Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Local Beneficiaries | 33.00 |
Borrower/Recipient | 1.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 14.00 |
P178553
Active
Lucia Spinelli
Argentine Republic
June 6, 2022
(as of board presentation)
June 27, 2023
October 19, 2023
US$ 416.00 million
Secretariat of Energy
2023
US$ 400.00 million
N/A
Moderate
June 30, 2029
Yes
BANK APPROVED
February 7, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Local Beneficiaries | 33.00 |
Borrower/Recipient | 1.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 14.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 416.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 27, 2023 | IBRD-95210 | Loan Commitment | 400,000,000.00 |
Jan 1, 2024 | IBRD-95210 | Int Charges | 195,931.52 |
Oct 30, 2023 | IBRD-95210 | Loan Disb | 40,000,000.00 |
Jan 1, 2024 | IBRD-95210 | Int Charges | 195,931.52 |
Jan 1, 2024 | IBRD-95210 | Int Charges | 313,636.90 |
Jul 1, 2024 | IBRD-95210 | Int Charges | 1,044,136.20 |
Oct 19, 2023 | IBRD-95210 | Fee Charges | 1,000,000.00 |
Oct 19, 2023 | IBRD-95210 | Loan Disb | 1,000,000.00 |
Jul 1, 2024 | IBRD-95210 | Int Charges | 446,297.80 |
Jul 1, 2024 | IBRD-95210 | Int Charges | 446,297.80 |
Jul 1, 2024 | IBRD-95210 | Int Charges | 2,243.36 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2025-01-29 |
Procurement | Moderately Satisfactory | 2025-01-29 |
Project Management | Moderately Satisfactory | 2025-01-29 |
Financial Management | Moderately Satisfactory | 2025-01-29 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-01-29 |
Financial Management | Moderately Satisfactory | 2025-01-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-01-29 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-01-29 |
Procurement | Moderately Satisfactory | 2025-01-29 |
Project Management | Moderately Satisfactory | 2025-01-29 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-01-29 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-01-29 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with increased energy efficiency | Value | 0.00 | 0.00 | 1250000.00 |
Date | July 1, 2023 | September 22, 2023 | June 30, 2029 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 233000.00 |
Date | July 1, 2023 | September 22, 2023 | June 30, 2029 | |
Comment |
Projected energy or fuel savings | Value | 0.00 | 0.00 | 10170000000.00 |
Date | July 1, 2023 | September 22, 2023 | June 30, 2029 | |
Comment |
Projected energy or fuel savings | Value | 0.00 | 0.00 | 5900000000.00 |
Date | July 1, 2023 | September 22, 2023 | June 30, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of mini-grids | Value | 0.00 | 0.00 | 9.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
People provided with efficient refrigerators in households | Value | 0.00 | 0.00 | 576000.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Development of an assessment of the participation of rural women in employment in the renewable energy sector | Value | No | --- | Yes |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
People provided with new or improved energy access through mini-grids | Value | 0.00 | 0.00 | 43700.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Lifetime energy savings from the deployment of efficient appliances | Value | 0.00 | 0.00 | 2210.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Knowledge outputs and evidence produced to strengthen the energy sector's sustainability. | Value | 0.00 | 0.00 | 10.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Generation capacity of solar PV systems | Value | 0.00 | 0.00 | 9.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Energy efficiency campaigns launched | Value | 0.00 | 0.00 | 3.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
People provided with new or improved energy access through solar PV systems | Value | 0.00 | 0.00 | 136000.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Beneficiaries satisfied with the process to obtain a new and efficient refrigerator and resulting in improved energy efficiency | Value | 0.00 | 0.00 | 70.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
People trained on clean energy issues in connection with the Project | Value | 0.00 | 0.00 | 2000000.00 |
Date | July 1, 2023 | September 22, 2023 | June 30, 2029 | |
Comment |
People provided with new or improved energy access through solar thermal systems | Value | 0.00 | 0.00 | 24300.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
People provided with efficient lighting in community centers | Value | 0.00 | 0.00 | 680000.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
of which females | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to energy for productive uses | Value | 0.00 | 0.00 | 28600.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Lifetime energy savings from the deployment of efficient lighting in community centers | Value | 0.00 | 0.00 | 630.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Change in the time women spend on domestic/unpaid care work | Value | 0.00 | 0.00 | -10.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Beneficiaries satisfied with the process to obtain new and efficient lighting and resulting in improved energy efficiency | Value | 0.00 | 0.00 | 75.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Net greenhouse gas (GHG) emissions | Value | 0.00 | 0.00 | 19400.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |
Net greenhouse gas (GHG) emissions | Value | 0.00 | 0.00 | 58200.00 |
Date | July 1, 2023 | September 22, 2023 | May 31, 2029 | |
Comment |