Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
Borrower/Recipient | 1411.00 |
P178401
Active
Rajesh Koirala , Gang Qin, Xiawei Liao
People's Republic of China
November 23, 2022
(as of board presentation)
March 29, 2024
November 20, 2024
US$ 1200.00 million
Regional Economy Department of NDRC,Gansu Provincial Department of Water Resources,Shandong Provincial Department of Natural Resources
2024
US$ 300.00 million
N/A
March 6, 2024
June 30, 2029
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
Borrower/Recipient | 1411.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 29, 2024 | IBRD-96370 | Loan Commitment | 150,000,000.00 |
Mar 29, 2024 | IBRD-96380 | Loan Commitment | 150,000,000.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduced Pollutant loads (COD) entering rivers | Value | 0.00 | 0.00 | 9665.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Sequestered CO2eq due to ecosystem restoration | Value | 0.00 | 0.00 | 280333.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Number of technical documents for integrated landscape planning and decision making for ecosystem restoration and protection approved | Value | No | Six implementation plans in demonstration sub basi | |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Land area under sustainable landscape management practices | Value | 0.00 | 0.00 | 1217.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Hectares of terrestrial and aquatic areas under enhanced conservation and management | Value | 0.00 | 0.00 | 267.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Areas of wetlands in priority river basin locations restored, annual | Value | 0.00 | 0.00 | 7.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Areas of forests in priority river basin locations restored, annual | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Areas of improved forest management, annual | Value | 0.00 | 0.00 | 8933.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Number of township wastewater treatment plants upgraded or built | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Length of river channels in priority river basin segments restored, annual | Value | 0.00 | 0.00 | 16.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Areas of grasslands and other types of ecosystems restored, annual | Value | 0.00 | 0.00 | 36500.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Established number of ecosystem health monitoring and evaluation system pilots, annual | Value | 0.00 | 0.00 | 2.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Number of participants completing training and capacity building activities implemented at provincial, municipal and county levels (person times) | Value | 0.00 | 0.00 | 3300.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Women in leadership positions in ecosystem protection and restoration (proportion of women in both official and civil forest chiefsat the county level and below) | Value | 10.00 | 0.00 | 20.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Increased biodiversity monitored in selected program areas | Value | 0.00 | 0.00 | 20.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Number of rural villages newly covered with rural wastewater network | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2022 | December 31, 2028 | ||
Comment |
Of which are female participants (person times) | Value | 0.00 | 0.00 | 1200.00 |
Date | ||||
Comment |