Emergency Food Security Project

Abstract*

The proposed Second Additional Financing scales up selected interventions to enhance food availability and production. Furthermore, it expands its scope to activities that create sustainable economic opportunities in agriculture and food systems through crop diversification and strengthened value chain linkages, ensuring the target households have the necessary means to access and acquire food. To align the project with the expanded scope, a number...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve food security through promoting resilience and commercialization of agriculture production systems for target beneficiaries.

Key Details

Project Details

  • P178280

  • Active

  • Azeb Mekonnen , Amanullah Alamzai

  • Food and Agriculture Organization (FAO)

  • Afghanistan

  • April 22, 2022

  • (as of board presentation)

    June 2, 2022

  • June 3, 2022

  • US$ 195.00 million

  • Food and Agriculture Organization (FAO)

  • South Asia

  • 2022

  • US$ 295.00 million

  • N/A

  • July 29, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 295.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 295.00
Total Project Cost** 195.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-10-11
Progress towards achievement of PDO Satisfactory 2024-10-11
Procurement Satisfactory 2024-10-11
Financial Management Satisfactory 2024-10-11
Monitoring and Evaluation Satisfactory 2024-10-11
Overall Implementation Progress (IP) Satisfactory 2024-10-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Wheat crop production increase (by target households) in project intervention areasValue0.0026.0025.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.00102690.00218000.00
    DateApril 15, 2022November 28, 2023June 30, 2025
    Comment
  • Farmers reached with agricultural assets or servicesValue0.00750000.001417000.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.00112603.00150000.00
    DateApril 15, 2022November 28, 2023April 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Certified wheat seeds distributed to farmersValue0.0030000.0047000.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Beneficiaries satisfied with support provided by the projectValue0.0092.5580.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Rehabilitated Irrigation CanalsValue0.00522.001123.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Of which femaleValue0.0091.7080.00
    DateApril 15, 2022November 28, 2023June 30, 2025
    Comment
  • Public grievances received and resolved within the prescribed timelineValue0.0091.1080.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Area cultivated for food production with the distributed seeds by the beneficiariesValue0.00239984.00360000.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Erosion control structures constructedValue0.0098.00140.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Female headed-households benefiting from support for production of higher nutrition value vegetables and legumesValue0.00111133.00150000.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Karezes restored/repaired through upper catchment managementValue0.0051.00150.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Days of short-term jobs created by projectValue0.005397260.007929000.00
    DateApril 15, 2022January 31, 2024June 30, 2025
    Comment
  • Beneficiaries with improved processing and post harvest management facilities (Number)Value0.000.0012000.00
    DateNovember 15, 2023November 15, 2023June 30, 2025
    Comment
  • Days of short-term jobs worked by female beneficiariesValue0.00101775.00300000.00
    DateApril 15, 2022November 28, 2023June 30, 2025
    Comment
  • Private Seed Enterprises with improved capacity to produce and market climate resilient seeds (Number)Value0.00100.00100.00
    DateApril 29, 2022November 15, 2023June 30, 2025
    Comment
  • Number of female potential cash for work beneficiaries reached with unconditional cash transfersValue0.00363660.000.00
    DateMarch 1, 2023January 31, 2024June 30, 2025
    Comment
  • Area planted with climate resilient vegetative coverageValue0.000.001800.00
    DateNovember 15, 2023November 15, 2023June 30, 2025
    Comment