Matenggeng Hydropower Pumped Storage Project

Abstract*

The proposed MPS project is part of the least-cost plan and is expected to be commissioned in 2030. The proposed project will be structured in the following three components:Component 1: Development of the Pumped Storage Hydropower Plant and 500 kV transmission lines in the Java-Bali System (Indicative estimate: USD 1,051 million – IBRD USD 791 million and PLN USD 260 million). This Component covers the development, construction, and commissioning...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to improve the power system peaking and storage capacity of the Java-Bali grid by developing the second large-scale pumped storage hydropower plant and strengthen PLN’s capacity for hydropower development and management.

Key Details

Project Details

  • P178779

  • Dropped

  • Nicolas Sans , Puguh Imanto, Maria Ayuso Olmedo

  • Government of Indonesia

  • Indonesia

  • March 16, 2023

  • (as of board presentation)

    N/A

  • N/A

  • US$ 1200.00 million

  • PT Perusahaan Listrik Negara (PLN)

  • East Asia and Pacific

  • 2025

  • US$ 826.00 million

  • N/A

  • High

  • N/A

  • Yes

  • CONCEPT REVIEW

  • July 10, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 300.00
International Bank for Reconstruction and Development 826.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 826.00
IDA Commitment N/A
IBRD + IDA Commitment 826.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1200.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.