Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 6.20 |
P177987
Active
Laura Di Giorgio , Behnaz Bonyadian Dehkordi
Belize
November 15, 2021
(as of board presentation)
February 23, 2022
July 20, 2022
US$ 6.20 million
Ministry of Health and Wellness
2022
US$ 6.20 million
N/A
Substantial
December 30, 2025
Yes
BANK APPROVED
February 28, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 6.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 6.20 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 6.20 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 6.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 15, 2023 | IBRD-93440 | Int Charges | 1,484.30 |
Apr 15, 2024 | IBRD-93440 | Int Charges | 1,718.54 |
Apr 15, 2023 | IBRD-93440 | Int Charges | 14,615.87 |
Apr 15, 2023 | IBRD-93440 | Int Charges | 15.63 |
Oct 15, 2023 | IBRD-93440 | Int Charges | 7,485.60 |
Mar 8, 2023 | IBRD-93440 | Loan Disb | 1,227,726.00 |
Sep 8, 2023 | IBRD-93440 | Loan Disb | 168,951.00 |
Jul 20, 2022 | IBRD-93440 | Fee Charges | 15,500.00 |
Jul 20, 2022 | IBRD-93440 | Loan Disb | 15,500.00 |
Feb 23, 2022 | IBRD-93440 | Loan Commitment | 6,200,000.00 |
Apr 21, 2024 | IBRD-93440 | Loan Disb | 82,080.00 |
Apr 21, 2024 | IBRD-93440 | Loan Disb | -82,080.00 |
Apr 17, 2024 | IBRD-93440 | Loan Disb | 485,727.56 |
Dec 2, 2022 | IBRD-93440 | Loan Disb | 750,000.00 |
Oct 15, 2022 | IBRD-93440 | Int Charges | 119.21 |
Dec 4, 2023 | IBRD-93440 | Loan Disb | 440,553.30 |
Oct 26, 2023 | IBRD-93440 | Loan Disb | 267,001.90 |
Apr 15, 2024 | IBRD-93440 | Int Charges | 42.82 |
Apr 15, 2024 | IBRD-93440 | Int Charges | 90,214.53 |
Apr 15, 2024 | IBRD-93440 | Int Charges | 4,338.70 |
Oct 15, 2023 | IBRD-93440 | Int Charges | 60,568.42 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-11-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-06 |
Procurement | Moderately Satisfactory | 2024-11-06 |
Project Management | Moderately Satisfactory | 2024-11-06 |
Financial Management | Satisfactory | 2024-11-06 |
Monitoring and Evaluation | Satisfactory | 2024-11-06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Eligible population fully vaccinated | Value | 10.50 | 66.20 | 41.60 |
Date | August 27, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
Eligible male population fully vaccinated | Value | 10.50 | 64.60 | 41.60 |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
Eligible female population fully vaccinated | Value | 10.50 | 67.70 | 41.60 |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Mobile visits to the rural areas to strenghten COVID-19 immunization | Value | 0.00 | 1207.00 | 1600.00 |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
Increase in frontline workers knowledge about gender based violence (GBV) | Value | 0.00 | 78.00 | 75.00 |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
User satisfaction survey conducted and findings used to adjust the Belize vaccination strategy | Value | No | Yes | Yes |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |
Central Medical Storage Facility with ULT capacity constructed | Value | No | No | Yes |
Date | August 9, 2023 | February 21, 2024 | December 30, 2025 | |
Comment |
COVID-19 vaccines that meet the VAC procured | Value | 0.00 | 148800.00 | 148800.00 |
Date | October 15, 2021 | February 21, 2024 | December 30, 2025 | |
Comment |