China: Yellow River Basin Ecological Protection and Environmental Pollution Control Program (Gansu and Shandong)

Abstract*

The development objective of the China - Yellow River Basin Ecological Protection and Environmental Pollution Control Program (Gansu and Shandong) is to Program will support a subset of provincial YRB program activities in the Gansu and Shandong program areas. Three criteria were used to screen proposed activities to be included in the Program boundary: (a) Relevance - alignment with national priorities and the proposed development objectives of the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Program Development Objective is to improve land and water resource management and restore degraded ecosystems in selected areas in the Yellow River Basin in Gansu Province and Shandong Province.

Key Details

Project Details

  • P178401

  • Active

  • Rajesh Koirala , Gang Qin, Xiawei Liao

  • People's Republic of China

  • China

  • November 23, 2022

  • (as of board presentation)

    March 29, 2024

  • November 20, 2024

  • US$ 1200.00 million

  • Regional Economy Department of NDRC,Gansu Provincial Department of Water Resources,Shandong Provincial Department of Natural Resources

  • East Asia and Pacific

  • 2024

  • US$ 300.00 million

  • N/A

  • March 6, 2024

  • June 30, 2029

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00
Borrower/Recipient 1411.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1200.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 2024 IBRD-96370 Loan Commitment 150,000,000.00
Mar 29, 2024 IBRD-96380 Loan Commitment 150,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-17
Monitoring and Evaluation Satisfactory 2024-12-17
Overall Implementation Progress (IP) Satisfactory 2024-12-17

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduced Pollutant loads (COD) entering riversValue0.000.009665.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Sequestered CO2eq due to ecosystem restorationValue0.000.00280333.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Number of technical documents for integrated landscape planning and decision making for ecosystem restoration and protection approvedValueNoSix implementation plans in demonstration sub basi
    DateDecember 31, 2022December 31, 2028
    Comment
  • Land area under sustainable landscape management practicesValue0.000.001217.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Hectares of terrestrial and aquatic areas under enhanced conservation and managementValue0.000.00267.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Areas of wetlands in priority river basin locations restored, annualValue0.000.007.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Areas of forests in priority river basin locations restored, annualValue0.000.000.00
    DateDecember 31, 2022December 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Areas of improved forest management, annualValue0.000.008933.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Number of township wastewater treatment plants upgraded or builtValue0.000.000.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Length of river channels in priority river basin segments restored, annualValue0.000.0016.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Areas of grasslands and other types of ecosystems restored, annualValue0.000.0036500.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Established number of ecosystem health monitoring and evaluation system pilots, annualValue0.000.002.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Number of participants completing training and capacity building activities implemented at provincial, municipal and county levels (person times)Value0.000.003300.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Women in leadership positions in ecosystem protection and restoration (proportion of women in both official and civil forest chiefsat the county level and below)Value10.000.0020.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Increased biodiversity monitored in selected program areasValue0.000.0020.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Number of rural villages newly covered with rural wastewater networkValue0.000.000.00
    DateDecember 31, 2022December 31, 2028
    Comment
  • Of which are female participants (person times)Value0.000.001200.00
    Date
    Comment