Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
P178534
Active
Nicolaas de Groot , Maria Ramirez
Agentine Republic
June 30, 2022
(as of board presentation)
June 27, 2023
October 20, 2023
US$ 200.00 million
Ministry of Public Works,Ministry of Economy
2023
US$ 200.00 million
N/A
Moderate
October 31, 2028
Yes
BANK APPROVED
February 13, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 1, 2024 | IBRD-95160 | Int Charges | 18,176.02 |
Jul 1, 2024 | IBRD-95160 | Int Charges | 247,978.40 |
Oct 20, 2023 | IBRD-95160 | Fee Charges | 500,000.00 |
Jan 1, 2024 | IBRD-95160 | Int Charges | 7,168.32 |
Jun 27, 2023 | IBRD-95160 | Loan Commitment | 200,000,000.00 |
Jan 1, 2024 | IBRD-95160 | Int Charges | 113,448.63 |
Oct 20, 2023 | IBRD-95160 | Loan Disb | 500,000.00 |
Jul 1, 2024 | IBRD-95160 | Int Charges | 33.88 |
Jul 1, 2024 | IBRD-95160 | Int Charges | 33.88 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2025-04-23 |
Monitoring and Evaluation | Satisfactory | 2025-04-23 |
Procurement | Satisfactory | 2025-04-23 |
Project Management | Satisfactory | 2025-04-23 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-04-23 |
Overall Implementation Progress (IP) | Unsatisfactory | 2025-04-23 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people with reduced flood exposure as a result of Project interventions | Value | 0.00 | 0.00 | 123000.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Number of cities that adopted improved integrated urban flood risk management practices as a result of the Project | Value | 0.00 | 0.00 | 10.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Number of people with reduced flood impacts as a result of Project interventions | Value | 0.00 | 0.00 | 818000.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Operation and management plans prepared for project interventions | Value | 0.00 | 0.00 | 100.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Events organized to engage civil society in flood-risk resilience, awareness, preparedness and management | Value | 0.00 | 0.00 | 10.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Grievances responded and/or resolved within the stipulated service standards for response times | Value | 0.00 | 0.00 | 100.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Number of cities with integration of green and/or blue interventions as a result of project's activities | Value | 0.00 | 0.00 | 5.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Development and endorsement of urban water management strategies and plans at watershed scale | Value | 0.00 | 0.00 | 3.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Change in percentage (increase) of the share of women in subnational organizations participating in water management decisions | Value | 0.00 | 0.00 | 5.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Creation of new public space as a result of green/blue interventions | Value | 0.00 | 0.00 | 30.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Officials and practitioners trained on increased resilience for flood-risk preparedness | Value | 0.00 | 0.00 | 150.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |
Subprojects that have incorporated feedback received on the beneficiaries participation process | Value | 0.00 | 0.00 | 30.00 |
Date | April 25, 2023 | September 27, 2023 | October 31, 2029 | |
Comment |