Financier | Commitments |
---|---|
Green Climate Fund | 12.50 |
IDA Credit | 67.70 |
P178286
Active
Federico Querio , Jianping Zhao
Kyrgyz Republic
July 11, 2022
(as of board presentation)
June 28, 2023
August 28, 2024
US$ 77.00 million
Ministry of Energy
2023
US$ 80.20 million
N/A
February 22, 2024
June 30, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Green Climate Fund | 12.50 |
IDA Credit | 67.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 67.70 |
IBRD + IDA Commitment | 67.70 |
Lending Instrument | |
---|---|
Grant Amount | 12.50 |
Total Project Cost** | 77.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 28, 2023 | TF-C3809 | Loan Commitment | 10,000,000.00 |
Jun 28, 2023 | IDA-73700 | Loan Commitment | 67,700,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-03-24 |
Financial Management | Moderately Satisfactory | 2025-03-24 |
Monitoring and Evaluation | Satisfactory | 2025-03-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-24 |
Procurement | Moderately Satisfactory | 2025-03-24 |
Project Management | Moderately Satisfactory | 2025-03-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of hydropower constructed or rehabilitated | Value | 0.00 | 0.00 | 20.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Variable renewable energy enabled | Value | 0.00 | 0.00 | 100.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Net greenhouse gas (GHG) emission avoided | Value | 0.00 | 0.00 | 50.30 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transmission lines newly constructed/rehabilitated | Value | 0.00 | 0.00 | 105.50 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
ESIA/ESMP finalized and disclosed | Value | No | No | Yes |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Number of managerial and technical staff trained | Value | 0.00 | 0.00 | 300.00 |
Date | April 21, 2023 | September 25, 2023 | December 29, 2028 | |
Comment |
Substations added/rehabilitated | Value | 0.00 | 0.00 | 1.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Policy, measures and procedures conducive to integration of VRE developed and adopted | Value | No | No | Yes |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
IT system upgraded | Value | No | No | Yes |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Complaints received which are responded and resolved within the specified timeframe | Value | 0.00 | 0.00 | 90.00 |
Date | April 21, 2023 | September 25, 2023 | December 29, 2028 | |
Comment |
Climate resilient standards and guidelines developed and adopted | Value | No | No | Yes |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Increased generation from RE | Value | 0.00 | 0.00 | 88.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Increase in the share of women employed by participating companies in technical and managerial positions | Value | 10.00 | 0.00 | 20.00 |
Date | April 21, 2023 | September 25, 2023 | December 29, 2028 | |
Comment |
Reduction of average interruption duration per year in the project area | Value | 5760.00 | 0.00 | 1450.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Percentage increase in the share of women hired by participating companies in technical and managerial positions | Value | 0.00 | 0.00 | 2.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Total number of firms/businesses that are grid customers that benefit from improved resilience of the grid | Value | 0.00 | 0.00 | 122470.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Private capital enabled | Value | 0.00 | 0.00 | 60000000.00 |
Date | April 21, 2023 | September 25, 2023 | June 30, 2028 | |
Comment |
Technical standard adopted for resilient grid utilities | Value | No | No | Yes |
Date | October 31, 2022 | September 25, 2023 | October 31, 2028 | |
Comment |