Punjab Family Planning Program

Abstract*

The Program will increase access to quality family planning services in the project districts of Punjab through advocacy and political commitment, improved availability of family planning services increased demand of family planning commodities. The project will be a PforR and will consist of an investment project financing component to provide technical assistance, to strengthen the capacity of the implementing agency and improve their systems to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase utilization of effective quality family planning services in Punjab.

Key Details

Project Details

  • P178410

  • Active

  • Jahanzaib Sohail

  • Islamic Republic of Pakistan

  • Pakistan

  • March 9, 2022

  • (as of board presentation)

    July 12, 2023

  • September 25, 2023

  • US$ 11299.00 million

  • Population Welfare Department of the Province of Punjab,Primary and Secondary Healthcare Department of the Province of Punjab

  • South Asia

  • 2024

  • US$ 100.00 million

  • N/A

  • Low

  • June 30, 2027

  • TBD

  • BANK APPROVED

  • June 20, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 396.00
IDA Shorter Maturity Loan (SML) 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 11299.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 11, 2024 IDA-73840 Loan Disb 642,000.00
Dec 1, 2023 IDA-73840 Loan Disb 21,250,000.00
Jul 12, 2023 IDA-73840 Loan Commitment 100,000,000.00
Sep 4, 2024 IDA-73840 Loan Disb 2,872,500.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-03-17
Monitoring and Evaluation Satisfactory 2025-03-17
Overall Implementation Progress (IP) Satisfactory 2025-03-17

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • P&SHD facilities and PWD facilities have availability of the required mix of contraceptivesValueTBD
    DateJune 30, 2023June 30, 2027
    Comment
  • Improved modern Contraceptive Prevalence RateValueTBD
    DateJune 30, 2023June 30, 2027
    Comment
  • FP users have been counselled appropriatelyValueTBD
    DateJune 30, 2023June 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • A comprehensive gender responsive SBCC strategy developedValueNoYes
    DateJune 30, 2023June 30, 2027
    Comment
  • Procurement of FP commodities as per the individual annual projection executed individually by P&SHD and PWDValueNot measured
    DateJune 30, 2023June 30, 2027
    Comment
  • Additional FP users over last year as per projections individually by P&SHD and PWD facilitiesValueNot measured
    DateJune 30, 2023June 30, 2027
    Comment
  • Review and establishment of IT based information system by P&SHD and PWD for informed decision-making capturing commodities utilization, stock positions, forecasting and profile of FP usersValueNoYes
    DateJune 30, 2023June 30, 2027
    Comment
  • Surveys completed for i) PPFP/PAFP services ii) quality of FP counselling services and iii) mCPRValueNoYes
    DateJune 30, 2023June 30, 2027
    Comment
  • Advocacy workshop of key stakeholders from parliament, ministries and partners conductedValue0.000.002.00
    DateJune 30, 2023June 30, 2027
    Comment
  • TV talk shows/ debate on FP/population growth/climate change impact/ economic growth with parliamentariansValue0.000.004.00
    DateJune 30, 2023June 30, 2027
    Comment
  • BISP beneficiaries availed FP services at public and private facilities through voucher schemes in conjunction with clinical franchisingValue0.000.00234000.00
    DateJune 30, 2023June 30, 2027
    Comment
  • Districts have engaged the required number of community and religious leaders for FP messaging as agreed in the SBCC strategyValue9.000.000.00
    DateJune 30, 2023June 30, 2027
    Comment
  • Grievances that have been redressedValue0.000.0070.00
    DateJune 30, 2023June 30, 2027
    Comment
  • LHW-uncovered population are reached with FP servicesValue0.000.000.00
    DateJune 30, 2023June 30, 2027
    Comment
  • Performance based contract for social marketing developedValueNoYes
    DateJune 30, 2023June 30, 2027
    Comment
  • Additional deliveries/ abortion avail PPFP/PAFP (immediate post-partum/post-abortion) over baselineValueTBD
    DateJune 30, 2023June 30, 2027
    Comment
  • Population of districts of Punjab are covered by social marketing contractsValueNot measured
    DateJune 30, 2023June 30, 2027
    Comment
  • Timely release of allocated budgets for FP to P&SHD and PWDValueNo
    DateJune 30, 2023June 30, 2027
    Comment
  • High intensity mass media implementedValueNot measured2 education FP melas over a year, in each district
    DateJune 30, 2023June 30, 2027
    Comment