Financier | Commitments |
---|---|
Borrower/Recipient | 3.50 |
IDA Grant | 145.00 |
P178954
Active
Ivaylo Kolev , Lillian Muhebwa
Republic of Malawi
September 9, 2022
(as of board presentation)
March 23, 2023
June 6, 2023
US$ 127.00 million
Blantyre Water Board
2023
US$ 145.00 million
N/A
Substantial
March 31, 2029
Yes
BANK APPROVED
December 19, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 3.50 |
IDA Grant | 145.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 145.00 |
IBRD + IDA Commitment | 145.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 127.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 9, 2024 | IDA-E1590 | Loan Disb | 3,646,620.00 |
Aug 12, 2024 | IDA-E1590 | Loan Disb | 234,706.62 |
Apr 2, 2024 | IDA-E1590 | Loan Disb | 234,160.03 |
Jun 25, 2024 | IDA-E1590 | Loan Disb | 1,229,267.00 |
May 21, 2024 | IDA-E1590 | Loan Disb | 320,820.00 |
Jun 29, 2023 | IDA-E1590 | Loan Disb | 3,000,000.00 |
Feb 15, 2024 | IDA-E1590 | Loan Disb | 413,952.75 |
Mar 23, 2023 | IDA-E1590 | Loan Commitment | 145,000,000.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Moderately Satisfactory | 2025-05-26 |
Procurement | Moderately Satisfactory | 2025-05-26 |
Progress towards achievement of PDO | Satisfactory | 2025-05-26 |
Project Management | Satisfactory | 2025-05-26 |
Financial Management | Satisfactory | 2025-05-26 |
Monitoring and Evaluation | Satisfactory | 2025-05-26 |
Overall Implementation Progress (IP) | Satisfactory | 2025-05-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to improved water sources | Value | 0.00 | 0.00 | 330000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
People provided with access to improved sanitation services | Value | 0.00 | 0.00 | 100000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Non-Revenue Water for Blantyre Water System | Value | 53.00 | 53.00 | 35.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Working ratio for BWB | Value | 1.25 | 1.25 | 0.90 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of water supply pipes replaced, upgraded and extended under the project | Value | 0.00 | 0.00 | 332.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Length of sewerage network upgraded, rehabilitated and extended under the project | Value | 0.00 | 0.00 | 50.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Reduced physical losses in water-stressed areas as a result of project interventions | Value | 0.00 | 0.00 | 1000000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Number of connections receiving improved water supply as a result of project interventions | Value | 0.00 | 0.00 | 55000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Sewerage connections benefiting from improved sanitation services as a result of project interventions | Value | 0.00 | 0.00 | 15300.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Staff per 1000 connections | Value | 12.00 | 12.00 | 8.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Percentage of staff in decision-making roles (supervisory or managerial) who are female | Value | 10.00 | 10.00 | 30.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Of which new domestic connections | Value | 0.00 | 0.00 | 34000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Number of public sanitation facilities constructed under the project | Value | 0.00 | 0.00 | 20.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Customer satisfaction index | Value | 44.00 | 44.00 | 70.00 |
Date | November 17, 2022 | December 15, 2023 | April 28, 2028 | |
Comment |
Number of businesses with improved water supply due to the project interventions | Value | 0.00 | 0.00 | 1000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Volume of potable water treated as a result of project interventions | Value | 800000.00 | 800000.00 | 2500000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Volume of wastewater treated with demonstrated methane emissions reduction | Value | 0.00 | 0.00 | 3500000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Approved ISO certification | Value | No | No | Yes |
Date | November 17, 2022 | December 15, 2023 | April 28, 2028 | |
Comment |
Energy consumption per cubic meter billed | Value | 6.00 | 6.00 | 4.00 |
Date | December 1, 2022 | December 15, 2023 | September 29, 2028 | |
Comment |
Households receiving safely managed refuse collection services as a result of project interventions | Value | 0.00 | 0.00 | 80000.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
Utility Maturity Level | Value | 3.10 | 3.10 | 4.50 |
Date | November 22, 2022 | December 15, 2023 | November 30, 2027 | |
Comment |
Volume of compost produced | Value | 360.00 | 360.00 | 720.00 |
Date | October 17, 2022 | December 15, 2023 | October 31, 2028 | |
Comment |
People engaged (owning a business or employed) in waste collection and recycling as an income generating activity as a result of project interventions | Value | 0.00 | 0.00 | 250.00 |
Date | December 1, 2022 | December 15, 2023 | September 30, 2028 | |
Comment |
Proportion of sewer blockage complaints resolved within 3 days of being recorded in the database | Value | 0.00 | 0.00 | 80.00 |
Date | January 23, 2023 | December 15, 2023 | March 31, 2028 | |
Comment |