Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
P177765
Closed
Paula Restrepo Cadavid , Diana Rubiano Vargas, Bledi Celiku
Republic of Peru
October 18, 2021
(as of board presentation)
March 31, 2022
September 29, 2022
US$ 0.00 million
Ministry of Economy and Finance
2022
US$ 500.00 million
N/A
March 24, 2023
June 30, 2023
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 500.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 4, 2022 | IBRD-93630 | Fee Charges | 1,250,000.00 |
Dec 15, 2023 | IBRD-93630 | Int Charges | 265,900.47 |
Jun 15, 2023 | IBRD-93630 | Int Charges | 2,030,144.00 |
Jun 15, 2023 | IBRD-93630 | Int Charges | 78,767.13 |
Mar 31, 2022 | IBRD-93630 | Loan Commitment | 500,000,000.00 |
Jun 15, 2024 | IBRD-93630 | Int Charges | 99,416.81 |
Jun 15, 2024 | IBRD-93630 | Int Charges | 16,251,555.00 |
Dec 15, 2023 | IBRD-93630 | Int Charges | 15,311,115.00 |
Nov 14, 2022 | IBRD-93630 | Loan Disb | 500,000,000.00 |
Jun 15, 2023 | IBRD-93630 | Int Charges | 13,323,966.00 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2023-03-28 |
Progress towards achievement of PDO | Satisfactory | 2023-03-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-03-28 |
Program Management | Satisfactory | 2023-03-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Allocation reports are prepared and published, in line with Peru's sustainable bond framework | Value | 0.00 | 1.00 | 2.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Reduction in the average time to develop and approve technical dossiers of investments applying the Building Information Modeling (BIM) methodology (%) | Value | 0.00 | 0.00 | 10.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Number of detailed EIAs and EIA modifications that are evaluated within the timeframe established by the regulatory framework, and that receive on time binding technical opinions (%) | Value | 33.00 | 0.00 | 67.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Number of people living in areas with local Emergency Operation Centers (EOCs) operating according to new guidelines. | Value | 0.00 | 311976.00 | 2000000.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Number of people living in cities or populated settlements with urban planning instruments that integrate disaster risk management,public spaces management in accordance with Law No. 31313 | Value | 0.00 | 0.00 | 5500000.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Number of housing projects from MiVivienda certified with the new Technical Code for Sustainable Construction | Value | 0.00 | 0.00 | 300.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Reduction of GHG emissions and local pollutants (PM2.5, SO2 and NOx) | Value | 0.00 | 0.00 | 0.92 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Solar Home Systems (SHS) capacity provided by PPPs (MW) | Value | 0.00 | 0.00 | 6.50 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Nominal power of non-conventional renewable energy generation awarded in the first supply auction that introduce hourly blocks (MW) | Value | 0.00 | 0.00 | 50.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |
Annual Energy savings from public sector buildings and energy efficient appliances (Gwh) | Value | 0.00 | 0.00 | 70.00 |
Date | December 1, 2021 | December 21, 2022 | June 30, 2023 | |
Comment |