Bolivia Resilient Water Management for Community and Household Irrigation Project

Abstract*

The Project will support the implementation of the first phase of the Government of Bolivia's Climate Smart and Resilient Program (Programa Lucho por una Bolivia Climaticamente Inteligente y Resiliente, Fase 1), which is a comprehensive rural development program, covering actions from water conservation, irrigation and risk management investments to information, knowledge management and water governance. It will have a strong focus on adaptation strategies...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve integrated water resources management in selected basins and increase the resilience to climate variability of vulnerable rural families in selected micro basins.

Key Details

Project Details

  • P178861

  • Active

  • Luis Alvestegui Justiniano

  • Plurinational State of Bolivia

  • Bolivia

  • November 13, 2022

  • (as of board presentation)

    February 20, 2024

  • N/A

  • US$ 173.40 million

  • Viceministerio de Recursos Hidricos y Riego (VRHyR),Ministerio de Medio Ambiente y Agua (MMAyA)

  • Latin America and Caribbean

  • 2024

  • US$ 150.00 million

  • N/A

  • May 25, 2023

  • January 30, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 150.00
Borrower/Recipient 21.49

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 173.40

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 20, 2024 IBRD-96430 Loan Commitment 150,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-11-25
Overall Implementation Progress (IP) Satisfactory 2024-11-25
Project Management Satisfactory 2024-11-25
Progress towards achievement of PDO Satisfactory 2024-11-25
Financial Management Satisfactory 2024-11-25
Monitoring and Evaluation Satisfactory 2024-11-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.