Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 5.00 |
IDA Grant | 15.00 |
P178819
Active
Christopher Trimble , Manuel Berlengiero
Republic of Tajikistan
May 28, 2022
(as of board presentation)
January 12, 2023
May 11, 2023
US$ 20.00 million
Project Management Group for Energy Facilities Construction
2023
US$ 20.00 million
N/A
High
December 31, 2027
Yes
BANK APPROVED
May 8, 2024
Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 5.00 |
IDA Grant | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | 5.00 |
Total Project Cost** | 20.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 28, 2024 | IDA-E1460 | Loan Disb | 716,626.94 |
Apr 1, 2024 | IDA-E1460 | Loan Disb | 487,247.25 |
Apr 1, 2024 | IDA-E1460 | Loan Disb | 193,151.25 |
Mar 27, 2024 | IDA-E1460 | Loan Disb | 221,571.50 |
Jan 12, 2023 | IDA-E1460 | Loan Commitment | 15,000,000.00 |
Feb 2, 2024 | IDA-E1460 | Loan Disb | 110,728.75 |
Feb 2, 2024 | IDA-E1460 | Loan Disb | 794,271.94 |
Jun 30, 2023 | IDA-E1460 | Loan Disb | 1,000,000.00 |
Dec 7, 2023 | IDA-E1460 | Loan Disb | 606,657.00 |
Jul 25, 2024 | IDA-E1460 | Loan Disb | 588,461.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-05-26 |
Monitoring and Evaluation | Satisfactory | 2025-05-26 |
Procurement | Satisfactory | 2025-05-26 |
Project Management | Moderately Satisfactory | 2025-05-26 |
Financial Management | Moderately Satisfactory | 2025-05-26 |
Overall Implementation Progress (IP) | Satisfactory | 2025-05-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The Government adopts a macroeconomically sustainable and financially viable plan for completing construction of Rogun HPP Project | Value | No | No | Yes |
Date | October 31, 2022 | April 23, 2024 | December 31, 2023 | |
Comment |
Rogun HPP Project has functioning dam safety as well as environmental and social POEs | Value | No | Yes | Yes |
Date | October 31, 2022 | October 17, 2023 | February 28, 2023 | |
Comment |
The summary information on existing and future contracts and financing plan for completion of construction of Rogun HPP Project arepublicly disclosed | Value | No | Yes | Yes |
Date | October 31, 2022 | April 23, 2024 | March 31, 2023 | |
Comment |
PPAs are signed for sale of Rogun HPP Project’s electricity in the amount to make the financing plan viable | Value | No | No | Yes |
Date | October 31, 2022 | April 23, 2024 | December 31, 2023 | |
Comment |
The environmental and social instruments of Rogun HPP Project comply with the requirements of the World Bank’s Environmental and Social Framework | Value | No | Yes | Yes |
Date | October 31, 2022 | April 23, 2024 | February 28, 2024 | |
Comment |
Rogun HPP Project’s community benefit sharing program is launched | Value | No | No | Yes |
Date | October 31, 2022 | April 23, 2024 | April 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Rogun PMG is strengthened with project management, procurement, FM, and E&S experts | Value | No | Yes | Yes |
Date | October 31, 2022 | April 24, 2024 | February 1, 2023 | |
Comment |
Update of Rogun HPP Project implementation schedule is completed | Value | No | No | Yes |
Date | October 31, 2022 | April 23, 2024 | January 31, 2023 | |
Comment |
Dam safety POE, with composition and qualifications acceptable to the Bank, is hired | Value | No | Yes | Yes |
Date | October 31, 2022 | April 23, 2024 | January 31, 2023 | |
Comment |
E&S POE, with composition and qualifications acceptable to the Bank, is hired and retained | Value | No | Yes | Yes |
Date | October 31, 2022 | April 24, 2024 | January 31, 2023 | |
Comment |
Increase in the number of women taking on permanent jobs at Rogun PMG at technical and managerial levels | Value | 5.00 | 3.00 | 10.00 |
Date | October 17, 2023 | April 24, 2024 | December 31, 2024 | |
Comment |
Update of E&S instruments of Rogun HPP Project is completed | Value | No | No | Yes |
Date | October 31, 2022 | April 24, 2024 | December 31, 2024 | |
Comment |
Percentage of citizens who believe that the Project has established effective engagement processes | Value | To be established during 2022 survey | to be yet determined | At least 65 percent |
Date | March 31, 2023 | April 24, 2024 | December 31, 2026 | |
Comment |
Electricity market analysis is completed and the PPAs for sale of Rogun electricity are drafted | Value | No | No | Yes |
Date | October 31, 2022 | April 23, 2024 | April 30, 2023 | |
Comment |
Preparation of Rogun HPP Project community benefit sharing program is completed | Value | No | No | Yes |
Date | October 31, 2022 | April 24, 2024 | January 31, 2024 | |
Comment |