Additional Financing for Resilient Kerala Program

Development Objective

The objective of the Program is to enhance Kerala’s resilience against the impacts of climate change and natural disasters, including disease outbreaks and pandemics.

Key Details

Project Details

  • P177980

  • Active

  • Elif Ayhan , Balakrishna Menon Parameswaran, Natsuko Kikutake

  • India

  • India

  • January 14, 2022

  • (as of board presentation)

    June 16, 2023

  • N/A

  • US$ 300.00 million

  • Government of Kerala

  • South Asia

  • 2023

  • US$ 150.00 million

  • N/A

  • August 6, 2023

  • June 30, 2028

  • BANK APPROVED

  • P174778

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 150.00
Borrower/Recipient 65.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Fiscal sustainability of GOK to cope with disease outbreaks and natural disasters is strengthenedValueGOK’s debt to Gross State Domestic Product (GSDP) The Debt-to-GSDP ratio in FY21/22 was estimated toGoK’s debt to Gross State Domestic Product (GSDP)
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • People are benefiting from flood early warning services and flood protection measures in Pamba BasinValueNot available.The development of flood forecasting and reservoir4.8 million people are benefiting from flood early
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Women’s access to post-disaster adaptive safety net payment is enhancedValueSafety net payments are processed to the head of tThe data from Public Distributions System has been100,000 women are benefiting from relief payments
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • People are benefiting from local DRM plans and One Health Community Surveillance systems in Pamba Basin districtsValueState level DRM plans and emergency response protoKerala State Disaster Management Authority (KSDMA)3.9 million people are benefiting from local DRM p
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Share of climate adaptation or mitigation investments by LSGIs in Pamba Basin districts has increasedValue0.000.0020.00
    DateApril 30, 2021September 26, 2022June 30, 2026
    Comment
  • People are benefiting from strengthened shoreline management and coastal protection measures in Coastal DistrictsValueNot available.Not available.2.34 million people are benefiting from strengthen
    DateDecember 15, 2022December 15, 2022March 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Disaster-related adaptive safety net system of GOK is strengthenedValueThere is no Unified Database of beneficiary househA state unified database has been built for the pr100,000 beneficiary households are receiving socia
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Disease surveillance, referral care and case management are improved at district level through Integrated Public Health Laboratories (IPHLs)ValueThe district level IPHLs have low capacity on outbThe needs assessment of the IPHLs are underway to 6,000,000 beneficiaries are utilizing specialized
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Disaster risk financing and insurance capacity of GoK and vulnerable households in Kerala are improvedValue$0 mobilized through market-based disaster risk fiGoK has given administrative approval and releasedDoF has mobilized $50 million using market-based d
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Capacity to track and respond to zoonotic disease outbreaks of human importance in a timely manner is strengthenedValueNo formal district level One Health (OH) coordinatThe state government has decided to launch a One HDoHFW has identified and controlled at least one z
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Integrated River Basin Management Plan is developed and implemented for Pamba BasinValueNo Integrated River Basin Management Plan has beenThe development of flood forecasting and reservoirImplemented river basin restoration and improvemen
    DateApril 19, 2021September 26, 2022March 31, 2028
    Comment
  • ULBs developed and sanctioned risk-informed Urban Master Plans and Priority Action PlansValueUrban Master Plans are not risk-informed; many areTechnical guideline and capacity building program 4 urban local bodies in Pamba Basin districts have
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Disaster and Climate Action Tracker (DCAT) tool is developed and adopted for assessing climate adaptation and mitigation investmentsValueNoNoYes
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Farmer Producer Organizations (FPOs) have increased access to new and organized marketsValue12 FPOs exist across all Pamba Basin districts.Small Farmers’ Agribusiness Consortium, Kerala (SF15 FPOs have increased access of farmers to new an
    DateApril 30, 2021September 26, 2022June 30, 2026
    Comment
  • Climate risk Information is integrated into local body DRM plansValueThere lacks of integration and use of local level To rectify systemic bias, bias correction is done 150 LGs have been assessed through DCAT and achiev
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Female members in the Board of Directors of all FPOsValue5.005.0025.00
    DateApril 30, 2021September 26, 2022June 30, 2026
    Comment
  • Capacity of GOK is enhanced on disaster and climate risk-informed urban and DRM planningValueGOK lacks of capacity to integrate DRM and climateIn the area of risk informed master planning, a ca1700 trained LSG resource persons and functionarie
    DateApril 19, 2021September 26, 2022June 30, 2026
    Comment
  • Farmers in 16 AEUs have access to technical and financial support for AEU-wise designated cropsValue40 Lacs (4 million) farmers are registered in AIMI40 Lacs (4 million) farmers are registered in AIMI80,000 farmers across 16 AEUs have access to techn
    DateSeptember 26, 2022September 26, 2022June 30, 2026
    Comment
  • Core Road Network (CRN) is rehabilitated and/or maintained to meet resilient service standards in the Pamba BasinValueZero km of CRN is meeting resilient service standaThe Public Works Department (PWD) has notified the400 km of CRN is meeting resilient standards in Pa
    DateApril 30, 2021September 26, 2022June 30, 2026
    Comment
  • GoK has published document titled “Climate Budget” along with the Annual Budget for climate relevant sectors and initiated State Climate Resilience Plan.ValueLack of systematic environment and climate expendiLack of systematic environment and climate expendiImplementation of any two out of top five critical
    DateDecember 15, 2022December 15, 2022March 31, 2028
    Comment
  • A comprehensive Roadmap for Open Data to Strengthen Climate and Disaster Resilience has been developedValueLack of a Roadmap to guide the Open Data InitiativLack of a Roadmap to guide the Open Data InitiativRoadmap for Leveraging Open Data to Strengthen Cli
    DateDecember 15, 2022December 15, 2022March 31, 2028
    Comment
  • People received trainings on Open Data for building climate and disaster resilience from both public and private sectorsValue0.000.001500.00
    DateDecember 15, 2022December 15, 2022March 31, 2028
    Comment
  • Shoreline Management Plan is developed and investments to protect coastal erosion in critical sites carried outValueNo Long-term Shoreline Management Plan for the entNo Long-term Shoreline Management Plan for the entCoastal protection works completed in 30 km stretc
    DateDecember 15, 2022December 15, 2022March 31, 2028
    Comment