Financier | Commitments |
---|---|
IDA Credit | 168.34 |
IDA Grant | 50.00 |
IDA Shorter Maturity Loan (SML) | 111.66 |
P178207
Active
Francis Ovanda Mbele , Theophile Bougna Lonla, Papa Ndiaye
Ministry of Public Works
June 14, 2022
(as of board presentation)
June 20, 2023
May 16, 2024
US$ 280.00 million
Ministry of Economy, Planning, and Regional Development
2023
US$ 330.00 million
N/A
High
June 30, 2029
Yes
BANK APPROVED
January 12, 2024
Financier | Commitments |
---|---|
IDA Credit | 168.34 |
IDA Grant | 50.00 |
IDA Shorter Maturity Loan (SML) | 111.66 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 330.00 |
IBRD + IDA Commitment | 330.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 280.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 20, 2023 | IDA-73510 | Loan Commitment | 111,660,000.00 |
Jun 20, 2023 | IDA-E2090 | Loan Commitment | 50,000,000.00 |
Jun 13, 2024 | IDA-73520 | Loan Disb | 1,647,938.90 |
May 16, 2024 | IDA-73520 | Loan Disb | 972,101.70 |
Jun 20, 2023 | IDA-73520 | Loan Commitment | 168,340,000.00 |
Jun 13, 2024 | IDA-73520 | Loan Disb | 13,183,511.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2025-06-20 |
Monitoring and Evaluation | Satisfactory | 2025-06-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-06-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-06-20 |
Procurement | Moderately Unsatisfactory | 2025-06-20 |
Project Management | Moderately Satisfactory | 2025-06-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The share of people with access to an all-weather passable road within five kilometers of the MDK road section (modified road access index). | Value | 80.00 | 80.00 | 91.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of health centers along the Mora–Dabanga–Kousséri road section with improved road access | Value | 0.00 | 0.00 | 20.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of health centers around around refugee camps with improved road access | Value | 0.00 | 0.00 | 3.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of refugees and host communities population with access to an all-weather passable road within five kilometers of the MDK road section. | Value | 0.00 | 0.00 | 123000.00 |
Date | July 3, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of markets along the Mora–Dabanga–Kousséri road section with improved road access | Value | 0.00 | 0.00 | 6.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Share of women with improved access to an all-weather passable road within five kilometers of the MDK road section. | Value | 0.00 | 0.00 | 30.00 |
Date | ||||
Comment |
Share of beneficiaries reporting satisfaction with the socio-economic infrastructures | Value | 0.00 | 0.00 | 85.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of markets around refugee camps with improved access to markets | Value | 0.00 | 0.00 | 3.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Average travel time between Mora and Kousséri | Value | 8.00 | 8.00 | 3.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of schools along the Mora–Dabanga–Kousséri road section with improved road access | Value | 0.00 | 0.00 | 41.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Length of MDK road vulnerable to identified climate change hazards (floods and heat). | Value | 205.00 | 205.00 | 0.00 |
Date | April 17, 2023 | September 14, 2023 | December 29, 2028 | |
Comment |
Number of schools around refugee camps with improved road access | Value | 0.00 | 0.00 | 10.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Institutional capacity of the decentralized PIUs of MINTP and MINEPAT (PSRDREN) improved | Value | No | No | Yes |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of water points constructed or rehabilitated with improved conditions | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of schools constructed or rehabilitated along the MDK road | Value | 0.00 | 0.00 | 20.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Road safety audits conducted | Value | No | No | Yes |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Length of road rehabilitated with safety and climate change resilient features along the MDK road section | Value | 0.00 | 0.00 | 212.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of health centers constructed or rehabilitated along the MDK road | Value | 0.00 | 0.00 | 12.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Proportion of complaints addressed timely | Value | 0.00 | 0.00 | 100.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Length of bridge rehabilitated | Value | 0.00 | 0.00 | 180.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of cattle markets constructed or rehabilitated along the MDK and roads connecting refugees camps and host communities | Value | 0.00 | 0.00 | 5.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of students enrolled in the internship Program within the project and MINTP | Value | 0.00 | 0.00 | 45.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Road safety measures introduced along the Mora-Dabanga-Kousseri | Value | No | No | Yes |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Construction or rehabilitation of community multimedia centers | Value | 0.00 | 0.00 | 3.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Climate change resilient features introduced along the Mora-Dabanga-Kousseri | Value | No | No | Yes |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Number of women’s groups supported through trainings and equipment provision | Value | 0.00 | 0.00 | 5.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Length of road connecting refugees camps and host communities rehabilitated with safety and climate change resilient features | Value | 0.00 | 0.00 | 150.00 |
Date | July 3, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Percentage of women from the internship Program who report being employed 12 months after they completed the internship | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Storage facilities rehabilitated/constructed reserved/leased for women | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Kilometer of communal and regional roads maintained and rehabilitated with safety and climate change resilient features along the MDK | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2023 | September 14, 2023 | June 29, 2029 | |
Comment |
Share of women enrolled in the internship Program within the project and MINTP | Value | 0.00 | 0.00 | 40.00 |
Date | ||||
Comment |