Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 352.62 |
P177823
Active
Chloe Viola , Christophe Prevost
Dominican Republic
June 1, 2022
(as of board presentation)
March 24, 2023
May 30, 2024
US$ 3190.56 million
National Water and Sewerage Institute (INAPA),La Vega Water and Sewerage Corporation (CORAAVEGA),Santiago Water and Sewerage Corporation (CORAASAN),National Institute for Hydraulic Resources (INDRHI),Ministry of Economy, Planning, and Development (MEPyD)
2023
US$ 250.00 million
N/A
June 26, 2024
December 31, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 352.62 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 250.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 3190.56 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 24, 2023 | IBRD-94900 | Loan Commitment | 250,000,000.00 |
Jul 11, 2024 | IBRD-94900 | Loan Disb | 1,078,480.10 |
Aug 30, 2024 | IBRD-94900 | Loan Disb | 56,250,000.00 |
May 30, 2024 | IBRD-94900 | Fee Charges | 625,000.00 |
May 30, 2024 | IBRD-94900 | Loan Disb | 625,000.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Strengthened WSS performance monitoring | Value | 0.22 | 0.48 | 0.33 | 0.22 | 0.48 | 0.33 | 0.99 | 0.99 | 0.99 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Households serviced with safely managed water supply | Value | 0.00 | 0.00 | 34.70 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Reduced non-revenue water | Value | 0 | 0 | 0 | 0 | 0 | 0 | -13.0 | -15.9 | -9.3 |
Date | October 28, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Strengthened accountability and improved operational planning capacity | Value | Not Achieved. | Not Achieved. | 3 e. (i) Achievements against Performance Agreemen |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Households serviced with safely managed sanitation | Value | 0.00 | 0.00 | 76.30 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Methodology for water rights formalization developed and approved | Value | Not Achieved | Not Achieved | Achieved |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Number of learning pilots implemented | Value | 0.00 | 0.00 | 3.00 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Proposal for restructuring of the WRM institutional framework completed | Value | Not Achieved | Not Achieved | Achieved |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Percentage of women in engineering and technical positions | Value | 5.5 | 15.5 | 31.0 | 5.5 | 15.5 | 31.0 | 6.5 | 16.5 | 39.0 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
National water information system strengthened and used for decision-making | Value | Not Achieved | Not Achieved | Achieved |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |
Percentage point improvement in customer satisfaction | Value | Baselines established in Year 1 | Baselines established in year 1 | 15 | 15 | 15 |
Date | October 1, 2022 | June 11, 2024 | December 31, 2027 | |
Comment |