Local Governance and Community Resilience Project

Abstract*

The development objective of the Local Governance and Community Resilience Project for Central African Republic is to build state and citizen capacity for local service delivery, improve access to basic socio-economic climate adaptive infrastructure, and provide socio-economic support to the reintegration of ex-combatants. The project comprises of five components. The first component, strengthening central systems underpinning decentralization and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project development objective is to: build state and citizen capacity for local service delivery, improve access to basic socio-economic climate adaptive infrastructure, and provide socio-economic support to the reintegration of ex-combatants.

Key Details

Project Details

  • P178699

  • Active

  • Abderrahim Fraiji , Eugenie Kiendrebeogo, Camilla Lindstrom

  • Central African Republic

  • Central African Republic

  • July 11, 2022

  • (as of board presentation)

    September 6, 2023

  • December 19, 2023

  • US$ 100.00 million

  • Ministry of Economy, Planning and International Cooperation

  • Western and Central Africa

  • 2024

  • US$ 90.00 million

  • N/A

  • December 19, 2023

  • August 31, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 90.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 90.00
IBRD + IDA Commitment 90.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 17, 2024 IDA-E2240 Loan Disb 153,972.48
Jan 25, 2024 IDA-E2240 Loan Disb 3,002,502.00
May 31, 2024 IDA-E2240 Loan Disb 603,072.56
Feb 6, 2024 IDA-E2240 Loan Disb 255,239.98
Sep 6, 2023 IDA-E2240 Loan Commitment 90,000,000.00
Dec 19, 2023 IDA-E2240 Loan Disb 566,906.70

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-12-19
Procurement Satisfactory 2024-12-19
Progress towards achievement of PDO Moderately Satisfactory 2024-12-19
Financial Management Moderately Satisfactory 2024-12-19
Monitoring and Evaluation Satisfactory 2024-12-19
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Increased percentage of women reporting improved perceptions of inclusive and accountable local governanceValue0.000.000.00
    Date
    Comment
  • Of which youthValue0.000.000.00
    Date
    Comment
  • Community members reporting that the socio-economic investments reflect their needsValue0.000.0080.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women reporting that the socio-economic investments reflect their needsValue0.000.000.00
    Date
    Comment
  • Youth reporting that the socio-economic infrastructure reflect their needsValue0.000.000.00
    Date
    Comment
  • Female participants in village committees in the targeted prefecturesValue0.000.0040.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Civic registration services provided by local authorities in the targeted communitiesValue0.000.0030.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Direct beneficiaries in project areas with improved access to climate resilient infrastructureValue0.000.0068000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Former combatants that have received socio-economic support to reintegrate into their communitiesValue0.000.002000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Increased percentage of Community members reporting improved perceptions of inclusive and accountable local governance in a multi-dimensional survey instrumentValue0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of knowledge products developedValue0.000.005.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Ex-combatants who complete civic educationValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Small-scale infrastructures created (demarcation and water points)Value0.000.0060.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Implementation decrees, compendiums and vulgarization documents producedValue4.000.0015.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Beneficiaries involved in LIPWValue0.000.0022000.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Community Groups established and trained in participatory methods.Value0.000.0022.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Community leaders (e.g. CSO leaders, local associations leaders, traditional chiefs etc.) trained on their rights and voice within local governanceValue0.000.00110.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Deconcentrated or decentralized staff trained on core functions using the new modulesValue0.000.00150.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women trainedValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Women involved in LIPWValue0.000.000.00
    Date
    Comment
  • Women in leadership positions in the community groups established and trained by the ProjectValue0.000.0040.00
    DateJanuary 15, 2024November 22, 2023August 31, 2028
    Comment
  • Regional treasury agencies (including Bangui) with a connection to Simba and reporting municipal financial dataValue1.000.004.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Mediation platforms trained by the projectValue0.000.0022.00
    DateApril 15, 2024November 22, 2023July 31, 2028
    Comment
  • Increase in revenues (local taxes and retroceded taxes from central government) mobilized by communesValue0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Ex-combatants who complete vocational trainingValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Disputes related to transhumant pastoralists mediated by structures created or supported by the project in areas where the project is implemented.Value0.000.0022.00
    DateApril 15, 2024November 22, 2023July 31, 2028
    Comment
  • Training modules on core decentralized or deconcentrated functions produced by the enhanced training programValue0.000.0010.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Local Development plans including community climate led diagnostics Value0.000.00100.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Respondents to the governance surveys who report an improved awareness of their role in the local governance and increased voice and agency.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women who report an improved awarenessValue0.000.000.00
    Date
    Comment
  • Climate resilient infrastructure built or rehabilitatedValue0.000.0066.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Communes with a rehabilitated an operational office (town hall, or public administration offices)Value0.000.0015.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Communes where a platform for receiving feed-back from community members on community infrastructure and local development plans have been establishedValue0.000.0022.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Reintegration kits distributed to ex-combatantsValue0.000.002000.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Communes with core planning documents approved and published (LDP, annual budget, annual investment plan)Value0.000.0075.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Grievances registered and addressed within the Projects grievance mechanismValue0.000.00100.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • AGRs establishedValue0.000.0020.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Grievances reported by women (and percentages of grievances addressed)Value0.000.000.00
    Date
    Comment
  • Respondents to the social cohesion survey that reports improvement in horizontal and vertical social cohesion in communes where theproject is implemented.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023August 31, 2028
    Comment
  • Women that are part of AGRsValue0.000.000.00
    Date
    Comment
  • Women that reports improvement in vertical and social cohesion in communes where the Project is implementedValue0.000.000.00
    Date
    Comment
  • Ex-combatants expressing that they are accepted by their communitiesValue0.000.0080.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Community members that express acceptance of ex-combatantsValue0.000.0080.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Ex-combatants report an increase in household incomeValue0.000.0090.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment
  • Women reporting an increaseValue0.000.000.00
    Date
    Comment
  • Climate resilient socio-economic infrastructure rehabilitated and constructed.Value0.000.0020.00
    DateApril 15, 2024November 22, 2023December 31, 2026
    Comment