Grant Amount 57.50
Total Project Cost** 497.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 3, 2022 IBRD-94500 Loan Commitment 439,500,000.00
Dec 20, 2022 TF-B9712 Loan Commitment 47,500,000.00
Jun 1, 2024 IBRD-94500 Int Charges 130.03
Dec 1, 2023 IBRD-94500 Int Charges 24,463.75
Jun 1, 2024 IBRD-94500 Int Charges 37,359.25
Jul 28, 2023 IBRD-94500 Fee Charges 1,098,750.00
Jul 28, 2023 IBRD-94500 Loan Disb 1,098,750.00
Jun 1, 2024 IBRD-94500 Int Charges 548,255.94
Dec 1, 2023 IBRD-94500 Int Charges 649,270.94

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2025-03-07
Project Management Satisfactory 2025-03-07
Financial Management Unsatisfactory 2025-03-07
Monitoring and Evaluation Satisfactory 2025-03-07
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-07
Progress towards achievement of PDO Moderately Satisfactory 2025-03-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Eskom Workers at Komati retrained / re-deployed / compensatedValue0.000.00100.00
    DateJuly 28, 2022August 8, 2023October 24, 2028
    Comment
  • Suppliers, contractors and enterprises supportedValue0.000.0040.00
    DateSeptember 22, 2022August 8, 2023October 24, 2028
    Comment
  • Net greenhouse gas (GHG) emissionsValue80000.0080000.000.00
    DateSeptember 30, 2022August 8, 2023October 24, 2028
    Comment
  • EJETP Community Forum established (% of female representation)Value0.000.0050.00
    DateOctober 26, 2022August 8, 2023March 22, 2023
    Comment
  • Renewable energy produced (annually)Value0.000.00420.00
    DateOctober 26, 2022August 8, 2023October 25, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Hiring of Owner-Engineer (OE)Value202206222023083120230925
    DateSeptember 30, 2022August 8, 2023October 24, 2028
    Comment
  • Installation of 150 MW energy storageValue0.000.00150.00
    DateSeptember 29, 2022July 16, 2025July 16, 2025
    Comment
  • Suppliers, contractors, enterprises supported that are women-ledValue0.000.0050.00
    DateSeptember 28, 2022August 8, 2023October 26, 2028
    Comment
  • Hiring of EPC contractorValue202206222024043020250331
    DateOctober 26, 2022August 8, 2023October 25, 2028
    Comment
  • Synchronous CondensersValue0.000.003.00
    DateSeptember 28, 2022August 8, 2023October 27, 2026
    Comment
  • Female Komati workers trained at Komati who are gainfully employed or self-employed 6 months after certificationValue0.000.0080.00
    DateSeptember 28, 2022August 8, 2023October 25, 2028
    Comment
  • Coal Plant Decommissioning GuidelinesValueNoNoYes
    DateOctober 27, 2022August 8, 2023October 25, 2028
    Comment
  • Generation capacity of energy constructed or rehabilitatedValue0.000.00220.00
    DateOctober 26, 2022August 8, 2023October 24, 2028
    Comment
  • Grievances solved within 6 monthValue0.000.0080.00
    DateSeptember 28, 2022August 8, 2023October 24, 2028
    Comment
  • Feedback received through the stakeholder engagement platforms and Eskom’s responses published on a semi-annual basisValue0.000.0040.00
    DateOctober 25, 2022August 8, 2023October 24, 2028
    Comment
  • Thermal (conventional) power generation capacity constructed under the projectValue0.000.000.00
    DateOctober 25, 2022August 8, 2023October 25, 2028
    Comment
  • Socio-Economic Guidelines for Coal Plant RetirementValueNoNoYes
    DateOctober 25, 2022August 8, 2023October 24, 2028
    Comment
  • Hydropower generation capacity constructed under the projectValue0.000.000.00
    DateJuly 27, 2022August 8, 2023October 24, 2028
    Comment
  • Hydropower generation capacity rehabilitated under the projectValue0.000.000.00
    DateOctober 25, 2022August 8, 2023October 24, 2028
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.000.00220.00
    DateOctober 26, 2022August 8, 2023October 25, 2028
    Comment
  • Renewable energy generation capacity (other than hydropower) rehabilitated under the projectValue0.000.000.00
    DateOctober 26, 2022August 8, 2023October 31, 2028
    Comment
  • Thermal (conventional) power generation capacity rehabilitated under the projectValue0.000.000.00
    DateOctober 25, 2022August 8, 2023October 24, 2028
    Comment
  • Coal Plant Repurposing GuidelinesValueNoNoYes
    DateOctober 26, 2022August 8, 2023October 25, 2028
    Comment
  • Volume of private and public direct finance mobilized for renewable energy leveragedValue0.000.00350000000.00
    DateOctober 25, 2022August 8, 2023October 25, 2028
    Comment
  • New renewable energy jobs directly created (Percentage m/f, Percentage permanent/temporary).Value0.000.00100.00
    DateOctober 25, 2022August 8, 2023October 25, 2028
    Comment