Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 56.31 |
P178141
Active
Sateh El-Arnaout , Chaymae Belouali
Municipality of Casablanca
January 3, 2022
(as of board presentation)
June 22, 2022
N/A
US$ 156.31 million
Casa Prestations / UNITE DE GESTION DU PROGRAMME (UGP)
2022
US$ 100.00 million
N/A
December 24, 2023
June 30, 2026
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 56.31 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 156.31 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage Increase in Municipal Revenues excluding transfers from a baseline of 0% in CY 2015 | Value | 0.00 | 22.76 | 90.00 |
Date | March 31, 2016 | December 1, 2020 | March 31, 2026 | |
Comment |
Reduction in average number of days required for issuance of a building permit at the Municipality | Value | 72.00 | 39.00 | 30.00 |
Date | October 2, 2017 | December 1, 2020 | December 31, 2021 | |
Comment |
Households in disadvantaged neighborhoods provided with improved access to basic services | Value | 0.00 | 4069.00 | 8000.00 |
Date | October 2, 2017 | December 1, 2020 | December 31, 2022 | |
Comment |
Private capital mobilized for investments through new or additional value of PPP contracts | Value | 0.00 | 940.00 | 900.00 |
Date | October 2, 2017 | December 1, 2020 | December 31, 2021 | |
Comment |
Daily savings in fresh water use resulting from the treated reused wastewater system set up | Value | 0.00 | 0.00 | 8000.00 |
Date | December 29, 2017 | April 1, 2022 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in revenues administered by the municipality | Value | 0.00 | 15.12 | 90.00 |
Date | January 1, 2016 | December 6, 2021 | December 31, 2025 | |
Comment |
Number of kilometers of comprehensive street upgrading | Value | 0.00 | 68.77 | 125.00 |
Date | January 1, 2016 | December 1, 2020 | December 31, 2025 | |
Comment |
Simplification and digitalization of administrative transactions for the issuance of: (i) authorizat | Value | Platforms for the dematerialization of administrat | Dematerialized procedures for all business license | Dematerialized procedures for all business license |
Date | October 2, 2017 | December 1, 2020 | December 31, 2019 | |
Comment |
Annual rate of execution of the Municipality’s investment budget | Value | 0.00 | 35.00 | 80.00 |
Date | January 1, 2016 | June 30, 2021 | December 31, 2025 | |
Comment |
Female of households in disadvantaged neighborhoods provided with improved access to basic services | Value | 0.00 | 11000.00 | 22400.00 |
Date | January 1, 2016 | December 31, 2020 | December 31, 2022 | |
Comment |
Increase in operating surplus on the municipal budget | Value | 50.00 | 147.00 | 500.00 |
Date | January 1, 2016 | December 6, 2021 | December 31, 2025 | |
Comment |
Deployment of a system to manage citizen requests | Value | No standard GRM procedure | The system has been deployed in all districts. 17 | More than 60% of requests are adressed and closed |
Date | January 1, 2016 | December 31, 2020 | December 29, 2023 | |
Comment |
Households in disadvantaged neighborhoods provided with improved access to drinking water service | Value | 0.00 | 2217.00 | 5200.00 |
Date | January 1, 2016 | December 1, 2020 | December 31, 2022 | |
Comment |
Increase in women use of green spaces (Number) | Value | 0.00 | 0.00 | 15.00 |
Date | April 20, 2022 | April 20, 2022 | December 31, 2025 | |
Comment |