Skip to Main Navigation

Vietnam Partnership for Market Implementation

Abstract*

Vietnam has been experiencing a relatively high growth rate in socio-economic development with the diverse portfolio of GHG emitters in terms of abatement sizes, abatement costs, and constraints to mitigate GHG emissions. Developing and applying CPIs are critical to leverage businesses and individuals' incentives to seek out and exploit the lower-cost ways of reducing emissions. Pricing carbon delivers clear signals to innovators and entrepreneurs...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to facilitate Vietnam’s transition to a low-carbon economy through the implementation of carbon pricing instruments.

Key Details

Project Details

  • P178165

  • Active

  • Muthukumara Mani , Taisei Matsuki

  • State Bank of Vietnam

  • Viet Nam

  • January 24, 2022

  • (as of board presentation)

    July 21, 2023

  • N/A

  • US$ 5.00 million

  • Ministry of Natural Resources and Environment

  • East Asia and Pacific

  • 2024

  • US$ 5.00 million

  • N/A

  • Moderate

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • November 22, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Partnership for Market Implementation Facility 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.00
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2024-05-22
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-05-22
Progress towards achievement of PDO Moderately Unsatisfactory 2024-05-22
Progress towards achievement of PDO Moderately Satisfactory 2024-05-22
Overall Moderable 2024-05-22

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Commissioning of the Pilot National Crediting Program (NCP)ValueNoYes
    DateMay 31, 2023December 31, 2028
    Comment
  • Commissioning of the Pilot Emissions Trading Scheme (ETS)ValueNoYes
    DateMay 31, 2023December 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Issuance of the MRV guidelines/rules for the cement, steel and non-coal thermal powerValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Operationalization of a carbon trading exchange platformValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Operationalization of ETS allowance trading platformValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Establishment of the NCP Pilot Support FacilityValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Issuance on the regulation(s) on the scope, cap-setting, quota allocation and administration for the ETSValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Development of a just transition framework to map vulnerable groups, types of adverse impacts and response optionsValueNoYes
    DateMay 31, 2023December 31, 2027
    Comment
  • Operationalization of the national registryValueNoYes
    DateMay 31, 2023December 31, 2028
    Comment