Food Systems Resilience Program for Eastern and Southern Africa (Phase 3) FSRP

Abstract*

The development objectives of the Third Phase of the Food Systems Resilience Program for Eastern and Southern Africa Project for Eastern and Southern Africa, Kenya, Comoros, Malawi, Somalia are to increase resilience of food systems and the Recipient’s preparedness for food insecurity in project areas, and, in case of an eligible crisis or emergency, to respond promptly and effectively to it. The project comprises of six components. The first component...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to increase resilience of food systems and the Recipient’s preparedness for food insecurity in Project areas, and, in case of an Eligible Crisis or Emergency, to respond promptly and effectively to it.

Key Details

Project Details

  • P177816

  • Active

  • Benjamin Billard , Bobojon Yatimov, Jeehye Kim, Ghada Elabed, Mampionona Amboarasoa

  • The Republic of Malawi,The Republic of Kenya,The Union of Comoros,The Federal Republic of Somalia,African Union

  • Eastern and Southern Africa

  • March 3, 2023

  • (as of board presentation)

    May 31, 2023

  • June 29, 2023

  • US$ 375.00 million

  • Ministry of Agriculture, Malawi,Ministry of Agriculture & Livestock Development (MoALD), Kenya,Ministry of Agriculture and Irrigation (MoAI), Somalia,African Union Commission,Ministry of Agriculture, Fisheries, Environment, Tourism and Handicrafts (MAPETA), Comoros

  • Eastern and Southern Africa

  • 2023

  • US$ 682.00 million

  • N/A

  • June 28, 2024

  • August 31, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Agriculture and Food Security Program 15.00
IDA Credit 150.00
PROBLUE MDTF 3.00
FoodSystems2030 Umbrella Program 16.00
Sec Agr Commercialization and Resilience Enhancem MDTF 45.00
IDA Grant 453.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 603.00
IBRD + IDA Commitment 603.00
Lending Instrument
Grant Amount 79.00
Total Project Cost** 375.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 8, 2024 IDA-E1840 Loan Disb 765,278.56
Feb 1, 2024 IDA-E1840 Loan Disb 20,000,000.00
Jun 14, 2024 IDA-E1830 Loan Disb 999,323.10
Apr 10, 2024 IDA-E1830 Loan Disb 32,524.72
Jul 19, 2024 IDA-E1840 Loan Disb 320,575.60
Jul 15, 2024 IDA-E1820 Loan Disb 1,111,924.60
Aug 9, 2024 IDA-E1830 Loan Disb 150,709.33
Dec 12, 2023 IDA-E1830 Loan Disb 2,159,200.00
Aug 21, 2023 IDA-E1850 Loan Disb 10,000,000.00
Jul 11, 2024 IDA-E1850 Loan Disb 1,000,000.00
Jul 18, 2024 IDA-E1840 Loan Disb 1,339,238.90
Aug 17, 2023 IDA-E1850 Loan Disb 5,000,000.00
Jun 28, 2024 IDA-E1840 Loan Disb 573,959.25
Aug 13, 2024 IDA-73270 Loan Disb 10,923,500.00
Aug 15, 2024 IDA-73270 Loan Disb 22,021,000.00
May 31, 2023 IDA-E1850 Loan Commitment 150,000,000.00
May 31, 2023 IDA-E1840 Loan Commitment 250,000,000.00
May 31, 2023 IDA-73270 Loan Commitment 50,000,000.00
May 31, 2023 IDA-73280 Loan Commitment 100,000,000.00
May 31, 2023 IDA-E1820 Loan Commitment 13,000,000.00
May 31, 2023 IDA-E1830 Loan Commitment 40,000,000.00
Feb 6, 2024 IDA-E1840 Loan Disb 17,200,000.00
Apr 23, 2024 IDA-E1850 Loan Disb 21,000,000.00
Aug 22, 2024 IDA-E1850 Loan Disb -16,000,000.00
May 13, 2024 IDA-E1830 Loan Disb 94,593.91
Mar 8, 2024 IDA-E1830 Loan Disb 246,298.28
Jul 15, 2024 IDA-E1830 Loan Disb 81,083.12

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-03-25
Procurement Moderately Satisfactory 2025-03-25
Financial Management Satisfactory 2025-03-25
Monitoring and Evaluation Satisfactory 2025-03-25
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-25
Progress towards achievement of PDO Moderately Satisfactory 2025-03-25
Procurement Moderately Satisfactory 2025-03-25
Project Management Satisfactory 2025-03-25
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-25
Financial Management Satisfactory 2025-03-25
Monitoring and Evaluation Satisfactory 2025-03-25
Project Management Satisfactory 2025-03-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction of food insecure people in Project-targeted areasValue0.000.0027.00
    DateAugust 20, 2023February 1, 2024August 31, 2029
    Comment
  • Farmers adopting resilience-enhancing technologies and practicesValue0.000.00611600.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.003.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which are female farmersValue0.000.0040.00
    Date
    Comment
  • KenyaValue0.000.0020.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.0012000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which are female farmersValue0.000.0030.00
    Date
    Comment
  • KenyaValue0.000.00300000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which are female farmersValue0.000.0020.00
    Date
    Comment
  • MalawiValue5000.000.0089600.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which are female farmersValue0.000.0030.00
    Date
    Comment
  • SomaliaValue0.000.00210000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which are female farmersValue0.000.0015.00
    Date
    Comment
  • Land area under sustainable land management practicesValue0.000.00596600.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.0010000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.00250000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.0036600.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.00300000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Increase in volume of agricultural production sold in domestic and regional marketsValue0.000.0030.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which sold in the domestic marketValue0.000.0030.00
    Date
    Comment
  • of which sold in regional marketsValue0.000.0015.00
    Date
    Comment
  • ComorosValue0.000.006.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which sold in the domestic marketValue0.000.003.00
    Date
    Comment
  • of which sold in regional marketsValue0.000.000.00
    Date
    Comment
  • KenyaValue0.000.0020.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which sold in the domestic marketValue0.000.0045.00
    Date
    Comment
  • of which sold in regional marketsValue0.000.0020.00
    Date
    Comment
  • MalawiValue0.000.0030.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which sold in the domestic marketValue0.000.008.00
    Date
    Comment
  • of which sold in regional marketsValue0.000.007.00
    Date
    Comment
  • SomaliaValue0.000.0025.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which sold in the domestic marketValue0.000.004.00
    Date
    Comment
  • of which sold in regional marketsValue0.000.0011.00
    Date
    Comment
  • Policy products adopted with Project’s support related to agriculture, natural resource management, and food systems resilienceValue0.000.0045.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • AUValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0020.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • of which SomaliaValue0.000.00150.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Land area restored, reforested or afforestedValue0.000.0096447.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.00300.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.001000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Somalia gender-sensitive technologies and practicesValue0.000.0015.00
    Date
    Comment
  • KenyaValue0.000.0020000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.00350000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Farmers accessing agrometeorological data information and advice, market information, or other digital support services on climate and market risk managementValue0.000.00980000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which femaleValue0.000.00419000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Somalia womenValue0.000.0075000.00
    Date
    Comment
  • MalawiValue0.000.00447.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which ComorosValue0.000.0010000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0075000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Regional knowledge sharing mechanisms established by the ProjectValue0.000.0037.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Beneficiaries satisfied with the Project’s interventionsValue0.000.0085.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Water users’ associations and farmer or community organizations established or strengthened for agricultural water and landscape managementValue0.000.00580.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • AUValue0.000.0012.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Comoros femaleValue0.000.002000.00
    Date
    Comment
  • AUValue0.000.0090.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.002.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.002.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which KenyaValue0.000.00600000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.00275.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.002.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Kenya femaleValue0.000.0075000.00
    Date
    Comment
  • ComorosValue0.000.0080.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.001.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which MalawiValue0.000.0020000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue1.000.003.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Malawi femaleValue0.000.005000.00
    Date
    Comment
  • SomaliaValue0.000.00300.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0020.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.0075.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.000.007044.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Area provided with new irrigation or drainage servicesValue0.000.005244.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Area provided with improved irrigation or drainage servicesValue0.000.001800.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.0080.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.00350000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Somalia femaleValue0.000.0065000.00
    Date
    Comment
  • of which Comoros area provided with new irrigation or drainage servicesValue0.000.00100.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Change in the households dietary diversity score (HDDS) among targeted beneficiariesValue0.000.0015.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Comoros area provided with improved irrigation or drainage servicesValue0.000.00100.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Kenya area provided with new irrigation or drainage servicesValue0.000.00800.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0090.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Kenya area provided with improved irrigation or drainage servicesValue0.000.00200.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.0010.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which Malawi provided with new irrigation or drainage servicesValue0.000.003844.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Grievances registered through the Program GRM and addressedValue0.000.0090.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Somalia area provided with new irrigation or drainage servicesValue0.000.00500.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • AUValue0.000.0090.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.0090.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which Somalia area provided with improved irrigation or drainage servicesValue0.000.001500.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Decrease in yield gap between program beneficiary female and male farmersValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.00100.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.0090.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • SomaliaValue0.000.0090.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • SomaliaValue0.000.0025.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Agricultural landscape and natural resource management plans developed with Project supportValue0.000.00166.00
    DateMay 17, 2023February 1, 2024June 30, 2029
    Comment
  • Climate-smart agriculture technologies and practices transferred to extension services with Project supportValue0.000.00365.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Marketing infrastructure constructed or rehabilitatedValue0.000.00352.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Regionally harmonized policy frameworks and legislation facilitated by Regional Economic Communities (RECs) through the ProjectValue0.000.0016.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Direct program beneficiaries reachedValue0.000.00984400.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which womenValue0.000.00407200.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • AUValue0.000.003.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • ComorosValue0.000.0016.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which gender-sensitive technologies and practicesValue0.000.0036.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which implemented with Project supportValue0.000.00114.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • ComorosValue0.000.001.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.0026.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which ComorosValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which ComorosValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.001.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Comoros implemented with Project supportValue0.000.001.00
    Date
    Comment
  • MalawiValue100.000.00280.00
    DateMay 17, 2023February 1, 2024June 29, 2029
    Comment
  • of which Comoros gender-sensitive technologies and practicesValue0.000.002.00
    Date
    Comment
  • ComorosValue0.000.00150000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • MalawiValue0.000.001.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which KenyaValue0.000.00104.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which KenyaValue0.000.00200.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Comoros womenValue0.000.004000.00
    Date
    Comment
  • of which Kenya implemented with Project supportValue0.000.0013.00
    Date
    Comment
  • SomaliaValue0.000.0030.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Kenya gender-sensitive technologies and practicesValue0.000.0030.00
    Date
    Comment
  • SomaliaValue0.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.00350000.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which MalawiValue5.000.0010.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • Agrifood SMEs and or cooperatives supported by the ProjectValue0.000.001205.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which MalawiValue0.000.004.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Malawi gender-sensitive technologies and practicesValue1.000.003.00
    Date
    Comment
  • ComorosValue0.000.005.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Malawi implemented with Project supportValue0.000.003.00
    Date
    Comment
  • of which Kenya womenValue0.000.0050000.00
    Date
    Comment
  • MalawiValue40000.000.00134400.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • KenyaValue0.000.00340.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which SomaliaValue0.000.0048.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Malawi womenValue20000.000.0030000.00
    Date
    Comment
  • MalawiValue275.000.00560.00
    DateMay 17, 2023February 1, 2024August 31, 2029
    Comment
  • of which Somalia implemented with Program supportValue0.000.0025.00
    Date
    Comment