Financier | Commitments |
---|---|
IDA Credit | 100.00 |
P177492
Active
Silas Udahemuka , Yoonyoung Cho, Mba Djekombe Rony
Republic of Rwanda
Rwanda
March 16, 2022
(as of board presentation)
September 22, 2022
December 23, 2022
US$ 100.00 million
The Ministry of Local Government (MINALOC),Local Administrative Entities Development Agency (LODA)
2023
US$ 100.00 million
N/A
Moderate
December 31, 2026
TBD
BANK APPROVED
February 1, 2024
Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 22, 2023 | IDA-72060 | Loan Disb | 2,478,330.50 |
Sep 7, 2023 | IDA-72060 | Loan Disb | 13,194,978.00 |
Sep 22, 2022 | IDA-72060 | Loan Commitment | 100,000,000.00 |
Jun 18, 2024 | IDA-72060 | Loan Disb | 18,064,042.00 |
May 26, 2023 | IDA-72060 | Loan Disb | 7,698,068.00 |
Aug 21, 2023 | IDA-72060 | Loan Disb | 5,176,880.00 |
Sep 5, 2023 | IDA-72060 | Loan Disb | 2,312,752.50 |
Apr 9, 2024 | IDA-72060 | Loan Disb | 9,230,172.00 |
Jan 2, 2024 | IDA-72060 | Loan Disb | 560,002.20 |
Jan 24, 2023 | IDA-72060 | Loan Disb | 2,068,215.10 |
Jan 24, 2023 | IDA-72060 | Loan Disb | 19,538,920.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-11-11 |
Progress towards achievement of PDO | Satisfactory | 2024-11-11 |
Project Management | Satisfactory | 2024-11-11 |
Financial Management | Satisfactory | 2024-11-11 |
Monitoring and Evaluation | Satisfactory | 2024-11-11 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-11 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Eligible households supported under ePWs | Value | 95.63 | 91.00 | 97.77 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible households supported through DS | Value | 100.00 | 100.00 | 100.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Proportion of VUP beneficiaries enrolled in human capital-focused interventions | Value | 49.68 | 53.00 | 51.47 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Proportion of female beneficiaries reached through ePWs | Value | 70.00 | 70.00 | 0.00 |
Date | ||||
Comment |
Eligible households covered by the VUP cash transfer schemes in targeted sectors and/or districts | Value | 71.52 | 89.00 | 74.46 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible VUP households benefiting from SLE package | Value | 1.90 | 1.90 | 21.20 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
VUP beneficiaries identified through the dynamic social registry | Value | 0.00 | 0.00 | 100.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible households covered by climate-smart cPW | Value | 18.87 | 64.00 | 50.00 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible beneficiaries receiving NSDS transfers | Value | 64.79 | 70.02 | 70.02 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
CSOs involved in monitoring and supporting of delivery of social protection services at the district and central levels | Value | 11.00 | 12.00 | 20.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Social registry information system modules deployed | Value | 0.00 | 9.00 | 4.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible VUP households receiving SLE | Value | 21333.00 | 21333.00 | 201633.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Beneficiaries of social safety net programs | Value | 1465688.00 | 1897846.00 | 1539020.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Beneficiaries who receive cash transfers through digital payment modality | Value | 159592.00 | 252235.00 | 185512.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible female-headed VUP households receiving SLE | Value | 7587.00 | 7587.00 | 0.00 |
Date | ||||
Comment |
Beneficiaries of social safety net programs - Female | Value | 908049.00 | 908049.00 | 0.00 |
Date | ||||
Comment |
SP communities of practice and peer learning sessions organized | Value | 0.00 | 0.00 | 6.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Para-social workers receiving refresher trainings to deliver socio-economic services | Value | 0.00 | 4167.00 | 14752.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Female beneficiaries who receive cash transfers through digital payment modality | Value | 98847.00 | 98847.00 | 0.00 |
Date | ||||
Comment |
Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) | Value | 282845.00 | 290260.00 | 282845.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Project related grievances addressed, disaggregated by gender | Value | 100.00 | 100.00 | 100.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
District staff trained on social protection information systems | Value | 1985.00 | 10978.00 | 4462.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Share of VUP beneficiaries registered to save under Ejo Heza | Value | 73.00 | 73.00 | 75.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Beneficiaries of Safety Nets programs - Other cash transfers programs (number) | Value | 133249.00 | 171684.00 | 150742.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible VUP beneficiaries who reach a minimum saving threshold (annual) to Ejo Heza savings scheme | Value | 170940.00 | 170940.00 | 239849.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number) | Value | 1049595.00 | 1333967.00 | 1127290.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
District staff trained on VUP MEIS | Value | 1985.00 | 654.00 | 4282.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Beneficiaries of ePWs | Value | 95318.00 | 90691.00 | 102340.00 |
Date | July 19, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
District staff trained on social registry | Value | 0.00 | 2742.00 | 180.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Eligible female VUP beneficiaries who reach a minimum saving threshold (annual) to Ejo Heza savings scheme | Value | 123854.00 | 123854.00 | 0.00 |
Date | ||||
Comment |
Share of climate-smart cPWs projects as a proportion of all cPW | Value | 28.00 | 56.00 | 50.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Pregnant women enrolled in NSDS attending 4 ANC visits | Value | 39.00 | 45.00 | 55.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
0-6 weeks old children whose mothers/guardians are NSDS beneficiaries attending 2 PNC visits at health facility | Value | 59.70 | 61.00 | 65.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Enrolled children 18 months to 24 months whose mothers/guardians are NSDS beneficiaries attending 6 height for age measurement at health facility | Value | 46.40 | 51.00 | 60.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Children benefiting from Community-Based/Home-Based ECD | Value | 78751.00 | 80518.00 | 87040.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |
Parents participating in community meetings where behavior change parenting sessions are delivered | Value | 3174.00 | 5071.00 | 14592.00 |
Date | July 14, 2022 | September 26, 2023 | December 31, 2026 | |
Comment |