Skip to Main Navigation

Technical Assistance for Financing Framework for Rogun Hydropower Project

Abstract*

The development objectives of the Technical Assistance for Financing Framework for Rogun Hydropower Project for Tajikistan are to strengthen Rogun Hydropower Plant (HPP) Project’s financial and commercial frameworks, enhance its environmental and social sustainability, improve the transparency, and support establishment of Rogun HPP Project’s benefit sharing program. The project comprises of four components. The first component is development of a...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objectives are to strengthen Rogun HPP Project’s financial and commercial frameworks, enhance its environmental and social sustainability, improve the transparency, and support establishment of Rogun HPP Project’s benefit sharing program

Key Details

Project Details

  • P178819

  • Active

  • Christopher Trimble , Manuel Berlengiero

  • Republic of Tajikistan

  • Tajikistan

  • May 28, 2022

  • (as of board presentation)

    January 12, 2023

  • May 11, 2023

  • US$ 20.00 million

  • Project Management Group for Energy Facilities Construction

  • Europe and Central Asia

  • 2023

  • US$ 20.00 million

  • N/A

  • High

  • December 31, 2027

  • Yes

  • BANK APPROVED

  • May 8, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Asian Infrastructure Investment Bank 5.00
IDA Grant 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount 5.00
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 28, 2024 IDA-E1460 Loan Disb 716,626.94
Apr 1, 2024 IDA-E1460 Loan Disb 487,247.25
Apr 1, 2024 IDA-E1460 Loan Disb 193,151.25
Mar 27, 2024 IDA-E1460 Loan Disb 221,571.50
Jan 12, 2023 IDA-E1460 Loan Commitment 15,000,000.00
Feb 2, 2024 IDA-E1460 Loan Disb 110,728.75
Feb 2, 2024 IDA-E1460 Loan Disb 794,271.94
Jun 30, 2023 IDA-E1460 Loan Disb 1,000,000.00
Dec 7, 2023 IDA-E1460 Loan Disb 606,657.00
Jul 25, 2024 IDA-E1460 Loan Disb 588,461.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-05-26
Monitoring and Evaluation Satisfactory 2025-05-26
Procurement Satisfactory 2025-05-26
Project Management Moderately Satisfactory 2025-05-26
Financial Management Moderately Satisfactory 2025-05-26
Overall Implementation Progress (IP) Satisfactory 2025-05-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • The Government adopts a macroeconomically sustainable and financially viable plan for completing construction of Rogun HPP ProjectValueNoNoYes
    DateOctober 31, 2022April 23, 2024December 31, 2023
    Comment
  • Rogun HPP Project has functioning dam safety as well as environmental and social POEsValueNoYesYes
    DateOctober 31, 2022October 17, 2023February 28, 2023
    Comment
  • The summary information on existing and future contracts and financing plan for completion of construction of Rogun HPP Project arepublicly disclosedValueNoYesYes
    DateOctober 31, 2022April 23, 2024March 31, 2023
    Comment
  • PPAs are signed for sale of Rogun HPP Project’s electricity in the amount to make the financing plan viableValueNoNoYes
    DateOctober 31, 2022April 23, 2024December 31, 2023
    Comment
  • The environmental and social instruments of Rogun HPP Project comply with the requirements of the World Bank’s Environmental and Social FrameworkValueNoYesYes
    DateOctober 31, 2022April 23, 2024February 28, 2024
    Comment
  • Rogun HPP Project’s community benefit sharing program is launchedValueNoNoYes
    DateOctober 31, 2022April 23, 2024April 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Rogun PMG is strengthened with project management, procurement, FM, and E&S expertsValueNoYesYes
    DateOctober 31, 2022April 24, 2024February 1, 2023
    Comment
  • Update of Rogun HPP Project implementation schedule is completedValueNoNoYes
    DateOctober 31, 2022April 23, 2024January 31, 2023
    Comment
  • Dam safety POE, with composition and qualifications acceptable to the Bank, is hiredValueNoYesYes
    DateOctober 31, 2022April 23, 2024January 31, 2023
    Comment
  • E&S POE, with composition and qualifications acceptable to the Bank, is hired and retainedValueNoYesYes
    DateOctober 31, 2022April 24, 2024January 31, 2023
    Comment
  • Increase in the number of women taking on permanent jobs at Rogun PMG at technical and managerial levelsValue5.003.0010.00
    DateOctober 17, 2023April 24, 2024December 31, 2024
    Comment
  • Update of E&S instruments of Rogun HPP Project is completedValueNoNoYes
    DateOctober 31, 2022April 24, 2024December 31, 2024
    Comment
  • Percentage of citizens who believe that the Project has established effective engagement processesValueTo be established during 2022 surveyto be yet determinedAt least 65 percent
    DateMarch 31, 2023April 24, 2024December 31, 2026
    Comment
  • Electricity market analysis is completed and the PPAs for sale of Rogun electricity are draftedValueNoNoYes
    DateOctober 31, 2022April 23, 2024April 30, 2023
    Comment
  • Preparation of Rogun HPP Project community benefit sharing program is completedValueNoNoYes
    DateOctober 31, 2022April 24, 2024January 31, 2024
    Comment