Barwaaqo - Somalia Water for Rural Resilience Project

Abstract*

Somalia has embarked on a journey for the sustainable development of its water resources for its communities. With the support of the World Bank, the Somaliland and Puntland states piloted low cost and conflict deterring water solutions under the Water for Agro-Pastoralist Livelihoods Pilot Project (WALP), a US$2 million pilot that resulted in the building of eight sand dams over the period 2016 to 2018. This investment paved the way for the ongoing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To develop water, agriculture, and environmental services for rural communities in Somalia’s drylands.

Key Details

Project Details

  • P177627

  • Active

  • Raghava Neti , Jeehye Kim, James Otieno

  • Federal Republic of Somalia

  • Somalia

  • March 29, 2022

  • (as of board presentation)

    December 9, 2022

  • January 20, 2023

  • US$ 70.00 million

  • Ministry of Planning Investment and Economic Development

  • Eastern and Southern Africa

  • 2023

  • US$ 70.00 million

  • N/A

  • March 4, 2024

  • February 29, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 70.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 70.00
IBRD + IDA Commitment 70.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 70.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 21, 2023 IDA-E1320 Loan Disb 1,369,727.20
Dec 29, 2023 IDA-E1320 Loan Disb 39,580.01
Mar 13, 2024 IDA-E1320 Loan Disb 544,858.56
Jun 5, 2024 IDA-E1320 Loan Disb 101,694.42
Aug 21, 2024 IDA-E1320 Loan Disb 181,448.20
May 31, 2024 IDA-E1320 Loan Disb 12,862.51
Sep 3, 2024 IDA-E1320 Loan Disb 195,836.81
May 31, 2024 IDA-E1320 Loan Disb 72,351.57
Aug 21, 2024 IDA-E1320 Loan Disb 37,728.68
Jun 17, 2024 IDA-E1320 Loan Disb 1,916,847.60
Jun 17, 2024 IDA-E1320 Loan Disb 419,809.38
Jun 25, 2024 IDA-E1320 Loan Disb 312,570.90
Feb 23, 2024 IDA-E1320 Loan Disb 27,702.01
Aug 7, 2024 IDA-E1320 Loan Disb 275,358.75
Feb 28, 2024 IDA-E1320 Loan Disb 195,836.81
Jun 20, 2024 IDA-E1320 Loan Disb 8,391.50
Dec 9, 2022 IDA-E1320 Loan Commitment 70,000,000.00
Mar 13, 2024 IDA-E1320 Loan Disb 1,579,248.60
Dec 22, 2023 IDA-E1320 Loan Disb 346,841.20
Nov 7, 2023 IDA-E1320 Loan Disb 195,836.81
Jan 10, 2024 IDA-E1320 Loan Disb 19,700.00
Jan 10, 2024 IDA-E1320 Loan Disb 289,406.25
Jan 10, 2024 IDA-E1320 Loan Disb 67,798.69
Jan 10, 2024 IDA-E1320 Loan Disb 228,000.00
Dec 4, 2023 IDA-E1320 Loan Disb 765,958.60
Dec 11, 2023 IDA-E1320 Loan Disb 10,129.00
Jan 16, 2024 IDA-E1320 Loan Disb 97,587.00
Feb 22, 2023 IDA-E1320 Loan Disb 1,000,000.00
Jul 5, 2023 IDA-E1320 Loan Disb -999,927.50
Sep 5, 2023 IDA-E1320 Loan Disb 678,438.10
Mar 6, 2023 IDA-E1320 Loan Disb 5,000,000.00
Jun 26, 2023 IDA-E1320 Loan Disb 413,267.97
Jun 26, 2023 IDA-E1320 Loan Disb 114,075.92
Sep 6, 2023 IDA-E1320 Loan Disb 9,170.01
Jun 16, 2023 IDA-E1320 Loan Disb 1,000,000.00
Aug 29, 2023 IDA-E1320 Loan Disb 771,050.30
Aug 10, 2023 IDA-E1320 Loan Disb 999,927.50
Jun 20, 2023 IDA-E1320 Loan Disb 489,592.03

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2025-03-19
Monitoring and Evaluation Satisfactory 2025-03-19
Progress towards achievement of PDO Moderately Satisfactory 2025-03-19
Financial Management Moderately Satisfactory 2025-03-19
Monitoring and Evaluation Satisfactory 2025-03-19
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-19
Procurement Moderately Satisfactory 2025-03-19
Procurement Moderately Satisfactory 2025-03-19
Project Management Moderately Satisfactory 2025-03-19
Progress towards achievement of PDO Moderately Satisfactory 2025-03-19
Financial Management Moderately Satisfactory 2025-03-19
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to improved water sourcesValue0.000.00500000.00
    DateFebruary 15, 2024February 15, 2024February 29, 2028
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • Farmers adopting improved agricultural technologyValue0.00506.00200000.00
    DateJune 30, 2022February 15, 2024February 29, 2028
    Comment
  • Farmers adopting improved agricultural technology - FemaleValue0.000.000.00
    Date
    Comment
  • Land area under sustainable landscape management practicesValue0.000.008000.00
    DateJune 30, 2023February 15, 2024February 29, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land area under invasive species management techniquesValue0.000.001000.00
    DateJanuary 2, 2023February 15, 2024February 29, 2028
    Comment
  • Number of functional Farmer Field Schools establishedValue0.000.00150.00
    DateJune 30, 2023February 15, 2024February 29, 2028
    Comment
  • Efficient and functional web-based Management Information System (MIS)Value1.000.002.00
    DateApril 13, 2022February 15, 2024February 29, 2028
    Comment
  • New water points constructed to reduce the risk of water shortages in drought-prone rural areasValue0.000.00100.00
    DateJune 30, 2023February 15, 2024February 29, 2028
    Comment
  • Agricultural land area with soil and water conservation measuresValue0.000.003000.00
    DateApril 13, 2022February 15, 2024February 29, 2028
    Comment
  • Number of Animals that received veterinary servicesValue0.00131769.001800000.00
    DateJanuary 2, 2023February 15, 2024February 29, 2028
    Comment
  • Beneficiaries that feel project investments reflected their needsValue0.000.0070.00
    DateApril 13, 2022February 15, 2024February 29, 2028
    Comment
  • Existing water points rehabilitated to reduce the risk of water shortages in drought-prone rural areasValue0.003.0050.00
    DateJune 30, 2023February 15, 2024February 29, 2028
    Comment
  • Forest area restoredValue0.000.00500.00
    DateMarch 1, 2023February 15, 2024February 29, 2028
    Comment
  • Number of Community Animal Health workers (CAHWs) trainedValue0.00160.00500.00
    DateJanuary 2, 2023February 15, 2024February 29, 2028
    Comment
  • Number of government staff gaining capacity to plan and design climate-resilient infrastructureValue0.0094.00175.00
    DateJune 30, 2022February 15, 2024February 29, 2028
    Comment
  • Project Implementation Units (PIUs) staffedValue4.005.006.00
    DateApril 13, 2022February 15, 2024February 29, 2028
    Comment
  • Female number of government staff gaining capacity to plan and design climate-resilient infrastructureValue0.000.000.00
    Date
    Comment
  • Female number of Community Animal Health workers (CAHWs) trainedValue0.000.000.00
    Date
    Comment
  • Female share of PIU staff, interns & seconded staff at line ministries & other water institutionsValue12.0024.0030.00
    DateFebruary 28, 2023February 15, 2024February 29, 2028
    Comment
  • Number of institutions providing veterinary services/certifications strengthenedValue0.000.0015.00
    DateJune 30, 2022February 15, 2024February 29, 2028
    Comment
  • Proportion of contracts awarded to female friendly contractorsValue0.0029.0020.00
    DateJuly 26, 2022February 15, 2024February 29, 2028
    Comment
  • Livestock managers with increased productivityValue0.000.0070.00
    DateJanuary 2, 2023February 15, 2024February 29, 2028
    Comment
  • Women’s share of leadership positions in Village Development Committees (VDCs)Value2.002.0020.00
    DateAugust 1, 2022February 15, 2024February 29, 2028
    Comment
  • Female share of livestock managers with increased productivityValue0.000.000.00
    Date
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.00100.0075.00
    DateMarch 1, 2023February 15, 2024February 29, 2028
    Comment
  • Community Investment Plans DevelopedValue0.000.00150.00
    DateFebruary 28, 2023February 15, 2024February 29, 2028
    Comment
  • Number of line Ministry buildings, laboratories and offices constructedValue16.0016.0022.00
    DateFebruary 28, 2023February 15, 2024February 29, 2028
    Comment
  • Number of line ministry buildings, laboratories, offices renovatedValue17.0021.0027.00
    DateFebruary 28, 2023February 15, 2024February 29, 2028
    Comment