Local Governance and Community Resilience Project

Abstract*

The project intends to achieve the development objective by (i) strengthening the capacity of local authorities to deliver services to the population in a participatory manner; (ii) delivering key climate-resilient community infrastructure with a focus on small-scale infrastructure that can generate income to both the population and the local authorities in selected communes and (iii) support the reconciliation of conflicts through socio-economic...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project development objective is to: build state and citizen capacity for local service delivery, improve access to basic socio-economic climate adaptive infrastructure, and provide socio-economic support to the reintegration of ex-combatants.

Key Details

Project Details

  • P178699

  • Active

  • Abderrahim Fraiji , Eugenie Kiendrebeogo, Camilla Lindstrom

  • Central African Republic

  • Central African Republic

  • July 11, 2022

  • (as of board presentation)

    September 6, 2023

  • December 19, 2023

  • US$ 100.00 million

  • Ministry of Economy, Planning and International Cooperation

  • Western and Central Africa

  • 2024

  • US$ 90.00 million

  • N/A

  • Substantial

  • August 31, 2028

  • TBD

  • BANK APPROVED

  • December 19, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 90.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 90.00
IBRD + IDA Commitment 90.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 17, 2024 IDA-E2240 Loan Disb 153,972.48
Jan 25, 2024 IDA-E2240 Loan Disb 3,002,502.00
May 31, 2024 IDA-E2240 Loan Disb 603,072.56
Feb 6, 2024 IDA-E2240 Loan Disb 255,239.98
Sep 6, 2023 IDA-E2240 Loan Commitment 90,000,000.00
Dec 19, 2023 IDA-E2240 Loan Disb 566,906.70

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-12-19
Financial Management Moderately Satisfactory 2024-12-19
Progress towards achievement of PDO Moderately Satisfactory 2024-12-19
Procurement Satisfactory 2024-12-19
Project Management Satisfactory 2024-12-19
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased percentage of Community members reporting improved perceptions of inclusive and accountable local governance in a multi-dimensional survey instrumentValue0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Increased percentage of women reporting improved perceptions of inclusive and accountable local governanceValue0.000.000.00
    Date
    Comment
  • Of which youthValue0.000.000.00
    Date
    Comment
  • Community members reporting that the socio-economic investments reflect their needsValue0.000.0080.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women reporting that the socio-economic investments reflect their needsValue0.000.000.00
    Date
    Comment
  • Youth reporting that the socio-economic infrastructure reflect their needsValue0.000.000.00
    Date
    Comment
  • Female participants in village committees in the targeted prefecturesValue0.000.0040.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Civic registration services provided by local authorities in the targeted communitiesValue0.000.0030.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Direct beneficiaries in project areas with improved access to climate resilient infrastructureValue0.000.0068000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Former combatants that have received socio-economic support to reintegrate into their communitiesValue0.000.002000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of knowledge products developedValue0.000.005.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Ex-combatants who complete civic educationValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Small-scale infrastructures created (demarcation and water points)Value0.000.0060.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Implementation decrees, compendiums and vulgarization documents producedValue4.000.0015.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Beneficiaries involved in LIPWValue0.000.0022000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Community Groups established and trained in participatory methods.Value0.000.0022.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Community leaders (e.g. CSO leaders, local associations leaders, traditional chiefs etc.) trained on their rights and voice within local governanceValue0.000.00110.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Deconcentrated or decentralized staff trained on core functions using the new modulesValue0.000.00150.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women trainedValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Women involved in LIPWValue0.000.000.00
    Date
    Comment
  • Women in leadership positions in the community groups established and trained by the ProjectValue0.000.0040.00
    DateJanuary 15, 2024November 22, 2023August 31, 2028
    Comment
  • Regional treasury agencies (including Bangui) with a connection to Simba and reporting municipal financial dataValue1.000.004.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Mediation platforms trained by the projectValue0.000.0022.00
    DateApril 15, 2024November 22, 2023July 31, 2028
    Comment
  • Increase in revenues (local taxes and retroceded taxes from central government) mobilized by communesValue0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Ex-combatants who complete vocational trainingValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Disputes related to transhumant pastoralists mediated by structures created or supported by the project in areas where the project is implemented.Value0.000.0022.00
    DateApril 15, 2024November 22, 2023July 31, 2028
    Comment
  • Training modules on core decentralized or deconcentrated functions produced by the enhanced training programValue0.000.0010.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Local Development plans including community climate led diagnostics Value0.000.00100.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Respondents to the governance surveys who report an improved awareness of their role in the local governance and increased voice and agency.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women who report an improved awarenessValue0.000.000.00
    Date
    Comment
  • Climate resilient infrastructure built or rehabilitatedValue0.000.0066.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Communes with a rehabilitated an operational office (town hall, or public administration offices)Value0.000.0015.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Communes where a platform for receiving feed-back from community members on community infrastructure and local development plans have been establishedValue0.000.0022.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Reintegration kits distributed to ex-combatantsValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Communes with core planning documents approved and published (LDP, annual budget, annual investment plan)Value0.000.0075.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Grievances registered and addressed within the Projects grievance mechanismValue0.000.00100.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • AGRs establishedValue0.000.0020.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Grievances reported by women (and percentages of grievances addressed)Value0.000.000.00
    Date
    Comment
  • Respondents to the social cohesion survey that reports improvement in horizontal and vertical social cohesion in communes where theproject is implemented.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women that are part of AGRsValue0.000.000.00
    Date
    Comment
  • Women that reports improvement in vertical and social cohesion in communes where the Project is implementedValue0.000.000.00
    Date
    Comment
  • Ex-combatants expressing that they are accepted by their communitiesValue0.000.0080.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Community members that express acceptance of ex-combatantsValue0.000.0080.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Ex-combatants report an increase in household incomeValue0.000.0090.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Women reporting an increaseValue0.000.000.00
    Date
    Comment
  • Climate resilient socio-economic infrastructure rehabilitated and constructed.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment