Gaza Emergency Support for Social Services.

Abstract*

Gaza’s healthcare system is struggling to respond to a large number of vulnerable populations with MHPSS needs due to chronic shortages of qualified healthcare workers. The Gaza Rapid Needs Damage Assessment shows that the May 2021 conflict has resulted in an enormous need for MHPSS services to address psychosocial trauma. Yet, disrupted by the ongoing COVID-19 outbreak and further weakened by extensive damage to key healthcare facilities and providers...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide selected social services, short-term cash for services, and online employment opportunities to the most vulnerable populations in Gaza.

Key Details

Project Details

  • P177897

  • Active

  • Samira Hillis , Emily Chapman

  • NGO Development Center

  • West Bank and Gaza

  • April 26, 2022

  • (as of board presentation)

    June 7, 2022

  • September 6, 2022

  • US$ 7.00 million

  • N/A

  • March 25, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Special Financing 7.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 7.00
Total Project Cost** 7.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-28
Project Management Satisfactory 2024-10-28
Procurement Satisfactory 2024-10-28
Financial Management Satisfactory 2024-10-28
Monitoring and Evaluation Satisfactory 2024-10-28
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of individuals that are provided MHPSS or relevant health services through the projectValue0.000.0030000.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Number of beneficiaries receiving cash for services from the ProjectValue0.000.001000.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • of which womenValue0.000.0015000.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • of which, womenValue0.000.00500.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of recipients of MHPSS or relevant health services through the project satisfied with the quality of the services receivedValue0.000.0060.00
    DateApril 11, 2022March 28, 2024June 30, 2025
    Comment
  • Number of beneficiaries among those receiving e-work support that have performed at least one paid freelancing job during the support period or six months after thatValue0.000.00200.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • of which, womenValue0.000.00100.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of individuals receiving temporary economic support through C4S that are satisfied with the support provided by the ProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of male direct beneficiaries of e-work that are satisfied with the support provided by the ProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of feedback cases that have been resolved and responded to within 30 daysValue0.000.0060.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of female individuals receiving temporary economic support through C4S that are satisfied with the support provided by the ProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Number of youth benefiting from e-work support through the projectValue0.000.00400.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of male individuals receiving temporary economic support through C4S that are satisfied with the support provided by theProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of feedback cases that have been resolved and responded to within 30 daysValue0.000.0060.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • WomenValue0.000.00200.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Number of members from households where individuals receive C4S from the ProjectValue0.000.005500.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment
  • Percentage of direct beneficiaries of e-work that are satisfied with the support provided by the ProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024January 30, 2025
    Comment
  • Percentage of female direct beneficiaries of e-work that are satisfied with the support provided by the ProjectValue0.000.0080.00
    DateApril 1, 2022March 28, 2024June 30, 2025
    Comment