Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 363.00 |
Borrower/Recipient | 781.91 |
P179039
Active
Kristoffer Welsien , Mariappa Kullappa
India
September 26, 2022
(as of board presentation)
March 28, 2023
August 29, 2023
US$ 1055.20 million
Rural Development and Panchayat Department, Government of Karnataka,Rural Drinking Water and Sanitation Department, Government of Karnataka
2023
US$ 363.00 million
N/A
Not Applicable
June 1, 2028
No
BANK APPROVED
February 28, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 363.00 |
Borrower/Recipient | 781.91 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 363.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 363.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1055.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 28, 2024 | IBRD-94960 | Loan Disb | 26,473,920.00 |
Mar 15, 2024 | IBRD-94960 | Int Charges | 99,346.39 |
Mar 15, 2024 | IBRD-94960 | Int Charges | 450,874.12 |
Mar 15, 2024 | IBRD-94960 | Int Charges | 28,495.77 |
Aug 29, 2023 | IBRD-94960 | Loan Disb | 907,500.00 |
Aug 29, 2023 | IBRD-94960 | Fee Charges | 907,500.00 |
Mar 28, 2024 | IBRD-94960 | Loan Disb | 34,213,120.00 |
Mar 28, 2023 | IBRD-94960 | Loan Commitment | 363,000,000.00 |
Mar 15, 2024 | IBRD-94960 | Int Charges | 2,549.21 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2025-03-12 |
Progress towards achievement of PDO | Satisfactory | 2025-03-12 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-12 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Tanks rejuvenated in water scarce select districts | Value | 0.00 | 0.00 | 500.00 |
Date | September 9, 2022 | February 29, 2024 | February 28, 2028 | |
Comment |
Functional Household Tap Connections Installed | Value | 5584665.00 | 6012329.00 | 7584665.00 |
Date | September 9, 2022 | February 19, 2024 | February 29, 2028 | |
Comment |
Gram Panchayats with sustainably functioning water service | Value | 0.00 | 0.00 | 5000.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Gram Panchayats with water tariff collection rate above 90 percent | Value | 0.00 | 0.00 | 3500.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Sector M&E system enhanced | Value | No | No | Yes |
Date | September 9, 2022 | February 29, 2024 | June 1, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of women trained as plumbers who are certified and employed as technicians | Value | 0.00 | 0.00 | 20.00 |
Date | September 9, 2022 | February 29, 2024 | February 28, 2028 | |
Comment |
Centre of Excellence for Water and Sanitation Established and Operational | Value | No | No | Yes |
Date | April 30, 2023 | February 29, 2024 | February 28, 2027 | |
Comment |
People living in rural areas provided with access to safely managed drinking water | Value | 27923325.00 | 30061645.00 | 37923325.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Operationalize energy efficiency at MVSs | Value | No | No | Yes |
Date | September 9, 2022 | February 29, 2024 | February 26, 2027 | |
Comment |
Development and implementation of behavior change communication campaign | Value | No | No | Yes |
Date | September 9, 2022 | February 29, 2024 | January 1, 2024 | |
Comment |
Gram Panchayats adhering to enhanced water quality testing, monitoring and public dissemination criteria | Value | 0.00 | 0.00 | 5000.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Tanks meeting O&M sustainability criteria | Value | 0.00 | 0.00 | 500.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Field Level Leadership Master Trainers | Value | 0.00 | 52.00 | 100.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Complaints received, categorized, and resolved | Value | 0.00 | 36.00 | 80.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Water Policy Implementation Roadmap Developed | Value | No | Yes | Yes |
Date | September 9, 2022 | January 31, 2024 | February 29, 2028 | |
Comment |
Gram Panchayats with 24/7 service delivery | Value | 0.00 | 0.00 | 500.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Staff trained on solar water pumping | Value | 0.00 | 50.00 | 150.00 |
Date | March 1, 2023 | February 29, 2024 | February 28, 2028 | |
Comment |
O&M Policy notified in official gazette | Value | No | No | Yes |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Female plumbers educated | Value | 0.00 | 0.00 | 3000.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |
Supply and installation of incinerators for village menstrual hygiene management | Value | 0.00 | 0.00 | 2000.00 |
Date | September 9, 2022 | February 29, 2024 | February 29, 2028 | |
Comment |