China Green Agricultural and Rural Revitalization Program for Results (Hubei and Hunan)

Abstract*

The development objective of the Green Agricultural and Rural Revitalization Program (RRP) for Results (Hubei and Hunan) for China is to enhance adoption of environmentally sustainable agricultural and rural infrastructure development practices in selected areas of Hubei and Hunan. The four result areas (RAs) are chosen to address the main challenges facing agriculture and rural infrastructure development under the RRP: (a) filling the remaining gaps...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To enhance adoption of environmentally-sustainable agricultural and rural infrastructure development practices in selected areas of Hubei and Hunan.

Key Details

Project Details

  • P178907

  • Active

  • Wendao Cao

  • People's Republic of China

  • China

  • June 28, 2022

  • (as of board presentation)

    April 28, 2023

  • N/A

  • US$ 350.00 million

  • Hubei Provincial Rural Revitalization Administration,National Rural Revitalization Administration,Hunan Provincial Department of Agriculture and Rural Affairs

  • East Asia and Pacific

  • 2023

  • US$ 345.00 million

  • N/A

  • April 17, 2024

  • June 29, 2029

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 4100.00
International Bank for Reconstruction and Development 345.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 345.00
IDA Commitment N/A
IBRD + IDA Commitment 345.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 350.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 28, 2023 IBRD-95000 Loan Commitment 170,000,000.00
Apr 28, 2023 IBRD-95140 Loan Commitment 5,000,000.00
Apr 28, 2023 IBRD-95010 Loan Commitment 170,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-10-29
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-29
Monitoring and Evaluation Satisfactory 2024-10-29

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in pollutant loads from agricultural production systems and rural domestic wastewater treatment facilities (COD and NH3-N) achieved in the Program Counties.Value0.000.00217166.00
    DateDecember 30, 2022April 17, 2024June 29, 2029
    Comment
  • COD (from livestock manure, aquaculture ponds, and demonstration village wastewater treatment)Value0.000.00211188.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • NH3N (from crop, livestock manure, aquaculture ponds, and demonstration village wastewater treatment)Value0.000.005977.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Greenhouse gas (GHG) emissions reduction achieved in the Program Counties (Metric tons/year CO2 equivalent).Value0.000.001987602.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Beneficiaries reached by assets or public services in the Program Counties (disaggregated by gender).Value0.000.007150814.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • FemaleValue0.000.00697407.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Spatial Integrated Village Development Plans (IVDPs) approved by the relevant authorities in the Program Counties.Value0.000.00413.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Quantity of chemical fertilizers reduced due to the adoption of green technologies and sustainable practices in selected crop production systems in the Program Counties.Value0.000.00116537.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Quantity of crop straw returned to the soil in farmlands in the Program Counties.Value5964305.000.006362050.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Counties implementing the approved guidelines for wastewater and solid waste management in rural villages in the Program Counties.Value0.000.0023.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Quantity of organic fertilizer used in the Program Counties.Value0.000.00929970.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Number of Program Counties that have adopted the IT-based platform for mapping and M&E of rural infrastructure and public services.Value0.000.0023.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Regulations, technical guidelines, and standards on treatment of aquaculture tail water issued by provincial authorities and implemented by the Program Counties.Value0.000.0010.00
    DateOctober 3, 2022April 17, 2024June 29, 2029
    Comment
  • Beneficiaries trained in the operations and maintenance (O&M) of rural wastewater and solid waste management systems in the ProgramCounties.Value0.000.0020191.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Area under crop production using formula fertilizer in the Program Counties.Value0.000.00111592.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Number of agro-products certified and/or registered in the Program Counties as either green, organic, or GI using the approved provincial regulations, standards and guidelines.Value0.000.00357.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Area of large-scale aquaculture farms (ponds) with tail water treatment systems in the Program Counties (Hubei only)Value0.000.0010938.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • FemaleValue0.000.003120.00
    Date
    Comment
  • Area under fertigation in the Program Counties.Value0.000.0010059.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Regulations, technical guidelines, and standards on degraded farmland treatment and protection issued by provincial authorities andimplemented by the Program Counties.Value0.000.0013.00
    DateOctober 3, 2022April 17, 2024June 29, 2029
    Comment
  • Demonstration villages in Program Counties with newly-constructed or rehabilitated climate-resilient wastewater treatment facilities and solid waste collection, sorting and transfer systems.Value0.000.00108.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Area under green manure in the Program Counties.Value0.000.0074608.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Area of agricultural farmland polluted with heavy metals that is treated and protected in the Program Counties (Hunan only).Value0.000.007989.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Rural domestic wastewater facilities in demonstration villages in the Program Counties meeting provincial effluent discharge standards.Value37.000.0070.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Beneficiaries in the Program Counties who have been trained in green agricultural technologies and practices (e.g., farmers, input suppliers, enterprises, extension staff), disaggregated by gender.Value0.000.0039521.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Newly created and upgraded jobs held by women in the transformation of agricultural value chain and in the rural waste management and environmental rehabilitation in the Program Counties.Value0.000.0045.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • FemaleValue0.000.006197.00
    Date
    Comment
  • Beneficiaries in the Program Counties who have adopted green agricultural technologies and practices (farmers, input suppliers, enterprises, extension staff), disaggregated by gender.Value0.000.0070.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • FemaleValue0.000.0030.00
    Date
    Comment
  • Quantity of livestock and poultry manure treated and recycled in the Program Counties.Value0.000.006178327.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Manure treated by large farms in the Program Counties.Value0.000.002440398.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Manure treated at centralized and small-scale manure treatment facilities constructed to cater for small and medium scale farms in the Program Counties.Value0.000.003737929.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment
  • Centralized manure treatment facilities constructed to cater for small- and medium-scale farms in the Program Counties.Value0.000.0059.00
    DateJanuary 18, 2023April 17, 2024June 29, 2029
    Comment