Ethiopia Electrification Program Additional Financing

Development Objective

The development objective is to increase access to electricity in Ethiopia and to enhance institutional capacity for planning and implementation of the Government’s electrification program.

Key Details

Project Details

  • P178895

  • Active

  • Maria Arango Campo , Lara Born

  • Ministry of Finance and Economic Cooperation

  • Ethiopia

  • June 17, 2022

  • (as of board presentation)

    March 31, 2023

  • N/A

  • US$ 250.00 million

  • Ethiopian Electric Utility,Ministry of Water and Energy

  • Eastern and Southern Africa

  • 2023

  • US$ 250.00 million

  • N/A

  • February 11, 2024

  • July 7, 2026

  • No

  • BANK APPROVED

  • P160395

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 250.00
Local Beneficiaries 70.30
Borrower/Recipient 93.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 250.00
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 250.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people provided with on-grid electricity servicesValue0.003266375.009790040.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Number of people provided with off-grid electricity servicesValue0.0016825.009900.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Improved planning and implementation capacity of the electricity sectorValueNoNoYes
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Households provided with electricity through mini-gridsValue0.003365.001980.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Improved cost-effectiveness of ProgramValueNoNoYes
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Cumulative capacity of renewable energy installed through mini-grid projects under the ProgramValue0.003.450.54
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Women in STEM: Percentage women’s employment at EEUValue20.0023.6530.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Cumulative number of non-residential grid electricity connections made under the ProgramValue0.0038286.0097900.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • Number of EEU and MoWIE staff trained under the ProgramValue0.00226.00400.00
    DateMarch 1, 2018June 17, 2022July 7, 2026
    Comment
  • Households connected to the grid under the Program that are female-headedValue0.0021.0024.00
    DateMarch 1, 2018October 25, 2022July 7, 2026
    Comment
  • ?Cumulative number of residential grid electricity connections under the Program (Number)Value925801.00925801.001958008.00
    DateFebruary 16, 2023February 16, 2023July 7, 2026
    Comment
  • Number of AMI connected distribution transformersValue0.000.0030000.00
    DateFebruary 17, 2023February 23, 2023July 7, 2026
    Comment
  • Number of AMI connected industrial and commercial customerValue0.000.0030000.00
    DateFebruary 17, 2023February 23, 2023July 7, 2026
    Comment