Skip to Main Navigation

Integrated Sustainable Mobility Project in the Foz do Rio Itajaí Region

Abstract*

The Integrated Sustainable Mobility Project in the Foz do Rio Itajai Region (AMFRI) will achieve a total investment amount of 162 USD million, out of which 90 USD million will be IBRD financing and 30 USD million counterpart financing, the rest of the investment concessions from the Private Sector for electric buses and barges. This project would be a pioneer in Brazil for being designed and implemented by a consortium of 11 Municipalities (CIM-AMFRI)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve accessibility and mobility in an inclusive and low-emission manner in selected areas of the Foz do Rio Itajaí Region.

Key Details

Project Details

  • P178557

  • Active

  • Carlos Bellas Lamas , Georges Darido, Tais Fonseca De Medeiros

  • CIM - AMFRI (Foz do Rio Itajaí Region Consortium of Municipalities)

  • Brazil

  • June 27, 2022

  • (as of board presentation)

    April 12, 2024

  • N/A

  • US$ 200.00 million

  • Consorcio Intermunicipal Multifinalitário - AMFRI - PCU

  • Latin America and Caribbean

  • 2024

  • US$ 90.00 million

  • N/A

  • Substantial

  • November 30, 2031

  • Yes

  • BANK APPROVED

  • June 20, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 90.00
Borrower/Recipient 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 90.00
IDA Commitment N/A
IBRD + IDA Commitment 90.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 200.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 12, 2024 IBRD-96710 Loan Commitment 90,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-07-24
Financial Management Satisfactory 2025-07-24
Procurement Satisfactory 2025-07-24
Project Management Moderately Unsatisfactory 2025-07-24
Monitoring and Evaluation Moderately Satisfactory 2025-07-24
Overall Implementation Progress (IP) Moderately Satisfactory 2025-07-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.