Cairo Alexandria Trade Logistics Development Project

Abstract*

The Project will build a railway bypass to the congested railway network around greater Cairo. This bypass will improve the efficiency of freight transport between the Alexandria Sea Port and Greater Cairo. Coupled with ongoing improvements to the railway lines between Cairo and Nag Hamadi under the RISE Project, freight trains can reach Upper Egypt. The bypass includes a greenfield segment starting at the Bani Salamah station on the line connecting...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the performance and support the decarbonization of the logistics and transport sectors in the Alexandria-6th October-Greater Cairo Area railway corridor.

Key Details

Project Details

  • P177932

  • Active

  • Arturo Ardila Gomez , Soran Ali, Salma Hany Ibrahim

  • Ministry of Finance, Egypt,Arab Republic of Egypt- Ministry of International Cooperation

  • Egypt, Arab Republic of

  • April 8, 2022

  • (as of board presentation)

    September 29, 2022

  • December 14, 2023

  • US$ 998.00 million

  • Ministry of Transport, Egypt,Egyptian National Railways - Ministry of Transport

  • Middle East and North Africa

  • 2023

  • US$ 400.00 million

  • N/A

  • April 4, 2024

  • September 28, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 400.00
Borrowing Country's Fin. Intermediary/ies 598.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 400.00
IDA Commitment N/A
IBRD + IDA Commitment 400.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 998.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 14, 2023 IBRD-94460 Loan Disb 1,000,000.00
Dec 14, 2023 IBRD-94460 Fee Charges 1,000,000.00
Sep 29, 2022 IBRD-94460 Loan Commitment 400,000,000.00
May 15, 2024 IBRD-94460 Int Charges 29,026.98
May 15, 2024 IBRD-94460 Int Charges 1,351,368.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2025-02-03
Procurement Satisfactory 2025-02-03
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-03
Progress towards achievement of PDO Satisfactory 2025-02-03
Project Management Moderately Satisfactory 2025-02-03
Monitoring and Evaluation Satisfactory 2025-02-03

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 2. Freight traffic volumes between AP, the GCA and Upper EgyptValue500000.00500000.00112000.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • 1. Containers handled by rail between AP and DP6Value0.000.00184000.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • Net greenhouse gas (GHG) emissionsValue0.000.001136.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.6 Female last-year university students and/or recent graduates from engineering faculties trained by the ENR in a one month training programValue0.000.00210.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • 2.2.2 Signaling towers commissioned in the Marazik–Wahat sectionValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 29, 2028
    Comment
  • 1.7 Policy reform preparatory analysis for IACValueNoNoYes
    DateApril 28, 2022June 15, 2023December 31, 2025
    Comment
  • 2.2.3 Signaling towers commissioned in the El Bashteel-Itay El Baroud segmentValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 29, 2028
    Comment
  • 1.8 Independent Safety RegulatorValueNoNoYes
    DateOctober 3, 2022June 15, 2023June 29, 2029
    Comment
  • 2.2 4. Signaling towers commissioned in the El Itihad-Tafaroa segmentValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 29, 2028
    Comment
  • 1.9 Enabling private capital mobilization (PCM) for the railway sectorValueNoNoYes
    DateSeptember 30, 2022June 15, 2023June 29, 2029
    Comment
  • 2.3 Centralized Traffic Control Centers (CTC) commissioned in Alexandria – October 6 -Greater CairoValue0.000.003.00
    DateApril 28, 2022June 15, 2023March 30, 2029
    Comment
  • 1.10 Decarbonization roadmap for the ENR& Green investment studyValueNoNoYes
    DateSeptember 30, 2022June 15, 2023June 29, 2029
    Comment
  • 2.4 Safety culture in railway design and operationValue0.000.00120.00
    DateApril 28, 2022June 15, 2023December 28, 2029
    Comment
  • 2.5 Safety culture adoption as FWSI (Fatalities and Weighted Serious Injuries) dataValue2.262.261.70
    DateApril 29, 2022June 15, 2023December 28, 2029
    Comment
  • 1.1 Steering Committee established and meets periodicallyValueNoYesYes
    DateApril 28, 2022June 15, 2023June 28, 2029
    Comment
  • 2.1 Construction progress works implemented through GARBValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 31, 2024
    Comment
  • 1.2 Project-affected people working group to meet regularlyValue0.000.0020.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • 1.3 Project Stakeholders working group to meet regularlyValue0.000.0020.00
    DateApril 28, 2022June 15, 2023April 12, 2023
    Comment
  • 1.4 Grievances registered related to the delivery of project benefits that are addressedValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 28, 2029
    Comment
  • 2.2 Signaling towers commissioned on the railway bypass around the Greater Cairo AreaValue0.000.00100.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • 1.5 Women employed in ENR after ENR upgrades its childcareValue0.000.0050.00
    DateApril 28, 2022June 15, 2023June 29, 2029
    Comment
  • 2.2.1 Signaling towers commissioned in the Greenfield segment linking the Bashteel–Itay El Baroud segment to the Marareek-Wahat lineValue0.000.00100.00
    DateApril 28, 2022June 15, 2023December 29, 2028
    Comment