Skip to Main Navigation

First Nepal Green, Resilient and Inclusive Programmatic DPC

Development Objective

The development objective is to improve the enabling environment for Nepal's green, climate-resilient, inclusive development pathway.

Key Details

Project Details

  • P177776

  • Closed

  • Stephen Danyo

  • Nepal

  • Nepal

  • February 24, 2022

  • (as of board presentation)

    July 14, 2022

  • September 9, 2022

  • US$ 0.00 million

  • Ministry of Finance

  • South Asia

  • 2023

  • US$ 100.00 million

  • N/A

  • July 8, 2024

  • June 30, 2023

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 1, 2024 IDA-71900 Int Charges 369,268.10
Feb 1, 2023 IDA-71900 Int Charges 265,080.10
Jul 14, 2022 IDA-71900 Loan Commitment 100,000,000.00
Aug 1, 2023 IDA-71900 Int Charges 369,523.88
Aug 1, 2023 IDA-71900 Int Charges 369,523.88
Aug 1, 2023 IDA-71900 Int Charges 6,103.20
Aug 1, 2023 IDA-71900 Int Charges 6,103.20
Feb 1, 2024 IDA-71900 Int Charges 2,725.88
Aug 1, 2024 IDA-71900 Int Charges 940.55
Aug 1, 2024 IDA-71900 Int Charges 366,838.12
Aug 1, 2024 IDA-71900 Int Charges 366,838.12
Aug 1, 2024 IDA-71900 Int Charges 940.55
Feb 1, 2024 IDA-71900 Int Charges 2,725.88
Sep 21, 2022 IDA-71900 Loan Disb 95,593,448.00
Feb 1, 2023 IDA-71900 Int Charges 265,080.10
Feb 1, 2024 IDA-71900 Int Charges 369,268.10

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Satisfactory 2023-06-28
Progress towards achievement of PDO Satisfactory 2023-06-28
Monitoring and Evaluation Satisfactory 2023-06-28
Overall Implementation Progress (IP) Satisfactory 2023-06-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Results Indicator #1A: Share of newly registered two-, three-, and four-wheeled vehicles that are electricValue1.001.0010.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #1B. Share of newly registered internal combustion engine vehicles (two-, three-, and four-wheelers) that meet the Euro 4 or higher standardValue1.001.0090.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #2. Effective, inclusive, and transparent land classification and planning framework is in placeValueNoNoYes
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results indicator #3. Automatic hydrological monitoring stations and radar that are fully operational in additional locationsValue0.000.0025.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results indicator #4. Strategic Environmental and Social Assessment (SESAs) carried out for policies, programs, and strategic plansValue0.000.001.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Result indicator #5: Tourism concession contracts issued under the new reformsValue0.000.002.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #6A. Land area covered by an approved forest management plan in line with the Forest Regulation and that includesclimate outcomes and documented women’s participation in the plan.Value2903825.002903825.002949325.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results indicator #8. Increase in the proportion of sectoral spending at the federal and provincial levels for climate-smart agriculture investmentsValue0.000.0030.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #9A. River Basin Offices established at the river basin levelValue0.000.004.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #9B. Palikas* that collect Water, Sanitation and Hygiene (WASH) data using the National WASH Management Information System, including at schools and health centersValue0.000.0040.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #6B. Share of annual income earned by forest users’ groups that is spent on women empowerment and female entrepreneurship activitiesValue0.000.0020.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results indicator #7. Social protection programs in which the respective delivery system is used for the provision of relief and recovery in response to a shock due to an adverse natural eventValue0.000.001.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment
  • Results Indicator #10. Increased investment flows to Solid Waste Management (SWM) at federal and local levels, from both public andprivate sourcesValue0.000.001000000.00
    DateDecember 31, 2021June 26, 2023December 31, 2026
    Comment