Skip to Main Navigation

Sierra Leone Connectivity and Agricultural Market Infrastructure Project

Abstract*

The development objective of the Connectivity and Agricultural Market Infrastructure Project for Sierra Leone is to enhance climate-resilient transport connectivity and agricultural market access in selected areas of Sierra Leone. The project comprises of five components. The first component, resilient urban transport builds on Integrated and Resilient Urban Mobility Project (IRUMP) concepts and objectives to improve climate resilience and the green...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project objective is to provide climate resilient rural bridges and agricultural market infrastructure at selected locations toenhance connectivity and access to agricultural markets for rural communities.

Key Details

Project Details

  • P178683

  • Active

  • Tojoarofenitra Ramanankirahina , Adetunji Oredipe, Ajara Ceesay

  • Republic of Sierra Leone

  • Sierra Leone

  • July 22, 2023

  • (as of board presentation)

    May 29, 2024

  • September 11, 2024

  • US$ 41.00 million

  • Ministry of Transport and Aviation

  • Western and Central Africa

  • 2024

  • US$ 74.00 million

  • N/A

  • Substantial

  • December 31, 2029

  • Yes

  • BANK APPROVED

  • June 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 74.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 74.00
IBRD + IDA Commitment 74.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 41.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 29, 2024 IDA-E3340 Loan Commitment 74,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-07-25
Financial Management Satisfactory 2025-07-25
Monitoring and Evaluation Satisfactory 2025-07-25
Overall Implementation Progress (IP) Satisfactory 2025-07-25
Procurement Satisfactory 2025-07-25
Progress towards achievement of PDO Satisfactory 2025-07-25
Project Management Satisfactory 2025-07-25
Financial Management Satisfactory 2025-07-25
Monitoring and Evaluation Satisfactory 2025-07-25
Overall Implementation Progress (IP) Satisfactory 2025-07-25
Procurement Satisfactory 2025-07-25
Project Management Satisfactory 2025-07-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.