Kazakhstan Digital Acceleration for an Inclusive Economy (DARE) Project

Abstract*

The largest landlocked country in the world located at the crossroads of Europe and Asia, Kazakhstan, is a resource-rich, upper-middle-income economy that – prior to the Coronavirus (COVID-19) pandemic – demonstrated robust economic growth and poverty reduction but remained largely dependent on its natural resources and vulnerable to climate change. Despite being a landlocked country, Kazakhstan has multiple international gateways, ensuring sufficient...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide access to high-quality and climate resilient broadband infrastructure in selected unserved and underserved areas of Kazakhstan.

Key Details

Project Details

  • P179204

  • Active

  • Natalija Gelvanovska-Garcia , Mikhail Bunchuk

  • Republic of Kazakhstan

  • Kazakhstan

  • October 31, 2023

  • (as of board presentation)

    February 22, 2024

  • N/A

  • US$ 100.00 million

  • Republican State Institution Telecommunications Committee of MDDIAI

  • Europe and Central Asia

  • 2024

  • US$ 92.43 million

  • N/A

  • April 12, 2023

  • December 31, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 92.43
Borrower/Recipient 0.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 92.43
IDA Commitment N/A
IBRD + IDA Commitment 92.43
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 22, 2024 IBRD-96490 Loan Commitment 92,430,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2024-10-16
Progress towards achievement of PDO Satisfactory 2024-10-16
Project Management Satisfactory 2024-10-16
Financial Management Satisfactory 2024-10-16
Monitoring and Evaluation Satisfactory 2024-10-16
Procurement Satisfactory 2024-10-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.