Water Supply and Sanitation Access Program (PASEA) Project

Abstract*

The Democratic Republic of Congo (DRC), the largest and third most populous country in Sub-Saharan Africa, is rich in natural resources. With a total land area of 234 million ha, DRC’s size is equivalent to that of Western Europe. It has a low population density of 16.1 person per km2 and an estimated 89.6 million inhabitants , of which 54.4 percent live in rural areas. DRC is one of the world’s poorest countries, with a per capita gross domestic...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase access to basic drinking water supply and sanitation services in selected provinces of the DRC and to strengthen the capacity of the public and private sector for drinking water supply and sanitation service delivery

Key Details

Project Details

  • P178389

  • Active

  • Patrick Ndolo , Susanna Smets, Feriha Mugisha

  • Democratic Republic of the Congo

  • US$ 400.00 million

  • Ministry of Water Resources and Electricity

  • Eastern and Southern Africa

  • 2023

  • US$ 400.00 million

  • N/A

  • September 30, 2024

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 400.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 400.00
IBRD + IDA Commitment 400.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 12, 2024 IDA-73390 Loan Disb 6,054,726.00
Apr 9, 2024 IDA-73390 Loan Disb 11,280,193.00
Apr 4, 2024 IDA-73390 Loan Disb 660,668.00
Jun 9, 2023 IDA-73390 Loan Commitment 400,000,000.00
Jun 13, 2024 IDA-73390 Loan Disb 1,938,353.00
Mar 11, 2024 IDA-73390 Loan Disb 2,025,792.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2024-12-06
Monitoring and Evaluation Satisfactory 2024-12-06
Financial Management Moderately Satisfactory 2024-12-06
Progress towards achievement of PDO Satisfactory 2024-12-06
Project Management Satisfactory 2024-12-06
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to at least basic drinking water servicesValue0.000.002900.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Provincial Water Supply Units that are operational and monitor performance of water operatorsValue0.000.004.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Share of water operators with satisfactory operational performance as per their delegation contractsValue0.000.0075.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Provincial governments that have adopted a governance framework for urban sanitationValue0.000.004.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Sanitation and hygiene enterprises that are delivering product and servicesValue0.000.0040.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which basic drinking water servicesValue0.000.002750.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which safely managed drinking water servicesValue0.000.00150.00
    DateMay 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which in rural areasValue0.000.001900.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which in (peri-)urban areasValue0.000.001000.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which femaleValue0.000.001450.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • People provided with access to basic sanitation servicesValue0.000.002000.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which ending open defecationValue0.000.00300.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which in rural areasValue0.000.001450.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which in (peri-)urban areasValue0.000.00550.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which femaleValue0.000.001000.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • People completing Young Professional program at provincial project implementation unitsValue0.000.0050.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Households living in villages or neighborhoods that are certified as Open Defecation FreeValue0.000.00240.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Share of water systems constructed powered by renewable energyValue0.000.0095.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Social institutions installed with water, sanitation and hygiene facilitiesValue0.000.00500.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which femalesValue0.000.0015.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Local water operators with maintenance contracts for solar-powered water productionValue0.000.0080.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which health centersValue0.000.00150.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which continue in PPIU jobValue0.000.0025.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Local water operators trained in management, technical and commercial operationsValue0.000.00100.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Grievances resolved in timely and satisfactory mannerValue0.000.0080.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which schoolsValue0.000.00350.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which female grievances adequately resolvedValue0.000.0080.00
    Date
    Comment
  • of which are accessible, functional and maintainedValue0.000.000.00
    Date
    Comment
  • Urban centers under REGIDESO that reduce NRW with 10% over baselineValue0.000.008.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • National water supply policy with implementation plan adoptedValueNoNoYes
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Provinces that adopt a governance framework for water supply service delegationValue0.000.004.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Girls participating in menstrual hygiene management empowerment sessionsValue0.000.00123.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Graduates of higher professional and vocational education programs on solar pumped water systemsValue0.000.00550.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Girls that report reduced school absenteeism due to better hygienic environment and self-management skillsValue0.000.0050.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Installed treatment capacity of fecal sludge treatment plantsValue0.000.0050000.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Enterprises participating in sanitation e-voucher scheme installing toiletsValue0.000.0055.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which have a job within 6 months of graduatingValue0.000.00385.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • City Wide Inclusive Sanitation Plans published and implementation startedValue0.000.004.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which female graduatesValue0.000.00110.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Service delegation agreements signed for O&M of fecal sludge treatment plantsValue0.000.004.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which females in a job 6 months within graduatingValue0.000.0077.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Climate-informed WRM plan for Kasai sub-basin consulted and endorsedValue0.000.001.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Graduates from higher professional and vocational education programs relevant to sanitation and hygieneValue0.000.00500.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • Hydromet and groundwater monitoring stations installed and operational in Kasai basinValue0.000.0010.00
    DateJune 30, 2023October 16, 2023June 30, 2029
    Comment
  • of which in job 6 months after graduationValue0.000.000.00
    Date
    Comment
  • of which female graduatesValue0.000.000.00
    Date
    Comment
  • of which females in job within 6 months after graduationValue0.000.000.00
    Date
    Comment