Skip to Main Navigation

Tamil Nadu Climate Resilient Urban Development Program

Abstract*

The TA will have two subcomponents each to be implemented through the DMA and the TNUIFSL. The main activities will include (a) Program management and independent verification agency (IVA); (b) assessment of ULBs’ credit rating and exploring credit enhancement mechanism for municipal bonds; (c) communications, stakeholder, and WSS customers’ engagement at the ULBs; (d) training and capacity building for urban sector staff and ULB councilors on urban...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen urban management and improve access to efficient and climate resilient urban water and sanitation services in participating ULBs in Tamil Nadu

Key Details

Project Details

  • P179189

  • Active

  • Raghu Kesavan , Mathews Mullackal

  • India

  • India

  • December 8, 2022

  • (as of board presentation)

    December 21, 2023

  • April 22, 2024

  • US$ 300.00 million

  • Tamil Nadu Urban Infrastructure Financial Services Limited,Tamil Nadu Municipal Administration & Water Supply Department

  • South Asia

  • 2024

  • US$ 300.00 million

  • N/A

  • June 5, 2023

  • December 31, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00
Borrower/Recipient 540.37

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 22, 2024 IBRD-96250 Loan Disb 730,276.90
Dec 21, 2023 IBRD-96250 Loan Commitment 300,000,000.00
Apr 22, 2024 IBRD-96250 Fee Charges 730,276.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-09-20
Monitoring and Evaluation Satisfactory 2024-09-20
Overall Implementation Progress (IP) Satisfactory 2024-09-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework